Dec 26 (Reuters) - NHPC Ltd NHPC.NS :
* NHPC LTD - SUBANSIRI LOWER HE PROJECT TO COMPLETE 3 UNITS
BY MAY
2025
* NHPC - SUBANSIRI LOWER HE PROJECT TO COMPLETE 5 UNITS OF
250 MW
EACH BY MAY, 2026
* NHPC LTD - LOSS REVISED TO 10.76 BILLION RUPEES FOR
TEESTA-V
FLASH FLOOD
* NHPC LTD - 1.50 BILLION RUPEES RECEIVED FOR MATERIAL
DAMAGE LOSS
AT TEESTA-V