RNS Number : 8256YRio Tinto PLC14 October 2026Rio Tinto releases third quarter 2026 production results
14 October 2026
Strong operational performance at Oyu Tolgoi copper and Pilbara iron ore
Rio Tinto Chief Executive Simon Trott said: “We delivered strong operational performance in the third quarter. Oyu Tolgoi copper production increased 29% year-to-date, with the operation running at a ~450 kt annualised rate in the quarter, and global iron ore sales are up 3% year-to-date. The Simandou iron ore mine hit an annualised production run-rate of ~10 Mtpa (100% basis) in the quarter as the project continues to ramp up.
“We are finishing the year with momentum, with significant opportunities to accelerate improvements in safety, productivity and reliability through implementation of our operating system. We remain on track for a $1.8 billion annualised productivity benefit run-rate by the end of 2026. Our major projects remain on schedule and budget, underwriting our growth profile to 2030.
“We made further significant steps in decarbonising our business in the third quarter, with our Pacific Aluminium smelter repowering arrangements now well progressed.
“Today, we announce that we have achieved more than $2 billion1 of capital release year-to-date, as we actively manage our portfolio with discipline to maximise long-term value, as part of the $5 to 10 billion capital release program.”
- Executive Summary
• Operational excellence: ~1% YTD increase in copper equivalent (CuEq2) production, driven by growth from Oyu Tolgoi copper and Pilbara iron ore.
• Copper: Oyu Tolgoi production increased by 27% YoY in Q3 and 29% YTD. At Kennecott, we successfully completed the rebuild of the flash converting furnace at end-August ahead of plan.
• Iron ore: Q3 global iron ore sales were 90.8 Mt, up 3% YoY, while Pilbara sales increased 2% YoY. Simandou hit an annualised production run-rate of ~10 Mtpa (100% basis) in Q3 as the project ramps up and remains on track to reach a 60 Mtpa production run-rate during H2 20283.
• Aluminium: Consistent, stable performance across the full operating system. Pacific smelter repowering arrangements are now well progressed, following the Tomago and Bell Bay power agreements in Q3.
• Lithium: Production up 33% YTD despite adverse weather impacting Q3 operations. Fenix 1B ramp-up continues to progress well.
Production and sales4
Q3
2026
vs Q3 2025
vs Q2
20269 MTHS
2026
vs
9 MTHS 2025
2026 guidance12
Guidance status
Copper production (consolidated basis)
kt
205
0 %
-4 %
646
+1 %
800 - 870
Unchanged
Global iron ore production5 (100% basis)
Mt11
89.7
+2 %
+3 %
259.6
+4 %
NA
NA
Pilbara iron ore production (100% basis)
Mt11
83.4
-1 %
0 %
245.7
+3 %
NA
NA
Global iron ore sales6 (100% basis)
Mt11
90.8
+3 %
+2 %
255.3
+3 %
343 - 366
Unchanged
Pilbara iron ore sales7 (100% basis)
Mt11
85.7
+2 %
0 %
243.3
+4 %
323 - 338
Unchanged
Bauxite production
Mt
15.7
-4 %
+4 %
44.2
-6 %
58 - 61
Unchanged
Alumina production8
Mt
2.1
+10 %
+3 %
6.1
+9 %
7.6 - 8.0
Unchanged
Aluminium production9
Mt
0.8
-2 %
0 %
2.52
0 %
3.25 - 3.45
Unchanged
Lithium carbonate equivalent (LCE) production10
kt
13.0
+4 %
-11 %
40.3
+33 %
61 - 64
Unchanged
(at lower end)
1 Announced year-to-date. Completion and cash receipt is subject to entry into binding agreements and satisfaction of conditions precedent. We remain on track to announce around $5 billion in total of capital release initiatives by end 2026. 2 Copper equivalent (CuEq) volume = Rio Tinto’s share of production volume / Volume conversion factor x Product price ($/t) / Copper price ($/t). Prices are based on long-term consensus prices. 3 The estimated annualised capacity of approximately 60 million dry tonnes per annum iron ore for the Simandou life of mine schedule was previously reported in a release to the Australian Securities Exchange (ASX) dated 6 December 2023 titled “Investor Seminar Presentation”. Rio Tinto confirms that all material assumptions underpinning that production target continue to apply and have not materially changed. 4 Rio Tinto share unless otherwise stated. 