Picture of Lucara Diamond logo

LUC Lucara Diamond News Story

0.000.00%
ca flag iconLast trade - 00:00
Basic MaterialsAdventurousSmall CapNeutral

REG - Lucara Diamond Corp - LUCARA ANNOUNCES YEAR END 2023 RESULTS

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20240221:nRSU8995Da&default-theme=true

RNS Number : 8995D  Lucara Diamond Corp  21 February 2024

February 20, 2024

 

 

NEWS RELEASE

 

LUCARA ANNOUNCES YEAR END 2023 RESULTS; CONTINUED DEVELOPMENT OF THE
UNDERGROUND PROJECT

 

VANCOUVER, February 20, 2024 /CNW/ (LUC - TSX, LUC - BSE, LUC - Nasdaq
Stockholm)

 

Lucara Diamond Corp. ("Lucara" or the "Company") today reports its results for
the year and quarter ended December 31, 2023. All amounts are in U.S. dollars
unless otherwise noted.

FISCAL 2023 HIGHLIGHTS

·      The recovery of a 1,080 carat Type IIA white gem quality diamond
in August 2023, followed by a recovery of a 692 carat Type IIA diamond later
in the month. The fourth +1000 carat stone recovered from the Karowe Mine.

·      The Karowe Mine recorded record plant throughput of 2.8 million
tonnes milled for the year.

·      In January 2024, the successful execution of an amended project
financing debt package of $220 million to amend the repayment profile in line
with the rebase schedule released in July 2023 for the Karowe Underground
Project ("UGP").

·      On February 18, 2024, the Company announced the signing of a new
definitive sales agreement ("NDSA") with HB Trading BV ("HB") in respect of
all qualifying diamonds produced in excess of 10.8 carats in size from the
Karowe Mine.

·      Total revenue of $177.4 million for 2023, in line with revised
guidance.

·      Cash flow generated from operating activities of $63.4 million
for 2023.

·      2023 operating cash cost of $28.75 per tonne of ore
processed((1)).

·      Investment of $101.3 million in the Karowe UGP in 2023.
Significant sinking progress was made in both the production and the
ventilation shafts during the second half of 2023.

William Lamb, President & CEO commented: "2023 was a challenging year for
Lucara. Although mining activities in the open pit continued to show ongoing
sustainable improvements, including record production through the mill, the
development on the UGP experienced delays in the early part of the year.
Positive progress was made in the sinking of both the production and the
ventilation shafts resulting in both shafts starting lateral development at
the 670 level at the end of the year. The Company has dedicated significant
effort and resources to focus on the UGP as this project represents a very
exciting and valuable future for Lucara.

 

The diamond market in general remains a volatile environment with market
challenges coming from multiple areas. Lucara remains well positioned to meet
these market challenges head on due to its unique high value production mix
and its ability to provide provenance for its diamonds through its
well-defined sales channels. Our sales strategy which focuses on gaining
access to the upstream value chain from polished diamonds is well aligned to
the strategies of the Government of the Republic of Botswana. The Company aims
to continue working toward long-term sustainable business practices to provide
value for all our stakeholders."

REVIEW FOR THE YEAR ENDED DECEMBER 31, 2023

·      Operational highlights from the Karowe Mine for 2023 included:

o Ore and waste mined of 2.7 million tonnes ("Mt") (2022: 3.3Mt) and 3.1
million tonnes (2022: 1.5Mt), respectively.

o 2.8 million tonnes (2022: 2.8Mt) of ore processed.

o A total of 395,134 carats recovered, including 18,509 carats from the
processing of historic recovery tailings, (2022: 335,769 carats) at a
recovered grade of 13.2 carats per hundred tonnes ("cpht") of direct milled
ore (2022: 12.1 cpht).

§ A total of 602 Specials (stones larger than 10.8 carats in size) were
recovered, with 22 diamonds greater than 100 carats including five diamonds
greater than 300 carats.

§ Recovered Specials equated to 5.3% of the total recovered carats from ore
processed during 2023 (2022 - 7.2%).

o The Karowe Mine has operated continuously for over three years without a
lost time injury.

