Feb 20 (Reuters) - Methanex Corp MX.TO :
* METHANEX PROVIDES UPDATE ON GEISMAR 3 METHANOL PLANT IN
GEISMAR,
LOUISIANA
* METHANEX CORP - COMMERCIAL PRODUCTION OF ITS NEW 1.8
MILLION
TONNE METHANOL PLANT, GEISMAR 3 (G3), IN GEISMAR, LOUISIANA HAS
BEEN DELAYED
* METHANEX CORP: DETERMINED THAT THERE IS SIGNIFICANT DAMAGE
TO A
LARGE NUMBER OF SUPPORTING REFRACTORY BRICKS IN VESSEL WHICH
WILL REQUIRE REPLACEMENT
* METHANEX CORP - PRODUCTION DELAYED DUE TO COMPLICATIONS
THAT
OCCURRED IN AUTOTHERMAL REFORMER (ATR) DURING LATE STAGES OF
INITIAL START-UP PROCESS
* METHANEX CORP - ISSUE REQUIRED ATR TO BE COOLED AND
BROUGHT TO A
SAFE STATE WHERE TEAMS COULD CONDUCT DETAILED INSPECTIONS OF
VESSEL
* METHANEX: SPECIALTY FORMED REFRACTORY BRICKS REQUIRE TIME
TO
PROCURE AND, AS A RESULT, COMMERCIAL PRODUCTION COULD BE DELAYED
UP TO END OF Q3
* METHANEX CORP - MANAGEMENT BELIEVES THAT TOTAL CAPITAL
COST WILL
NOT SIGNIFICANTLY EXCEED UPPER END OF CAPITAL COST GUIDANCE OF
$1.30 BILLION
Source text for Eikon: ID:nGNXjFl5w
Further company coverage: MX.TO