Brief: Mostostal Warszawa Updates On Delay In Works On Elektrownia Jaworzno III

Jan 31 (Reuters) - Mostostal Warszawa SA  MSWP.WA :
    * SAYS IT HAS RECEIVED INFORMATION FROM RAFAKO THAT RAFAKO
HAS
INFORMED NOWE JAWORZNO GRUPA TAURON THAT WORKS ON IMPLEMENTATION
OF CONTRACT FOR CONSTRUCTION OF 910 MW BLOCK AT ELEKTROWNIA
JAWORZNO III - ELEKTROWNIA II WILL BE EXTENDED TILL FEB 4
    * RAFAKO IS THE LEADER OF THE CONSORTIUM (99.99%) IN WHICH
THE
COMPANY IS A PARTNER (0.01%)
    * PREVIOUSLY THE PLANNED COMPLETION DATE FOR WORKS WAS JAN
31
    * THE COMPANY HAS BEEN INFORMED THAT ACCORDING TO RAFAKO THE
EXTENSION IS A RESULT OF OBJECTIVE REASONS FOR WHICH RAFAKO'S
UNIT E003B7 IMPLEMENTING THE WORKS IS NOT RESPONSIBLE
    * THE COMPANY HAS ALSO BEEN INFORMED THAT THE ORDERER
EXPECTS
COMMISSIONING OF THE BLOCK TO TAKE PLACE BY FEB 15 

    
 Source text for Eikon:  urn:newsml:reuters.com:*:nEM20Z4z2a
    
 Further company coverage:  MSWP.WA  
   


 (Gdansk Newsroom)
 ((gdansk.newsroom@thomsonreuters.com; +48 58 778 51 10))

Recent news on Mostostal Warszawa SA

See all news