March 2 (Reuters) - Purecycle Technologies Inc PCT.O :
* UNDER LOAN AGREEMENT BETWEEN SOUTHERN OHIO PORT AUTHORITY
& CO'S
UNIT, CO WAS REQUIRED TO CAUSE IRONTON FACILITY TO BE COMPLETED
BY DEC 1, 2022
* IRONTON FACILITY NOT COMPLETED BY COMPLETION DATE DUE TO
CHALLENGES FROM DELAYS IN DELIVERY OF CRITICAL COMPONENTS,
SHORTAGES OF MATERIAL, AMONG OTHER THINGS
* ENGAGED IN NEGOTIATIONS WITH GROUP OF BONDHOLDERS HOLDING
ABOUT
70% OF OUTSTANDING SERIES A BONDS & 100% OF OUTSTANDING SERIES B
BONDS
* NEGOTIATIONS CONCERNING IF THERE HAS BEEN DEFAULT UNDER
LOAN
AGREEMENT AS A RESULT OF DELAY IN COMPLETION OF IRONTON FACILITY
Further company coverage: PCT.O