In order to ensure the security of the electricity supply in Denmark, the
Danish authorities have decided to order Ørsted to continue and resume
operations of three of its power station units which use oil and coal as
fuel.
This applies to unit 3 at Esbjerg Power Station and unit 4 at Studstrup
Power Station, which both use coal as their primary source of fuel, and
unit 21 at Kyndby Peak Load Plant, which uses oil as fuel. The two latter
units have already been decommissioned and preserved, whereas Esbjerg
Power Station was scheduled to be decommissioned on 31 March 2023.
Mads Nipper, Group President and CEO of Ørsted, says:
"In order to ensure the security of the electricity supply, the Danish
authorities have today ordered us to continue as well as resume operations
at some of our oil- and coal-fired power stations. We will, of course,
comply with the Danish authorities’ order, and we'll now begin preparing
and maintaining the units as well as securing the staffing necessary to
operate them. We still believe that we, as a society, must phase out the
use of gas, oil, and coal as soon as possible, but we're in the middle of
a European energy crisis, and we will, of course, contribute to ensuring
the electricity supply to the best of our ability."
Ørsted will be facing a number of technical and staffing issues that will
have to be solved. Maintenance will have to be carried out at all three
units to prepare them for operation during the required period. In
addition, it takes highly specialised workers to operate a power station,
and they must be trained in operating the specific power station. Ørsted
expects that it will take time to get everything in place, especially for
unit 4 at Studstrup Power Station and unit 21 at Kyndby Peak Load Plant,
but will make every effort to get the units ready for operation as soon as
possible.
The Danish authorities have ordered Ørsted to keep the three units in
operation until 30 June 2024, and Ørsted therefore maintains its goal of
becoming carbon-neutral by 2025.
Facts about the power station units:
Esbjerg Power Station, unit 3: Coal-fired, can generate 370 MW of
electricity
Studstrup Power Station, unit 4: Coal-fired, can generate 360 MW of
electricity
Kyndby Peak Load Plant, unit 21: Oil-fired, can generate 260 MW of
electricity
For further information, please contact:
Media Relations
Carsten Birkeland Kjær
+45 99 55 77 65
1 cabkj@orsted.com
Investor Relations
Rasmus Keglberg Hærvig
+45 99 55 90 95
2 ir@orsted.com
About Ørsted
The Ørsted vision is a world that runs entirely on green energy. Ørsted
develops, constructs, and operates offshore and onshore wind farms, solar
farms, energy storage facilities, renewable hydrogen and green fuels
facilities, and bioenergy plants. Moreover, Ørsted provides energy
products to its customers. Ørsted is the only energy company in the world
with a science-based net-zero emissions target as validated by the Science
Based Targets initiative (SBTi), and Ørsted aims to deliver a net-positive
biodiversity impact from all new renewable energy projects it commissions
from 2030 at the latest. Ørsted ranks as the world’s most sustainable
energy company in Corporate Knights' 2022 index of the Global 100 most
sustainable corporations in the world and is recognised on the CDP Climate
Change A List as a global leader on climate action. Headquartered in
Denmark, Ørsted employs 7,292 people. Ørsted's shares are listed on Nasdaq
Copenhagen (Orsted). In 2021, the company generated revenue of
DKK 77.7 billion (EUR 10.4 billion). Visit 3 orsted.com or follow us on
Facebook, LinkedIn, Instagram, and Twitter.
Attachments
• 4 Danish authorities order Ørsted’s oil- and coal-fired power
stations into operation.pdf
News Source: Ritzau
══════════════════════════════════════════════════════════════════════════
ISIN: DK0060094928
Category Code: MSCM
TIDM: Orsted
Sequence No.: 191782
EQS News ID: 1454857
End of Announcement EQS News Service
══════════════════════════════════════════════════════════════════════════
5 fncls.ssp?fn=show_t_gif&application_id=1454857&application_name=news&site_id=reuters8
References
Visible links
1. mailto:cabkj@orsted.com
2. mailto:ir@orsted.com
3. https://eqs-cockpit.com/cgi-bin/fncls.ssp?fn=redirect&url=c17d04adc46793f4466471ea992e18f7&application_id=1454857&site_id=reuters8&application_name=news
4. https://eqs-cockpit.com/cgi-bin/fncls.ssp?fn=redirect&url=185ee5a12b1139b904a1a590308358e9&application_id=1454857&site_id=reuters8&application_name=news
============