April 16 (Reuters) - Obsidian Energy Ltd OBE.TO :
* OBSIDIAN ENERGY ANNOUNCES AN OPERATIONAL UPDATE ON CARDIUM
DRILLING PROGRAM
* OBSIDIAN ENERGY LTD - WILL RESUME DRILLING OF ITS FAST
CYCLE
PRIMARY DEVELOPMENT PROGRAM IN CARDIUM FOLLOWING SPRING BREAK-UP
IN JULY 2019
* OBSIDIAN ENERGY LTD - ALL OF OUR PLANNED 2019 LOCATIONS
WILL BE
FULLY LICENSED AND DRILL READY IN VERY NEAR FUTURE
* OBSIDIAN ENERGY LTD - PLAN TO CONTINUE DRILLING OF ITS
FAST
CYCLE PRIMARY DEVELOPMENT PROGRAM IN CARDIUM THROUGH TO MARCH
2020
* OBSIDIAN ENERGY LTD - ALL 19 CARDIUM WELLS HAVE NOW BEEN
COMPLETED AND ARE ON PRODUCTION
* OBSIDIAN ENERGY LTD - AVERAGE DRILL, COMPLETE, EQUIP, AND
TIE-IN
COSTS OF ALL 19 WELLS CAME IN AT $3.8 MILLION PER WELL
Source text for Eikon: ID:nPn6QWzRDa