Sept 25 (Reuters) - Nordic Mining ASA NOM.OL:
FIRST CARGO OF RUTILE IS DELAYED, AND TAP ISSUE OF EXISTING BOND
DRY PLANT HAVE LOWER THROUGHPUT, UPTIME DUE TO SOME OPERATIONAL,TECHNICAL DIFFICULTIES IN LATTER PART OF Q3
WILL CARRY OUT OPERATIONAL REVIEW
FIRST CARGO OF RUTILE IS EXPECTED TO BE AVAILABLE IN Q1 2026
STATED GOAL IS REACHING DESIGN CAPACITY IN LATE Q2 2026
PROPOSES TAP ISSUE OF USD 22.5 MILLION
SECURES SUPPORT FROM HOLDERS OF BONDS REPRESENTING >80% OF TOTAL OUTSTANDING PRINCIPAL AMOUNT OF BONDS