Sept 13 (Reuters) - Purecycle Technologies Inc PCT.O :
* PURECYCLE TECHNOLOGIES- ON SEPTEMBER 3, IRONTON FACILITY
EXPERIENCED SEAL SYSTEM FAILURE IN KEY OPERATION
* PURECYCLE TECHNOLOGIES INC - ON SEPTEMBER 3, 2023,
IRONTON
FACILITY SEAL SYSTEM FAILURE RESULTED IN A LOSS OF BARRIER FLUID
PRESSURE SURROUNDING SEAL
* PURECYCLE TECHNOLOGIES:ON SEPT 7 SAID SEAL FAILURE WAS
RESULT OF
AUG 7 FULL PLANT POWER OUTAGE CAUSED BY FAILURE OF THIRD PARTY
POWER SUPPLY UTILITY
* PURECYCLE TECHNOLOGIES INC - CO'S UNIT PROVIDED NOTICE OF
A
FORCE MAJEURE EVENT PURSUANT TO SECTION 2.4(B)(VI)(C)(VI) OF
LOAN AGREEMENT
* PURECYCLE TECHNOLOGIES INC - CO'S UNIT AND COMPANY ARE
UNABLE TO
ELIMINATE RISK THAT RESTART WILL BE UNSUCCESSFUL AT IRONTON
FACILITY