March 21 (Reuters) - Metsa Board Oyj METSB.HE :
* METSÄ BOARD WILL NOT INVEST IN THE KASKINEN FOLDING
BOXBOARD
MILL
* PRE-ENGINEERING HAS NOW BEEN COMPLETED AND METSÄ BOARD HAS
DECIDED NOT TO PROCEED WITH INVESTMENT IN KASKINEN FOLDING
BOXBOARD MILL
* WILL WRITE DOWN COSTS OF PRE-ENGINEERING, IN TOTAL
APPROXIMATELY
EUR 8 MILLION
* TOTAL COST OF PLANNED INVESTMENT WAS SIGNIFICANTLY HIGHER
THAN
ORIGINALLY ESTIMATED, MEANING THAT TARGETS FOR PAYBACK TIME AND
RETURN ON CAPITAL EMPLOYED WOULD NOT HAVE BEEN MET
* TOTAL ESTIMATED INVESTMENT COST OF SIMPELE AND KYRO
PAPERBOARD
MILLS IS EUR 250 MILLION OVER NEXT 10 YEARS
* DECIDED TO LAUNCH PROGRAMMES FOR NEW PRODUCT OPTIONS AS
WELL AS
GROWTH AND DEVELOPMENT INVESTMENTS AT ITS EXISTING MILLS
* AT KYRO BOARD MILL, AN INVESTMENT PROGRAMME WILL BE
LAUNCHED TO
IMPROVE PERFORMANCE OF CURRENT BARRIER BOARD AND EXPAND ITS
END-USE AREAS
* LAUNCHES A MAJOR INVESTMENT PROGRAMME TO MODERNISE SIMPELE
BOARD
MILL