5 Iron Ore production for Pilbara operations and Iron Ore Company of Canada (IOC) refers to saleable production (after crushing, screening and beneficiation). For Simandou, it represents ore ready for train loading at the SimFer mine gate: final (tertiary) crushing of Simandou ore takes place in China. 6 Includes all shipments from Pilbara and IOC, including those to our Portside trading business; excludes shipments from our Portside trading business. It also includes Simandou sales. At our Dec-2025 Capital Markets Day, we announced the move to guide on global iron ore sales (100%): indicated sales ranges (all on 100% basis) - Pilbara of 323 - 338 Mt, IOC of 15 - 18 Mt and Simandou of 5 - 10 Mt. For the Simandou value chain to China: at full production targeting a ~75-to-90-day cycle, with customer collection up to a further 30 days (mine to recognised sales). 7 Pilbara iron ore sales range remains subject to the timing of approvals for planned mining areas and heritage clearances. 8 QAL production included on a 100% basis. 9 Includes primary aluminium only. 10 Year-to-date 2025 represents production since March following completion of the Arcadium acquisition. Q1 2025 LCE production was 5.6kt (6.5kt on a 100% basis); LCE shipments were 3.8kt (5.0kt on a 100% basis). 11 Wet metric tonnes. 12 See further notes in Section 2, 2026 guidance.
Production/sales guidance is maintained1.
Unit cost guidance is maintained2, 3, 4.
Notes for the quarter:
• Pilbara iron ore unit cash costs: impacts from external factors
◦ Diesel: Higher diesel prices increased unit costs by $0.9/t YTD vs 2025 YTD. Assuming the current spot price of ~$175/bbl for Q4, the full-year impact is expected to increase to $1.1/t.
◦ Foreign exchange: At US$0.70/A$, the full-year impact to unit costs is around $1.0/t relative to the guidance assumption of US$0.67/A$.
2026 Guidance
Pilbara iron ore unit cash costs, free on board (FOB) basis - US$ per wet metric tonne
23.5 - 25.03
Copper C1 net unit costs (Kennecott, Oyu Tolgoi and Escondida) - US cents per lb
30 - 504
1 Guidance remains subject to weather impacts.
2 There will be timing differences between market rates and realised diesel prices due to contractual arrangements.
3 Subject to the impact of higher diesel prices and foreign exchange. Based on Australian dollar exchange rate of 0.67.
4 Gold price assumption is $4,026/oz (spot price as at 30 June 2026).
3. Group update
Expenditure on exploration and evaluation
• YTD pre-tax and pre-divestment expenditure on exploration and evaluation charged to the Income Statement was $692 million compared with $537 million in 2025. Approximately 50% of the spend was by the Copper product group, 28% by central exploration and other operations, and 22% by the Iron Ore product group.
• Copper accounts for the majority of total expenditure on exploration and evaluation (included in the Copper product group and central exploration).
Capital release
We are systematically redeploying capital into higher-returning opportunities. To date, we have entered arrangements to release more than US$2 billion1 for redeployment through our capital allocation framework.
This comprises:
◦ In July, we signed an agreement with Yindjibarndi WaterCo for the proposed sale of the Dampier Seawater Desalination Plant in Western Australia.
◦ We have agreed the sale of land in Kitimat, British Columbia, Canada, to LNG Canada for their Phase II project. Completion expected in Q4.
◦ We have entered into a non-binding arrangement for a lithium sales contract with a pre-payment component.
◦ We have completed a number of smaller non-core asset disposals as part of our ongoing portfolio optimisation.
We are progressing other opportunities, with further announcements expected in 2026 as we deliver the initial ~$5 billion of the $5–10 billion capital release program announced at Capital Markets Day 2025.
1 Announced year-to-date. Completion and cash receipt is subject to entry into binding agreements and satisfaction of conditions precedent.
Middle East conflict
Ongoing disruptions in the Middle East continued to drive volatility in energy and freight markets. Operational impacts to Rio Tinto remained limited, with no material disruption to production or outbound supply chains. Rio Tinto’s fuel availability remained adequate, supported by inventory buffers and alternative sourcing.
