Dec 31 (Reuters) - Rafako SA RFK.WA :
* SAID ON MONDAY THAT ITS SUBSIDIARY HAS REVISED A BUDGET
FOR THE
CONTRACT ON THE CONSTRUCTION OF A 910 MW POWER PLANT IN JAWORZNO
AND WILL REPORT A LOSS FOR 2019 IN THE ESTIMATED AMOUNT OF ABOUT
155.8 MILLION ZLOTYS
* SAID THE LOSS IS DUE TO PROLONGED CONSTRUCTION TIME
* AFTER THE BUDGET'S REVISION THE MARGIN ON THE CONTRACT HAS
BEEN
LOWERED TO ABOUT 5% FROM 8%
* SAID IT HAS RECEIVED OVER 30% OF THE AMOUNT IT APPLIED FOR
TO
COVER THE COSTS OF THE PROLONGING OF THE CONTRACT
* SAID IT PLANS TO ESTIMATE THE IMPACT OF THE SUBSIDIARY'S
LOSS ON
ITS 2019 CONSOLIDATED RESULT
* SAID IT HAS INITIATED WORKS AIMED AT LIMITING THE
ESTIMATED
NEGATIVE IMPACT