Aug 19 (Reuters) - Kenon Holdings Ltd KEN.N :
* KENON'S SUBSIDIARY OPC ENERGY LTD. ANNOUNCES COMMENCEMENT
OF
CONSTRUCTION OF CPV GROUP WIND PROJECT
* KENON HOLDINGS LTD - OPC FURTHER ANNOUNCED THAT PROJECT'S
OVERALL CONSTRUCTION COST IS ESTIMATED AT APPROXIMATELY $365
MILLION
* KENON HOLDINGS - OPC DISCLOSED PROJECT ENTITIES ENTERED
INTO
PROJECT FINANCING AGREEMENT WITH INTERNATIONAL FINANCING
ENTITIES
* KENON HOLDINGS LTD - TOTAL AMOUNT OF AVAILABLE CREDIT
FACILITIES
AVAILABLE UNDER FINANCING AGREEMENT IS $274 MILLION
* KENON HOLDINGS LTD - OPC PROVIDED AN INTEREST BEARING
SHAREHOLDER LOAN TO PROJECT OF UP TO APPROXIMATELY $100 MILLION
Source text for Eikon: ID:n0001178913-24-002675
Further company coverage: KEN.N
((Reuters.Briefs@thomsonreuters.com;))