============
Polymetal International plc (POLY)
Polymetal International plc: Feasibility Study results and construction
approval for POX-2
11-Feb-2019 / 10:00 MSK
Dissemination of a Regulatory Announcement that contains inside information
according to REGULATION (EU) No 596/2014 (MAR), transmitted by EQS Group.
The issuer is solely responsible for the content of this announcement.
═════════════════════════════════════════════════════════════════════════════
Release time IMMEDIATE LSE, MOEX: POLY / ADR:
AUCOY
Date 11 February 2019
Polymetal International plc
Feasibility Study results and construction approval for POX-2
The Board of Polymetal International plc approved the POX-2 project on the
basis of the recently completed Feasibility Study (FS) and authorised the
immediate start of construction.
"POX-2 leverages our core technical capabilities and creates substantial
value. It also fully de-risks our business model by eliminating dependence on
concentrate off-take markets", said Vitaly Nesis, Group CEO of Polymetal.
"Emerging trends in the global gold mining industry make POX-2 a crucial
element of the Company's long-term strategy".
STRATEGIC RATIONALE
• The second POX line will meaningfully increase the value of Polymetal's
refractory reserve base, comprising approximately 55% of total ore
reserves. The facility will process concentrates from Polymetal's mines
at Kyzyl, Nezhda, Mayskoye, and Voro.
• POX-2 is expected to generate significant economic benefits as all
refractory concentrates will be retained for in-house processing as
opposed to selling to third-party off-takers. The project will result in
the incremental production of approximately 30-35 Koz of gold per year
from the same amount of feedstock and will, on average, lower TCC by US$
100-150/oz per ounce for 500 Koz of annual gold production.
• POX-2 will ensure strategic security of downstream processing against the
backdrop of tightening environmental regulations in China, currently the
main market for refractory gold concentrates.
• The project will allow Polymetal to create capacity for treatment of
third-party refractory concentrates, a market which has grown
considerably in Russia and globally in recent years.
• POX-2 will further our sustainable development strategy. The
environmental footprint of the Company's value chain will shrink
drastically on the back of substantial reductions in air pollution, water
usage, and solid toxic waste.
FS HIGHLIGHTS
• The project's base case IRR is 14% with an NPV of US$ 112 million, based
on the following assumptions:
◦ 10% discount rate
◦ US$ 1,200/oz gold price
◦ 65 RUB/USD exchange rate
◦ A total of 4.3 Mt of concentrate containing 9.3 Moz of gold
processed from Kyzyl, Nezhda, Mayskoye, and Voro over a period of 23
years
• Pre-production capital expenditures are estimated at US$ 431 million and
will be entirely funded out of Company's operating cash flows.
• The plant's design throughput capacity is 250-300 Ktpa of concentrate,
depending on the levels of sulphur content. Maximum sulfide sulfur
processing capacity is 48 Ktpa. This will complement the 200 Ktpa of
concentrate and 30 Ktpa of sulfur capacity of the existing Amursk POX
facility.
• The facility will utilise titanium-lined steel autoclave operating at 240
˚С and the pressure of 43 bar.
• Hatch Inc. (Toronto, Canada) is responsible for the basic engineering,
detailed engineering, POX procurement support and the supply of
custom-made equipment for high-pressure and acidic processing areas.
Polymetal Engineering is responsible for other processing areas, general
site layout, and infrastructure.
• Polymetal project team will include more than 30 professionals who
actively participated in the successful execution of the original POX
(2013) and POX debottlenecking (2018) projects.
PROJECT DEVELOPMENT TIMELINE
Polymetal envisages the following conceptual development timeline for the
POX-2 Project:
• Start of detailed engineering and construction Q2 2019
• Receipt of all permits Q1 2020
• Delivery of the autoclave on-site Q3 2020
• Completion of civil construction works Q3 2021
• Completion of main equipment installation Q1 2022
• Completion of external infrastructure Q3 2022
• Mechanical completion and start of commissioning activities Q4 2022
• End of commissioning and first production Q3 2023
• Full ramp-up by end of Q4 2023
PROCESSING
The POX-2 site is immediately adjacent to the current Amursk POX facility
within the city of Amursk and will share some of the external infrastructure
(gas main, access road, water main) with the existing POX facility.
Additional electricity supply will be provided via a new dedicated power line
from the regional 110Kw grid.
The project will include a new hydrometallurgical area (POX proper), CIL and
intensive cyanidation areas, an oxygen plant, an upgrade to the existing dry
tailings facility, reverse osmosis water treatment facility, and several
smaller infrastructural facilities (warehouses, maintenance areas, etc.).
POX-2 is designed for processing double refractory concentrates, which
contain micron gold particles encapsulated in sulfides (pyrites and arsenic
pyrites) together with high concentrations of organic carbon. High carbon
content drives high sorption activity (preg-robbing) and dictates the use of
high-temperature (240˚С) pressure oxidation compared with medium-temperature
(200˚С) oxidation utilized at the existing Amursk POX facility.
Pressure oxidation (POX) was selected as the most feasible processing
technology for double refractory ores. It is able to achieve gold recoveries
of 96% by utilizing high temperatures, elevated pressure and oxygen to
recover encapsulated gold, while conventional cyanidation methods would
result in sub-optimal recovery rates of 20-40%. Completed metallurgical tests
on Kyzyl and Mayskoye high-carbon concentrates confirm the recovery rate of
96%.
The total design capacity of the POX-2 plant will be 250-300 Kt of
concentrate per annum. The design of the new POX facility enables the Company
to process feed with different properties without impacting any of the design
parameters.