·      Financial highlights for 2023 included:

o Revenues of $177.4 million (2022: $212.9 million) achieved despite a weaker
rough diamond market. Fourth quarter pricing stabilized in smaller goods and
increases of 5% were observed compared to the third quarter of 2023, albeit
approximately 19% below prices observed in the fourth quarter of 2022. Revenue
reflects the weighting of Lucara's revenue towards larger goods where pricing
was observed to be more stable. The performance further reflects the increased
volume of material processed from the North and Centre lobes in the first half
of the year. During 2023, 26% of the carats processed were recovered from the
Centre Lobe, 3% from the North Lobe and 71% were recovered from South Lobe ore
(2022: 100% South Lobe ore). In comparison to the revenue earned in 2022,
current year revenues reflected a more diverse product mix with a return to
Centre and North Lobe processing during the year.

o Operating margins of 56% were achieved (2022: 63%). A strong operating
margin continues to be achieved through cost reduction initiatives assisted by
a strong U.S. dollar.

o Adjusted EBITDA((1)) was $54.4 million (2022: $86.7 million), with the
decrease attributable to the change in revenue.

o Net loss was $20.2 million (2022: net income of $40.4 million), resulting in
a loss per share of $0.04 (2022: earnings of $0.09). The change to a net loss
is due to the decrease in revenue, an impairment of intangible assets, and a
significant non-cash deferred tax expense as the investment in the underground
expansion project continues.

o The Company identified an impairment indicator for the Company's Clara sales
platform and completed an impairment test based on the fair value less cost of
disposal expected to be derived from the platform. An impairment was
recognized on the intangible asset by $11.2 million in Q4 2023.

o Cash flow from operating activities was $63.4 million (2022: $96.2 million).

 

·      During 2023, the Company invested $101.3 million into the Karowe
UGP, including capitalized borrowing costs:

o Shaft sinking, lateral development and grouting programs were the focus in
both the ventilation and production shafts in Q4 2023. At the end of 2023, the
production and ventilation shafts were both at 348 metres below collar or 666
metres above sea level ("masl") and the process of establishing the first
shaft stations and lateral connection between the two shafts (670 level) had
commenced.

o

During Q4 2023, the ventilation shaft sank 76 metres, the 718 slinging cubby
was completed, the 670-level station catwalk was established and the lateral
station development commenced. Total lateral development in Q4 2023 was 97
metres. During the quarter, development equipment, including a Kubota, a
Sandvik DD321 boom jumbo drill and a Caterpillar R1300G 7-tonne load, haul,
dump unit were mobilized at the 670-level for lateral development mining.
Sinking and lateral development was in the Thlabala mudstones in dry
conditions.

o Production shaft activities included sinking a total of 114 metres and
establishing the 670-level station catwalk and initiating lateral development.
A total of 30 metres of lateral development was completed.

o Commissioning of the temporary bulk air coolers at each shaft was completed
and construction of the permanent bulk air coolers at the production shaft
continued.

o Detailed engineering and fabrication of the permanent men and materials
winder commenced during the quarter, representing the last major component for
the permanent winders.

 

·      Cash position and liquidity at December 31, 2023:

o Cash and cash equivalents of $13.3 million.

o Working capital deficit (current assets less current liabilities) of $16.6
million.

o Cost overrun facility ("COF") of $18.6 million.

o $90.0 million drawn on the $170.0 million Project Loan ("Project Loan") for
the Karowe UGP.

o $35.0 million drawn on the $50.0 million working capital facility ("WCF").

·      On January 9, 2024, the Company announced that it had signed
amended documentation in relation to the senior secured project financing debt
package of $220.0 million (the "Facilities") executed in July 2021 (the
"Rebase Amendments"). The project facility portion had been increased from
$170.0 million to $190.0 million, while the working capital facility had been
decreased from $50.0 million to $30.0 million. While the total quantum of the
Facilities has not changed, the repayment profile has been extended in line
with the rebase schedule released on July 17, 2023, and the maturity of the
WCF has been extended to June 30, 2031.

·      During 2023, the Company announced the appointment of William
Lamb as Chief Executive Officer, effective August 17, 2023, and Glenn Kondo,
as Chief Financial Officer, effective January 1, 2024. Eira Thomas and Zara
Boldt departed during 2023.

DIAMOND MARKET

The long-term outlook for natural diamond prices remains positive, anchored on
improving fundamentals around supply and demand as many of the world's largest
mines reach their end of life. Currently, slower than anticipated economic
growth in China and a voluntary import ban on rough diamonds into India in Q4
2023 dampened the recovery of rough diamond prices towards the end of 2023.
Changes in global economic conditions, consumer demand, geopolitical events,
and industry-specific dynamics resulted in a challenging market in 2023 with
reduced demand and downward pressure on both polished and rough diamond
pricing, especially in the smaller size classes. Restricted supply by the
largest producers towards the end of 2023, together with the Group of Seven
discussions surrounding sanctions on rough diamonds from Russia, resulted in
low levels of price recovery at the end of 2023.

