July 16 (Reuters) - Rashtriya Chemicals and Fertilizers Ltd
RSTC.NS :
* RASHTRIYA CHEMICALS AND FERTILIZERS SAYS TROMBAY UNIT
COMMISSIONING OF GAS TURBINE PLANT REVISED TO MARCH 2021 VERSUS
MAY-JUNE 2020
* RASHTRIYA CHEMICALS AND FERTILIZERS - SEEN DELAYS IN
SETTLEMENT
OF SUBSIDY BY GOVERNMENT DUE TO COVID
* RASHTRIYA CHEMICALS AND FERTILIZERS SAYS GOVERNMENT ALLOWS
EXISTING NORMS AT TROMBAY UREA PLANT WITH MINOR PENALTY TILL
SEPTEMBER 30,2020
* RASHTRIYA CHEMICALS AND FERTILIZERS - FURTHER DELAY IN
SUBSIDY
SETTLEMENT TO ADD TO STRESS ON WORKING CAPITAL, BORROWING COSTS
Source text for Eikon: ID:
Further company coverage: RSTC.NS