Progress on delivery of the ERF
asset base can be summarised as:
· Exeter ERF - Safely completed on time (July), meeting capital budget and performing better than specification
· Oxford ERF - Takeover completed in November and plant fully operational. Below capital budget spend and performing better than specification
· Cardiff ERF - Construction complete and first waste burn has just occurred. On schedule and to capital budget
· Runcorn Phase I - Plant about to move into final takeover test
· Runcorn Phase II - construction complete, to capital budget and first waste burn is imminent
· Peterborough ERF - Progressing well to schedule and to capital budget
· Glasgow Recycling and Renewable Energy Centre - Construction progressing well and on schedule for completion 2016 as planned
· Beddington ERF - Judicial review challenge strongly dismissed. Well prepared for project commencement
· Dunbar ERF - Board approval to proceed. Construction commencement expected Q1 2015
· Overall programme is being delivered at world class safety levels and to good quality standards
The Pennon Board has given its
approval to proceed with the £177m
Dunbar ERF at its existing
Oxwellmains waste treatment hub in
East Lothian, Scotland. This
follows an extensive assessment of
market conditions and an appraisal
of current competitive advantages