Sales of lab-grown diamonds increased steadily through 2023 with many smaller
retail outlets increasingly adopting these diamonds as a product. Lab-grown
stones have established themselves in the marketplace and is expected to
continue to take up increasing market share in the smaller to medium sized
goods over time. The longer-term market fundamentals for natural diamonds
remain positive, pointing to continued price growth as demand is expected to
outstrip future supply, which is now declining globally.

2024 OUTLOOK

This section of the press release provides management's production and cost
estimates for 2024. These are "forward-looking statements" and subject to the
cautionary note regarding the risks associated with forward-looking
statements. Diamond revenue guidance does not include revenue related to the
sale of exceptional stones (an individual rough diamond which sells for more
than $10 million), or the Sethunya. No changes have been made to the Company's
Guidance which was released in November 2023.

 Karowe Diamond Mine                                                          2024
 In millions of U.S. dollars unless otherwise noted                           Full Year
 Diamond revenue (millions)                                                   $220 to $250
 Diamond sales (thousands of carats)                                          345 to 375
 Diamonds recovered (thousands of carats)                                     345 to 375
 Ore tonnes mined (millions)                                                  2.8 to 3.2
 Waste tonnes mined (millions)                                                0.8 to 1.4
 Ore tonnes processed (millions)                                              2.6 to 2.9
 Total operating cash costs((1)) including waste mined (per tonne processed)   $28.50 to $33.50
 Underground Project                                                          Up to $100 million
 Sustaining capital                                                           Up to $10 million
 Average exchange rate - Botswana Pula per United States Dollar                12.5

(1) Operating cash costs are a non-IFRS measure.  See "Non-IFRS Financial
Performance Measures".

DIAMOND SALES

Karowe diamonds are sold through three separate and distinct sales channels,
namely through the HB sales agreement, on the Clara digital sales platform and
through quarterly tenders.

SALES FOR +10.8 CARAT DIAMOND PRODUCTION FROM KAROWE

Karowe's large, high value diamonds have historically accounted for
approximately 60% to 70% of Lucara's annual revenues.  In September 2023,
Lucara terminated the definitive sales agreement executed with HB in November
2022 (for all +10.8 carat diamonds recovered from Karowe) due to HB's material
breach of its financial commitments. The rough diamonds delivered to HB prior
to the termination of the agreement continued to be manufactured and sold as
polished diamonds. The Company retains a contractual right to receive "top-up"
payments from polished diamond sales for goods delivered prior to the
termination of the agreement. The Company continued to sell its +10.8 carat
production through this established sales channels while it continued to work
with the management of HB on options for a new Diamond Sales Agreement which
is subject to pre-approval from the Government of the Republic of Botswana.

For the three months ended December 31, 2023, the Company recorded revenue of
$17.4 million from the HB arrangements (inclusive of top-up payments of $6.8
million), as compared to revenue of $24.1 million (inclusive of top-up
payments of $3.6 million) for the three months ended December 31, 2022. The
fourth quarter saw a reduction in the goods delivered to HB as a result of the
termination of the agreement at the end of the third quarter. Revenue was
affected by a 92% recovery factor achieved in 2023, 8% below plan. Revenue in
the fourth quarter was also affected by the natural variability in the value
of large stones recovered in any given period. As a result of these factors,
revenue from HB decreased to 48% of total revenue recognized in the fourth
quarter of 2023 (Q4 2022 - 60%). The product mix in Q4 2023 was predominantly
from the South Lobe ore body, with some contribution from the Centre Lobe (Q4
2022 - 100% South Lobe ore).

CLARA SALES PLATFORM

During Q4 2023, the sales volume transacted was $2.3 million (Q4 2022: $6.6
million), as lower volumes and lower valued goods were placed for sale (due to
the shift in product mix from the Karowe Mine). Some sales are recognized on a
net revenue basis.  A softer market was observed with the voluntary import
ban on rough diamonds into India during the fourth quarter. Prices increased
5% overall in December with a resumption of purchasing across most size
categories; however, prices remain lower than Q4 2022. Price stability
continues to be observed in the stones between 5 to 10.8 carats in size.

