Brief: Nordic Mining Completes Definitive Feasibility Study For Engebø Rutile And Garnet Project
Jan 28 (Reuters) - Nordic Mining ASA NOMIN.OL :
* COMPLETED DEFINITIVE FEASIBILITY STUDY ("DFS") FOR ENGEBØ
RUTILE
AND GARNET PROJECT
* DFS RESULT IS AVERAGE ANNUAL FREE CASHFLOW FIRST 15 YEARS
OF USD
70M
* DFS RESULT IS INITIAL CAPEX OF USD 311M AND DEFERRED CAPEX
OF
USD 25M (UNDERGROUND)
* DFS RESULT ISPAY-BACK PERIOD < 5 YEARS
Source text for Eikon: ID:nObimzrMWa