Northland, Orlen say first power generated at Poland wind farm
Northland, Orlen say first power generated at Poland wind farm By Amanda Stephenson
CALGARY, July 10 (Reuters) - Canada's Northland Power NPI.TO and its partner, Polish multinational Orlen PKN.WA, said on Friday the first electricity has been generated at their Baltic Power project, which is Poland's first offshore wind farm.
Here are more details from company statements:
The 1.1 gigawatt project is located about 23 km (14 miles) off the Polish coast near Choczewo and Leba, and spans 130 square km of the Baltic Sea.
It is expected to produce enough electricity annually to power 1.5 million Polish households.
The project is 49% owned by Northland and 51% by Orlen, and in 2023 was estimated to cost about €4.73 billion ($5.41 billion)
Offshore installation and commissioning activities continue, with 54 of the project’s 76 turbines installed.
The project is expected to be fully operational in the second half of 2026.
($1 = 0.8749 euros)
(Reporting by Amanda Stephenson in Calgary; Editing by Jamie Freed)
((amanda.stephenson@thomsonreuters.com))
Recent news on Northland Power (Ontario)
See all newsPoland - Factors to Watch October 8
Northland, Orlen complete turbine installation at Poland's first offshore wind project
Brief: Northland Power Announces Completion Of 1.1 GW Baltic Power Offshore Wind Project In Poland
Brief: Northland Power Brings Alberta’S Largest Battery Storage Facility Online Ahead Of Schedule And Under Budget
Northland Power Inc (Ontario) reports results for the quarter ended June 30 - Earnings Summary