Feb 29 (Reuters) - Portland General Electric Co POR.N :
* PORTLAND GENERAL ELECTRIC CO - FILED WITH PUBLIC UTILITY
COMMISSION OF OREGON (OPUC) A GENERAL RATE CASE BASED ON A 2025
TEST YEAR (2025 GRC)
* PORTLAND GENERAL ELECTRIC CO - 2025 GRC, AS REQUESTED,
WOULD
RESULT IN AN APPROXIMATE 7.4% OVERALL INCREASE RELATIVE TO
CURRENTLY APPROVED PRICES
* PORTLAND GENERAL ELECTRIC-TOTAL INCREASE IN ANNUAL REVENUE
REQUIREMENT INCLUDES $37 MILLION AS RESULT OF HIGHER NET
VARIABLE POWER COSTS EXPECTED IN 2025
* PORTLAND GENERAL ELECTRIC - REGULATORY REVIEW OF 2025 GRC
WILL
CONTINUE THROUGHOUT 2024, WITH FINAL ORDER TARGETED TO BE ISSUED
BY OPUC BY END OF YEAR
* PORTLAND GENERAL ELECTRIC - NEW CUSTOMER PRICES ARE
EXPECTED TO
BECOME EFFECTIVE JANUARY 1, 2025
* PORTLAND GENERAL ELECTRIC:FILING REQUESTS $225 MILLION
INCREASE
IN ANNUAL REVENUE REQUIREMENT RELATED TO RECOVERY OF COSTS WITH
NON-EMITTING BATTERY PROJECTS
Source text for Eikon: ID:n0000784977-24-000054