CAPITAL EXPENDITURE
Total capital costs for the construction of the POX-2 project in 2019-2023
are estimated at US$ 431 million, and will be funded out of Company's
operating cash flows.
Capital Cost,
Category
US$ million
Engineering 31
Processing plant equipment 149
Construction 138
Infrastructure 56
Owner's team 9
Contingency 48
Initial Capital Costs 431
In 2017-2018, Polymetal spent approximately US$ 26 million on POX-2, of which
US$ 12 million was for engineering activities and feasibility study and US$
14 million dedicated to pre-manufacturing engineering with equipment
suppliers.
SUSTAINABLE DEVELOPMENT
The FS incorporates several important design features that will minimise its
environmental impact and mitigate related risks:
• Tailings from the plant will be in the form of dry cake. No impoundments
or dam structures will be required.
• The project will have zero water discharge off-site. Process water will
be fully recycled.
• The project will have minimal carbon dioxide discharge and no sulfur or
arsenic oxides discharge.
The Project will boost social investments as Polymetal plans to invest
approximately US$ 6 million into more than 10 long-term projects most
important to city residents, as well as our employees and their families.
This will include the renovation and upgrade of educational, medical and
sports facilities, as well as the enhancement of the Amursk city look and
attractiveness. Polymetal also plans to build new apartment buildings that
will house 100 families.
POX-2 will create more than 400 permanent jobs and generate approximately US$
20 million per year in taxes for all levels of government.
Enquiries
Media Investor Relations
FTI Polymetal 1 ir@polymetalinternational.com
Consulting
+44 Eugenia Onuschenko +44 20 7016 9505 (UK)
Leonid 20
Fink 3727 Timofey Kulakov
1000
Viktor Michael +7 812 334 3666 (Russia)
Pomichal Vasiliev
Joint
Corporate
Brokers
Morgan +44
Stanley 20
7425
Sam 8000
McLennan
Richard
Brown RBC Europe Limited
Tristan Lovegrove +44 20 7653 4000
Panmure Marcus Jackson
Gordon
James
Stearns +44
20
Atholl 7886
Tweedie 2500
FORWARD-LOOKING STATEMENTS
THIS RELEASE MAY INCLUDE STATEMENTS THAT ARE, OR MAY BE DEEMED TO BE,
"FORWARD-LOOKING STATEMENTS". THESE FORWARD-LOOKING STATEMENTS SPEAK ONLY AS
AT THE DATE OF THIS RELEASE. THESE FORWARD-LOOKING STATEMENTS CAN BE
IDENTIFIED BY THE USE OF FORWARD-LOOKING TERMINOLOGY, INCLUDING THE WORDS
"TARGETS", "BELIEVES", "EXPECTS", "AIMS", "INTENDS", "WILL", "MAY",
"ANTICIPATES", "WOULD", "COULD" OR "SHOULD" OR SIMILAR EXPRESSIONS OR, IN
EACH CASE THEIR NEGATIVE OR OTHER VARIATIONS OR BY DISCUSSION OF STRATEGIES,
PLANS, OBJECTIVES, GOALS, FUTURE EVENTS OR INTENTIONS. THESE FORWARD-LOOKING
STATEMENTS ALL INCLUDE MATTERS THAT ARE NOT HISTORICAL FACTS. BY THEIR
NATURE, SUCH FORWARD-LOOKING STATEMENTS INVOLVE KNOWN AND UNKNOWN RISKS,
UNCERTAINTIES AND OTHER IMPORTANT FACTORS BEYOND THE COMPANY'S CONTROL THAT
COULD CAUSE THE ACTUAL RESULTS, PERFORMANCE OR ACHIEVEMENTS OF THE COMPANY TO
BE MATERIALLY DIFFERENT FROM FUTURE RESULTS, PERFORMANCE OR ACHIEVEMENTS
EXPRESSED OR IMPLIED BY SUCH FORWARD-LOOKING STATEMENTS. SUCH FORWARD-LOOKING
STATEMENTS ARE BASED ON NUMEROUS ASSUMPTIONS REGARDING THE COMPANY'S PRESENT
AND FUTURE BUSINESS STRATEGIES AND THE ENVIRONMENT IN WHICH THE COMPANY WILL
OPERATE IN THE FUTURE. FORWARD-LOOKING STATEMENTS ARE NOT GUARANTEES OF
FUTURE PERFORMANCE. THERE ARE MANY FACTORS THAT COULD CAUSE THE COMPANY'S
ACTUAL RESULTS, PERFORMANCE OR ACHIEVEMENTS TO DIFFER MATERIALLY FROM THOSE
EXPRESSED IN SUCH FORWARD-LOOKING STATEMENTS. THE COMPANY EXPRESSLY DISCLAIMS
ANY OBLIGATION OR UNDERTAKING TO DISSEMINATE ANY UPDATES OR REVISIONS TO ANY
FORWARD-LOOKING STATEMENTS CONTAINED HEREIN TO REFLECT ANY CHANGE IN THE
COMPANY'S EXPECTATIONS WITH REGARD THERETO OR ANY CHANGE IN EVENTS,
CONDITIONS OR CIRCUMSTANCES ON WHICH ANY SUCH STATEMENTS ARE BASED
═════════════════════════════════════════════════════════════════════════════
ISIN: JE00B6T5S470
Category Code: MSCH
TIDM: POLY
Sequence No.: 7427
EQS News ID: 774197
End of Announcement EQS News Service
══════════════════════════════════════════════════════════════════════════
2 fncls.ssp?fn=show_t_gif&application_id=774197&application_name=news&site_id=reuters6
References
Visible links
1. mailto:ir@polymetalinternational.com
============