QUARTERLY TENDER

A total of 108,137 carats were sold in the December 2023 tender, generating
revenues of $16.9 million or $156 per carat (Q4 2022 tender: $12.2 million
from the sale of 76,264 carats or $133 per carat). Rough diamond prices saw a
strong rebound in the fourth quarter of 2023 following the significant
decrease observed earlier in 2023 as market fundamentals strengthened. A 19%
increase from the third quarter tender was observed owing to price increases
and product mix offered in the fourth quarter tender.

SUBSEQUENT EVENT

On February 18, 2024, the Company announced the signing of a NDSA with HB in
respect of all qualifying diamonds produced in excess of 10.8 carats in size
from the Karowe Mine. The NDSA is subject to the approval of the Company's
project lenders. Upon such approval the agreement terms will be effective
retroactively from December 1, 2023. Since that time, Lucara has continued to
supply qualifying rough diamonds to HB in order to fund its operations and the
Karowe UGP.

KAROWE UNDERGROUND EXPANSION UPDATE

The Karowe UGP is designed to access the highest value portion of the Karowe
orebody, with initial underground carat production predominantly from the
highest value eastern magmatic/pyroclastic kimberlite (south) ("EM/PK(S)")
unit.  The underground expansion is expected to extend mine life to at least
2040.

On July 16, 2023, an update to the Karowe UGP schedule and budget was
announced (Press Release
(https://lucaradiamond.com/newsroom/news-releases/lucara-provides-karowe-underground-expansion-proje-122862/)
). This update was initiated in response to slower than planned ramp up to
expected sinking rates in 2022, and, to account for time incurred to complete
grouting programs while mining through the water-bearing geological zones.
These chemical grouting programs took longer than anticipated due to a
combination of high-water volumes in the sandstone lithologies between 870 and
752 metres above sea level in depth (144 metres to 262 metres below the shaft
collar) and technical challenges associated with the transition to main
sinking.

The updated schedule incorporates a 28% increase in the duration of
construction, extending the anticipated commencement of production from the
underground from H2 2026 to H1 2028. The revised forecast of costs at
completion is $683.0 million (including contingency), a 25% increase to the
May 2022 estimated capital cost of $547 million. The forecasted increase of
$136.0 million in estimated capital to reach project completion is
predominantly related to increased schedule duration and related labour costs
(approximately 56% of the total increase), grouting costs (approximately 20%
of the total increase), with the balance of the increase attributable to
owner's costs, procurement, and indirect project costs. As at December 31,
2023, capital expenditures of $310.5 million had been incurred and capital
commitments of $77.2 million had been made.

During the year ended December 31, 2023, a total of $101.3 million was spent
on the Karowe UGP development, capitalized borrowing costs, surface
infrastructure, grouting programs, and ongoing shaft sinking activities. The
following activities were completed during Q4 2023:

·      Main sinking in the production and ventilation shafts:

o  The ventilation shaft reached 348 metres below collar, with a planned
final depth of 731 metres. The shaft is currently 61 metres or approximately
26 days ahead of the July 2023 schedule update (combined vertical and lateral
metres).

o  The production shaft reached 348 metres below collar, with a planned final
depth of 765 metres. The production shaft is 11 metres or approximately 24
days behind the July 2023 schedule update (combined vertical and lateral)
mainly due to an unscheduled grouting event in Q3 2024. The production shaft
is not on the project schedule critical path.

o  At the end of 2023, both shaft bottoms were at 348 metres below collar
(666 masl) having completed the first shaft stations at the 670-level and
engaged in the start of 670-level lateral development.

o  During Q4 2023, the ventilation shaft sank 76 metres, completed the 718
slinging cubby and established the 670-level station, catwalk and was engaged
in level development. Total lateral developed in Q4 2023 was 97 metres. During
the quarter, a Kubota, Sandvik DD321 two boom jumbo drill and a Caterpillar
RG1300G 7-tonne LHD were slung down in the ventilation shaft to the 670-level
for lateral development mining.

o  Production shaft activities included sinking a total of 114 metres and
establishing the 670-level station, catwalk and initiating lateral
development. A total of 30 metres of lateral development was completed.

o  Commissioning of the temporary bulk air coolers at each shaft was
completed and construction of the permanent bulk air coolers at the production
shaft continued.

o  Detailed engineering and fabrication of the permanent men and materials
winder commenced during the quarter, representing the last major component for
the permanent winders.

o  Both shafts have completed sinking through the water-bearing Ntane and
Mosolotane sandstones. Sinking and lateral development during the fourth
quarter took place in the Thalbala mudstone in dry conditions.

