Jan 27 (Reuters) - J K Cement Ltd JKCE.NS :
* J.K.Cement Ltd.- stoppage of clinker/cement production at J.K.Cement works,
muddapur
* J.K.Cement Ltd.- actual loss is being assessed by the experts and necessary
insurance claim is being lodged
* J.K.Cement Ltd.- production and despatch is being resumed at the earliest
after taking out debris from clinker silo top.
* J.K.Cement Ltd.- cement available in depot(s) will serve the market.
* J.K.Cement Ltd.- restoration of clinker silo is expected to take six months
time; the actual loss is being assessed by the experts
* J.K.Cement- alternate arrangement for operation of kiln being initiated which
is expected to normalise clinker, cement production within 15 days from unit