Dec 2 (Reuters) - Tauron Polska Energia SA TPE.WA :
* SIGNS SETTLEMENT IN REGARDS TO JAWORZNO UNIT
* SETTLEMENT CONFIRMS DATE OF SYNCHRONIZATION OF UNIT FOR
APRIL 29
2022
* AT THIS STAGE THERE IS NO POSSIBILITY TO RULE ON WHO IS
RESPONSIBLE FOR UNIT FAILURE FROM JUNE 11 2021
* THE COST OF REPAIRMENT OF THE UNIT IS SET AT 91 MILLION
ZLOTYS
* ADDITIONALLY, NJGT HAS COMMITTED ITSELF TO ASSIGN
CONSORTIUM OF
RAFAKO SA AND MOSTOSTAL WARSZAWA SA OTHER WORKS TO INCREASE
UNITS EFFICIENCY AT TOTAL VALUE OF 23 MILLION ZLOTYS
* OTHER WORKS ARE CONDITIONAL TO CONSORTIUM'S TIMELY
SYNCHRONIZATION OF UNIT AND PRESENTATION OF DECLARATION TO
FINANCIAL INSTITUTIONS FOR REALISATION OF DEAL
Source text for Eikon: ID:nEM3LpyW8a
Further company coverage: TPE.WA
(Reporting by Gdansk Newsroom)