Nov 13 (Reuters) - Rain Industries Ltd RAID.NS :
* DECLARED AN INTERIM DIVIDEND OF 1 RUPEE PER EQUITY SHARE
* APPROVED SETTING UP OF ANHYDROUS CARBON PELLETS PLANT BY
RAIN
CII CARBON LLC, AT CHALMETTE, LOUISIANA, USA
* APPROVED SET UP OF ANHYDROUS CARBON PELLETS PLANT BY UNIT
TO
MAKE 250,000 MTPA OF ACP, CALCINED CARBON PELLETS AT SEZ,
VISAKHAPATNAM
* SEZ, VISAKHAPATNAM PLANT TO BE SET UP FOR $15 MILLION;
PROJECT
EXPECTED TO BE COMPLETED DURING Q2 2020
* CAPITAL COST OF US $12 MILLION FOR CARBON PELLETS PLANT
* SEPT-QUARTER CONSOL NET PROFIT 1.01 BILLION RUPEES VERSUS
1.90
BILLION RUPEES YEAR AGO