June 14 (Reuters) - Veolia Environnement SA VIE.PA :
* NORSKE SKOG GOLBEY, VEOLIA AND PEARL INFRASTRUCTURE
CAPITAL
LAUNCH THE INDUSTRIAL ECOLOGY PROJECT AT THE GOLBEY PAPER MILL
* FROM 2024, IT WILL PRODUCE 200 GWH OF CLEAN ELECTRICITY
PER
YEAR, EQUIVALENT TO THE CONSUMPTION OF MORE THAN 13,000 HOMES,
AS WELL AS 700 GWH OF HEAT
* PEARL INFRASTRUCTURE CAPITAL STRUCTURED THE FINANCING IN
THE
FORM OF A €150 MILLION NON-RECOURSE BOND, IS PROVIDING BULK OF
EQUITY REQUIRED FOR PROJECT COMPANY WHICH IS CARRYING
COGENERATION PLANT
* THIS PROJECT REPRESENTS AN INVESTMENT OF AROUND €200
MILLION,
THE FINANCIAL CLOSING OF WHICH WAS COMPLETED ON 8 JUNE 2022
* PEARL INFRASTRUCTURE CAPITAL IS THE MAIN INVESTOR (80%)
ALONGSIDE NORSKE SKOG GOLBEY (10%) AND VEOLIA (10%)
Further company coverage: VIE.PA
(Gdansk Newsroom)
((gdansk.newsroom@thomsonreuters.com; +48587696600;))