Brief: Platinum Group Metals says delays in underground development, stoping rates, planned tonnages resulted in ounce production delays

April 4 (Reuters) - Platinum Group Metals Ltd  PTM.TO : 
    * Platinum Group Metals Ltd - delays in underground 
development, stoping rates and planned tonnages have resulted in 
ounce production delays 
    * Platinum group metals - estimated 2017 annual production 
guidance, based on current mine plan, is adjusted from 100,000 
ounces 4e to 85,000 ounces 4e 
    * Platinum group - currently working with BMO capital 
markets and Macquarie Capital to review and assess corporate and 
asset level strategic alternatives 
    * Platinum Group Metals Ltd - during march 2017 Maseve Mine 
produced approximately 2,477 ounces of platinum, palladium, 
rhodium and gold in concentrate 
 