Northland, Orlen complete turbine installation at Poland's first offshore wind project
Northland, Orlen complete turbine installation at Poland's first offshore wind project Oct 7 (Reuters) - Canadian power producer Northland Power NPI.TO and Poland's biggest energy company Orlen PKN.WA have completed the installation of all 76 turbines at Poland's first offshore wind project, Baltic Power, they said on Wednesday.
The 1.1 gigawatt facility, jointly owned by Northland and Orlen, is on track to begin commercial operations in 2026, the companies said.
Overall costs are aligned with original expectations as the project advances through commissioning, Northland said
More than one-third of the turbines are already generating power, following the delivery of the project's first electricity to the grid in July
The facility will generate around 4 terawatt-hours of electricity per year
It is undergoing tests to provide enough electricity to power more than 1.5 million Polish households in a few months
The project is underpinned by a 25-year contract-for-difference mechanism that will provide revenue certainty
(Reporting by Marta Maciag and Stefan Gardawski)
((Marta.Maciag@thomsonreuters.com;))
Recent news on Northland Power (Ontario)
See all newsPoland - Factors to Watch October 8
Northland, Orlen complete turbine installation at Poland's first offshore wind project
Brief: Northland Power Announces Completion Of 1.1 GW Baltic Power Offshore Wind Project In Poland
Brief: Northland Power Brings Alberta’S Largest Battery Storage Facility Online Ahead Of Schedule And Under Budget
Northland Power Inc (Ontario) reports results for the quarter ended June 30 - Earnings Summary