Conditions in the Strait of Hormuz remain highly volatile, and we continue to monitor developments and maintain contingency plans for further disruption.
Global economy: global growth moderated slightly through Q3 due to persistent geopolitical and energy market uncertainty. Developed market activity remained strong, supported by ongoing AI-linked investment and resilient manufacturing output.
Chinese economy: domestic economic activity moderated in Q3, with strong export demand and manufacturing activity partly offset by weaker domestic consumption and investment. August’s industrial production grew 5% YoY, driven by a 17% YoY increase in high-tech manufacturing. Policy support remained focused on infrastructure, including grid and AI development.
US economy: growth remained resilient, supported by AI-related investment, broader business spending and consumer demand. Inflation remained elevated, prompting the Federal Reserve to raise interest rates by 25 basis points in September.
Copper
• London Metal Exchange (LME) copper reached a record high of $6.74/lb ($14,850/t) in mid-August, supported by constrained mine supply, strong investor flows and optimism around AI-driven electricity demand. Prices averaged $6.40/lb ($14,110/t) for the quarter.
• Copper mine supply remained constrained during Q3, with major storms in Chile adding to existing supply challenges. DRC production remained relatively resilient despite concerns around sulphur and sulphuric acid availability.
• Uncertainty around potential US tariffs on refined copper cathode imports persisted through Q3, sustaining a premium between Chicago Mercantile Exchange (CME) and LME prices and driving continued US imports above underlying demand.
• The copper concentrate market remained extremely tight in Q3, with spot treatment and refining charges ending the quarter at a record low of -$267/t. High sulphuric acid prices are helping to offset pressure on smelter economics.
Iron ore
• During Q3, iron ore prices were sustained in a narrow band around their $97/dmt 61% delivered (CFR) average. Higher seaborne freight costs compressed producer netbacks, particularly for longer haul Atlantic supply. Seaborne lump premiums rebounded by 33% QoQ, realigning to long-term historical average levels and the marginal cost of sintering in China.
• China's finished steel consumption is estimated to have declined ~4% QoQ and ~2% YoY in Q3, while steel exports increased 3% YoY to a 122 Mt annualised rate, partly offsetting weaker domestic demand and supporting crude steel and pig iron production.
• Seaborne iron ore supply declined 1% QoQ in Q3 in response to elevated operating and freight costs putting pressure on marginal supply. Of note, long-haul shipments outside Australia and Guinea declined by an estimated 8% MoM in September.
• China's domestic iron ore production declined 8% YoY in Q3, affected by flooding, safety inspections and scheduled maintenance.
Aluminium
• LME aluminium averaged $3,226/t in Q3, 23% above the 2025 average but below the four-year high reached in Q2.
• Middle East supply saw some recovery through Q3, with most of the smelting capacity curtailed earlier in the year remaining offline, while Chinese production remained close to its 45 Mt capacity cap.
• The global aluminium market remained in deficit as ex-China demand showed early signs of recovery and reported inventories continued to decline. Regional physical premiums remained elevated, reflecting constrained metal availability and higher freight costs.
• Australian FOB alumina prices increased 8% during Q3 to $355/t as the ex-China market tightened, while Chinese bauxite CIF prices remained supported by elevated Capesize freight costs.
Lithium
• Lithium carbonate prices averaged around $19,000/t in Q3, supported by healthy demand amid announcements of potential supply restarts in Australia and Africa.
• Battery energy storage systems (BESS) remained the strongest source of lithium demand growth, with global shipments increasing 94% YoY in the first eight months of 2026 to an annualised rate of around 1,050 GWh. Total EV sales have moderated as policy support in China and North America continues to unwind.
• Lithium demand is gaining further support from larger battery packs across vehicle models and strong growth in commercial EVs.
