Brief: Tauron Says Unit Signs Agreement Regarding Construction Of Power Plant Unit In Jaworzno

May 4 (Reuters) - Tauron Polska Energia  TPE.WA :
    * UNIT NOWE JAWORZNO GRUPA TAURON SIGNS AGREEMENT WITH
RAFAKO-MOSTOSTAL WARSZAWA CONSORTIUM AND WITH E003B7 ON
REALIZATION OF CONSTRUCTION OF 910 MW POWER PLANT UNIT IN
JAWORZNO
    * PARTIES DETERMINED CAUSES OF DAMAGE OF ONE OF BOILERS
ELEMENTS
AND THAT FAILURE WAS AFTERMATH OF ADVERSE COMBINATION OF EVENTS
DURING POWER PLANT UNIT START
    * EMERGENCY COMMISSION HAVE AGREED ON THE REPAIR OF DAMAGED
BOILER
ELEMENTS THAT WILL ALLOW TO AVOID SIMILAR FAULTS IN THE FUTURE
    * PROGRESS OF PROJECT AS AT MAY 4 IS OVER 98%
    * CONSORTIUM ESTIMATES THAT COMMISSIONING OF POWER PLANT
UNIT WILL
TAKE PLACE TILL NOV 15

Source text for Eikon:  ID:nEM3K9Rf5a 
Further company coverage:  TPE.WA 

 (Gdansk Newsroom)
 ((gdansk.newsroom@thomsonreuters.com; +48 58 778 51 10;))

Recent news on Mostostal Warszawa SA

See all news