Brief: Nordic Mining Maintains Goal Of First Cargo Of Rutile By End Of Q1 2026
Oct 31 (Reuters) - Nordic Mining ASA NOM.OL: MAINTAINING GOAL OF FIRST CARGO OF RUTILE IN Q1 AND REACHING DESIGN CAPACITY IN LATE Q2 2026 EXPERIENCED A DELAYED RAMP UP DUE TO OPERATIONAL AND TECHNICAL ISSUES DURING Q3. A TOTAL OF 3,800 TONNES OF GARNET WERE PRODUCED IN Q3. NOK 1.0 MILLION FROM SALE OF GARNET DURING Q3 WITH AN OPERATING LOSS OF NOK -129.1 MILLION. Source text: ID:nObisSS1ha Further company coverage: NOM.OL (Gdansk Newsroom) ((gdansk.newsroom@thomsonreuters.com; +48 58 7696600;))