·      Contract for fabrication of the permanent men and materials
winder was signed during the quarter, representing the last major component
for the permanent winders.

·      Mining engineering advanced with a focus on supporting shaft
sinking, underground infrastructure engineering and finalizing level plans.

·      The impact of implementing a behavioural-based safety training
program, Safe Start®, in Q4 2022 has been evident in 2023. During 2023, the
UGP achieved a twelve-month rolling Total Recordable Injury Frequency Rate of
0.19. Project to date Total Recordable Injury Frequency Rate at December 31,
2023 was 0.55.

The capital cost for the underground expansion in 2024 is expected to be up to
$100 million - see "2024 Outlook".  Activities for the Karowe UGP in Q1 2024
are expected to include the following:

·      Resumption of sinking within the ventilation and production
shafts.

·      Completion of mining and construction activities on the 670 level
station, including connection of the two shafts and establishment of
electrical substation, sump and de-watering pumps and ventilation doors.

·      Planned grouting events at the base of the Tlapana carbonaceous
shale and top of Mea formation is expected during the period in the production
shaft.

·      Procurement of underground equipment, including dewatering pumps,
underground crush and convey systems and the permanent stage winder.

·      Commissioning of the permanent bulk air cooler system.

·      Preparation of tender documents for the underground lateral
development work; and,

·      Continuation of detailed design and engineering of the
underground mine infrastructure and layout.

FINANCIAL HIGHLIGHTS - Q4 2023

                                                                    Three months ended December 31,         Year ended December 31,
 In millions of U.S. dollars, except carats or otherwise noted      2023              2022                  2023          2022

 Revenues                                                       $   36.5              42.5              $   177.4         212.9
 Operating expenses                                                 (22.3)            (18.5)                (78.6)        (79.3)
 Net income for the period                                          (36.7)            7.1                   (20.2)        40.4
 Earnings per share (basic and diluted)                             (0.07)            0.02                  (0.04)        0.09
 Operating cash flow per share((1))                                 0.00              0.03                  0.11          0.19
 Cash on hand                                                       13.3              26.4                  13.3          26.4
 Cost overrun facility (restricted cash)                            18.6              -                     18.6          -
 Amounts drawn on working capital facility((2))                     35.0              15.0                  35.0          15.0
 Amounts drawn on project finance facility                          90.0              65.0                  90.0          65.0
 Karowe Revenue                                                     36.3              40.1                  172.4         203.8
 Carats sold                                                        111,523           81,264                379,287       327,028

 QUARTERLY RESULTS OF OPERATIONS - KAROWE MINE, BOTSWANA

                                                 UNIT        Q4-23    Q3-23    Q2-23    Q1-23    Q4-22
 Sales
 Revenues from the sale of Karowe diamonds       US$M        36.3     56.2     38.6     41.3     40.1
 Karowe carats sold                              Carats      111,523  111,673  72,717   83,374   81,264
 Production
 Tonnes mined (ore)                              Tonnes      607,101  869,188  682,636  541,400  484,705
 Tonnes mined (waste)                            Tonnes      456,880  954,226  907,051  761,295  199,385
 Tonnes processed                                Tonnes      703,472  724,640  720,345  700,678  690,946
 Average grade processed((1))                    cpht ((*))  14.0     13.6     12.6     12.8     12.5
 Carats recovered((1))                           Carats      98,177   98,311   90,497   89,640   86,655
 Costs
 Operating cost per tonne of ore processed((2))  US$         31.96    28.62    27.97    26.65    26.20

 Capital Expenditures
 Sustaining capital expenditures                 US$M        8.0      3.2      2.4      0.8      9.9
 Underground expansion project((3))              US$M        28.0     20.3     22.5     30.5     22.3

CONFERENCE CALL

The Company will host a conference call and webcast to discuss the results on
Wednesday, February 21, 2024 at 6:00am Pacific, 9:00am Eastern, 2:00pm UK,
3:00pm CET. To join the conference call please use the following link
https://emportal.ink/48xMjQ6 (https://emportal.ink/48xMjQ6) or the phone
numbers listed below.

