Jan 5 (Reuters) - Jaguar Mining Inc JAG.TO :
* Sees announce successful recommissioning of mill #3 at its
turmalina gold mine in minas gerais, brazil
* Jaguar mining inc- mill #3 at turmalina gold minehas an
estimated installed capacity of 1,600 tonnes per day or 580,000
tonnes per year
* Jaguar mining inc- turmalina is expected to process
533,000 tonnes of ore in 2017
* Jaguar mining inc- currently mill #1 and mill #2 at
turmalina have been taken off-line for maintenance and will be
kept on standby mode
* Jaguar mining inc- expect that increase in process tonnage
and lower operating costs for mill #3 will positively impact
turmalina's unitary costs
Source text for Eikon: urn:newsml:reuters.com:*:nCNWHG688a
Further company coverage: JAG.TO
((Bangalore.newsroom@thomsonreuters.com;))