Jan 5 (Reuters) - Jaguar Mining Inc JAG.TO -
* Jaguar Mining Inc says announces successful
recommissioning of mill no.3 at its Turmalina Gold Mine in Minas
Gerais, Brazil
* Jaguar Mining Inc - Mill no.3 at Turmalina Gold Minehas an
estimated installed capacity of 1,600 tonnes per day or 580,000
tonnes per year
* Jaguar Mining Inc - Turmalina is expected to process
533,000 tonnes of ore in 2017
* Jaguar Mining Inc - Currently mill no.1 and mill no.2 at
Turmalina have been taken off-line for maintenance and will be
kept on standby mode
* Jaguar Mining Inc - Expect that increase in process
tonnage and lower operating costs for mill no.3 will positively
impact Turmalina's unitary costs
Source text for Eikon: ID:nPrejMqtra
Further company coverage: JAG.TO
((Bangalore.newsroom@thomsonreuters.com;))