 

Conference ID:

26126065 / Lucara Diamond

 

Dial-In Numbers:

Toll-Free Participant Dial-In North America
   (+1) 888 390 0605

UK Toll
free
   0800 652 2435

Local Toronto
 
(+1) 416 764 8609

 

Webcast:

To view the live webcast presentation, please log on using this direct link:
https://app.webinar.net/lrAM9b291Zz (https://app.webinar.net/lrAM9b291Zz) The
presentation slideshow will also be available in PDF format for download from
the Lucara website (Link to presentation
(https://lucaradiamond.com/newsroom/presentations/) ).

 

Conference Replay:

A replay of the telephone conference will be available two hours after the
completion of the call until February 28, 2024.  The pass code for the replay
is: 126065 #

 

Replay number (Toll Free North America)      (+1) 888 390 0541

Replay number (Local)
                (+1) 416 764 8677

 

On behalf of the Board,

William Lamb

President and Chief Executive Officer

 

Follow Lucara Diamond on Facebook (https://www.facebook.com/LucaraDiamond/) ,
Instagram (https://www.instagram.com/lucaradiamond/) , and LinkedIn
(https://www.linkedin.com/company/lucara-diamond-corp-)

 

For further information, please contact:

 

 Hannah Reynish       Investor Relations & Communications
                      +1 604 674 0272| info@lucaradiamond.com (mailto:info@lucaradiamond.com)

 Sweden               Robert Eriksson, Investor Relations & Public Relations
                      +46 701 112615 | reriksson@rive6.ch (mailto:reriksson@rive6.ch)

 UK Public Relations  Charles Vivian / Jos Simson, Tavistock
                      +44 778 855 4035 | lucara@tavistock.co.uk (mailto:lucara@tavistock.co.uk)

 

ABOUT LUCARA

Lucara is a leading independent producer of large exceptional quality Type IIa
diamonds from its 100% owned Karowe Diamond Mine in Botswana. The Karowe Mine
has been in production since 2012 and is the focus of the Company's operations
and development activities. Clara Diamond Solutions Limited Partnership
("Clara"), a wholly-owned subsidiary of Lucara, has developed a secure,
digital sales platform which ensures diamond provenance from mine to finger.
Lucara has an experienced board and management team with extensive diamond
development and operations expertise.  Lucara and its subsidiaries operate
transparently and in accordance with international best practices in the areas
of sustainability, health and safety, environment, and community relations.
Lucara has adopted the IFC Performance Standards and the World Bank Group's
Environmental, Health and Safety Guidelines for Mining (2007).  Accordingly,
the development of the Karowe underground expansion project ("UGP") adheres to
the Equator Principles. Lucara is committed to upholding high standards while
striving to deliver long-term economic benefits to Botswana and the
communities in which the Company operates.

 

The information is information that Lucara is obliged to make public pursuant
to the EU Market Abuse Regulation and the Swedish Securities Markets Act. This
information was submitted for publication, through the agency of the contact
person set out above, on February 20, 2024 at 2:00pm Pacific Time.

NON-IFRS FINANCIAL PERFORMANCE MEASURES

This news release refers to certain financial measures, such as adjusted
EBITDA, adjusted operating earnings, operating cash flow per share, operating
margin per carat sold and operating cost per tonne of ore processed, which are
not measures recognized under IFRS and do not have a standardized meaning
prescribed by IFRS. These measures may differ from those made by other
corporations and accordingly may not be comparable to such measures as
reported by other corporations. These measures have been derived from the
Company's financial statements, and applied on a consistent basis, because the
Company believes they are of assistance in the understanding of the results of
operations and financial position. Please refer to the Company's MD&A for
the year ended December 31, 2023 for an explanation of non-IFRS measures used.

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

Certain of the statements made herein contain certain "forward-looking
information" and "forward-looking statements" as defined in applicable
securities laws. Generally, any statements that express or involve discussions
with respect to predictions, expectations, beliefs, plans, projections,
objectives, assumptions or future events or performance and often (but not
always) using forward-looking terminology such as "expects", "is expected",
"anticipates", "believes", "plans", "projects", "estimates", "budgets",
"scheduled", "forecasts", "assumes", "intends", "strategy", "goals",
"objectives", "potential", "possible" or variations thereof or stating that
certain actions, events, conditions or results "may", "could", "would",
"should", "might" or "will" be taken, occur or be achieved, or the negative of
any of these terms and similar expressions) are not statements of historical
fact and may be forward-looking statements.

