(Adds comment from Equitrans)
June 23 (Reuters) - The $6.6 billion Mountain Valley
natural gas pipeline from West Virginia to Virginia is on track
to get final permits by Saturday, moving the long-delayed
project closer to re-starting construction.
Some analysts, however, said that even when the pipe enters
service, which could be as soon as the end of 2023, it would
only operate at half capacity or less due to transmission
constraints.
Equitrans Midstream Corp ETRN.N , the lead partner building
Mountain Valley, disputed that half-capacity analysis and noted
that it is normal for gas markets to take time to fully adjust
to new large-scale projects.
Mountain Valley "is not being built for the short term.
(It) will meet increasing gas demand and improve reliability and
affordability for domestic consumers for decades to come,"
Equitrans spokesperson Natalie Cox told Reuters in an email.
Mountain Valley has said it expects to resume construction
after the U.S. Army Corps of Engineers issues a water permit.
That should happen by Saturday as mandated by the Fiscal
Responsibility Act, which ended the debt ceiling crisis.
"We will request the administrative authorizations
necessary to resume full construction in the near future," Cox
said, noting that Mountain Valley continues to target project
completion by year-end 2023.
Mountain Valley is one of several U.S. projects delayed
by regulatory and legal fights with environmental and local
groups in recent years. The pipe is key to unlocking more gas
supplies in Appalachia, the nation's biggest shale gas basin.
But analysts at energy consulting firm East Daley Analytics
said Mountain Valley will only run at about 35% of its 2 billion
cubic feet per day (bcfd) capacity when it is finally built.
That's because the Transcontinental Gas Pipe Line (Transco)
system into which Mountain Valley will connect in Virginia has
limited takeaway capacity, East Daley said.
Transco is owned by U.S. energy company Williams Cos Inc
WMB.N . Officials at Williams were not immediately available
for comment.
Environmental groups, meanwhile, continue to challenge
Mountain Valley's permits in court.
"There is no reason to think they could build and operate
this project safely, and now analysts are saying that if
(Mountain Valley) is completed, it would only run at less than
half capacity," said Caroline Hansley, senior campaign
representative at the Sierra Club, an environmental group
opposed to the pipeline.
When Mountain Valley started construction in February 2018,
Equitrans estimated the 303-mile (488-km) project would cost
about $3.5 billion and enter service by late 2018.
Mountain Valley is owned by units of Equitrans, NextEra
Energy Inc NEE.N , Consolidated Edison Inc ED.N , AltaGas Ltd
ALA.TO and RGC Resources Inc RGCO.O .
(Reporting by Scott DiSavino; Editing by Mark Porter)
((scott.disavino@thomsonreuters.com; +1 332 219 1922; Reuters
Messaging: scott.disavino.thomsonreuters.com@reuters.net))