In particular, forward-looking information and forward-looking statements may
include, but are not limited to, information or statements with respect to the
Company's ability to continue as a going concern, the project schedule and
capital costs for the Karowe UGP, the diamond sales, projection and outlook
disclosure under "2024 Outlook", the Company's ability to fund the COF, the
impact of supply and demand of rough or polished diamonds, expectations
regarding top-up values, estimated capital costs, the timing, scope and cost
of additional grouting events at the Karowe UGP, the Company's ability to
comply with the terms of the Facilities which are required to construct the
Karowe UGP, including future funding requirements to the COF, that expected
cash flow from operations, combined with external financing will be sufficient
to complete construction of the  Karowe UGP, that the estimated timelines to
achieve mine ramp up and full production from the Karowe UGP can be achieved,
that sufficient stockpiled ore will be available to generate revenue prior to
the achievement of commercial production of the Karowe underground mine, the
economic potential of a mineralized area, the size and tonnage of a
mineralized area, anticipated sample grades or bulk sample diamond content,
expectations that the Karowe UGP will extend mine life, forecasts of
additional revenues, future production activity, that depletion and
amortization expense on assets will be affected by both the volume of carats
recovered in any given period and the reserves that are expected to be
recovered, the future price and demand for, and supply of, diamonds,
expectations regarding the scheduling of activities for the Karowe UGP in
2024, future forecasts of revenue and variable consideration in determining
revenue, the impact of the termination of the HB sales agreement on the
Company's projected revenue and sales channels, estimation of mineral
resources, exploration and development plans, cost and timing of the
development of deposits and estimated future production, interest rates,
including expectations regarding the impact of market interest rates on future
cash flows and the fair value of derivative financial instructions, currency
exchange rates, rates of inflation, credit risk, price risk, requirements for
and availability of additional capital, capital expenditures, operating costs,
timing of completion of technical reports and studies, production and cost
estimates, tax rates, timing of drill programs, government regulation of
operations, environmental risks and ability to comply with all environmental
regulations, reclamation expenses, title matters including disputes or claims,
limitations on insurance coverage, the profitability of Clara and the Clara
Platform, and the scaling of the digital platform for the sale of rough
diamonds owned by Clara, the expected use of the Clara Facility, that the
Company intends to continue to seek additional supply, both from third-party
producers and the secondary market for Clara, and the potential impacts of
COVID-19, economic and geopolitical risks, including potential impacts from
the Russian military invasion of Ukraine and the escalating conflict between
Israel and Hamas.

Forward-looking information and statements are based on the opinions and
estimates of management as of the date such statements are made, and they are
subject to several known and unknown risks, uncertainties and other factors
which may cause the actual results, performance or achievements of the Company
to be materially different from any future results, performance or achievement
expressed or implied by such forward-looking statements. The Company believes
that expectations reflected in this forward-looking information are
reasonable, but no assurance can be given that these expectations will prove
to be correct.  Certain risks which could impact the Company are discussed
under the heading "Risks and Uncertainties" in the Company's most recently
filed Annual MD&A and, in the Company's most recent Annual Information
Form available at http://www.sedar.com (the "AIF").

The foregoing is not exhaustive of the factors that may affect any of our
forward-looking statements. Forward-looking statements are statements about
the future and are inherently uncertain, and our actual achievements or other
future events or conditions may differ materially from those reflected in the
forward-looking statements due to a variety of risks, uncertainties, and other
factors, including, without limitation, those referred to in this news
release.

Although the Company has attempted to identify important factors that could
cause actual actions, events, or results to differ materially from those
described in forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or intended.
The forward-looking statements contained in this news release are based on the
beliefs, expectations, and opinions of management as of the date of this
disclosure. There can be no assurance that forward-looking statements will
prove to be accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly, readers and
investors should not place undue reliance on forward-looking statements.
Forward-looking information and statements are made as of the date of this
disclosure and accordingly are subject to change after such date. Except as
required by law, the Company disclaims any obligation to revise any
forward-looking information and statements to reflect events or circumstances
after the date of such information and statements. All forward-looking
information and statements contained or incorporated by reference in this news
release are qualified by the foregoing cautionary statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  DRLPPUWAPUPCUQG

Recent news on Lucara Diamond

See all news