Index prices
Start of Q3
(01/07/26)
End of Q3
(30/09/26)
% change
Start - end Q3
Q2 2026 average
Q3 2026 average
% change QoQ
Iron ore ($/dmt CFR China, 61% index)1
98
93
(5) %
105
97
(8) %
Iron ore ($/dmt CFR China, 65% index)2
113
108
(4) %
122
113
(7) %
Copper (LME spot, c/lb)
597
657
+10 %
605
640
+6 %
Aluminium (LME spot, $/t)
3,075
3,204
+4 %
3,571
3,226
(10) %
Lithium carbonate (spot, $/t CIF China, Japan & Korea)3
20,250
16,850
(17) %
22,043
19,022
(14) %
1 Monthly average Platts (CFR) index for 61% iron fines from 1 January 2026.
2 Fastmarkets Iron ore 65% Fe Brazil-origin fines, CFR Qingdao, $/dmt.
3 Fastmarkets index for Lithium carbonate min 99.5% Li2CO3 battery grade.
Rio Tinto production1 (‘000 tonnes)
Q3
2026vs Q3
2025vs Q2
20269 MTHS
2026
vs 9 MTHS
2025
Copper
Kennecott - Refined metal2
12
-10 %
-43 %
66
-31 %
Escondida - Metal in concentrates
63
-29 %
-17 %
216
-18 %
Escondida - Refined metal
16
+18 %
-18 %
53
+25 %
Oyu Tolgoi - Metal in concentrates
114
+27 %
+17 %
312
+29 %
Total copper production (consolidated basis1)
205
0 %
-4 %
646
+1 %
1 Includes Oyu Tolgoi and Kennecott on a 100% consolidated basis, and Escondida on an equity share basis.
2 We continue to process third party concentrate to optimise smelter utilisation, including 5 thousand tonnes of cathode produced from purchased concentrate in Q3 2026, and 25 thousand tonnes YTD. Purchased and tolled copper concentrates are excluded from reported production figures and guidance. Sales of cathodes produced from purchased concentrate are included in reported revenues.
Kennecott
• Q3:
◦ After the flash converting breach in late June 2026, we successfully completed the rebuild - over approximately 70 days - at the end of August and the furnace has since returned to normal capacity. The outage drove lower cathode production in Q3.
◦ Mined copper production increased QoQ on higher throughput, as Q2 was impacted by planned concentrator maintenance and a three-day safety stand-down in April. Grades and recoveries also increased.
◦ As previously disclosed, geotechnical management activities in the open pit are ongoing to restore access to the planned mining areas.
◦ Molybdenum production is expected to fall as planned through the rest of 2026 and into 2027 as the open-pit mining sequence moves into lower-molybdenum-bearing material, while gold production is expected to increase due to higher grades and recovery rates.
• YoY:
◦ Lower cathode production due to the flash converting furnace breach, with mined copper converted into matte and accumulated ahead of the flash converting furnace for subsequent processing to cathode. Note: Q3 2025 production was weak, impacted by a 45-day planned smelter shutdown which commenced in early September.
◦ Higher mined copper due to the timing of the annual concentrator shutdown which occurred in the third quarter in 2025 versus the second quarter in 2026.
Escondida
• Q3: lower concentrate production, reflecting lower throughput caused by scheduled maintenance, a safety stand-down following a fatal incident, planned lower concentrate feed grades and severe weather disruptions.
• YoY: lower concentrate production also reflected planned lower feed grades in line with mine sequence, scheduled maintenance, the safety stand-down and severe weather disruptions, partially offset by higher refined copper production.
Oyu Tolgoi
• Q3: increase in production driven by the continued ramp up of underground operations with higher recoveries.
• YoY: increase in production driven by the ramp up of underground operations, higher ore grades and improved recovery rates. Q3 2025 was impacted by a planned concentrator shutdown; the equivalent shutdown this year occurred in Q2.
• Open pit update: we have recently completed the latest phase of mining in a high gold-grade area of the pit and the next planned phases of the open pit mine sequence contain lower gold grades for the rest of 2026 and into 2027.
• In June 2026, the Government of Mongolia agreed to commence work on resolution of the Entrée licence transfer for Panel 1. As this remains in progress, we continue to advance Panels 0 and 2 North followed by Panel 2 South. Panel 1 is expected to be the final panel brought into production. Mine plan options will continue to be assessed and optimised as appropriate.
• As part of the periodic review required under the Shareholders Agreement, we formally signed the previously agreed adjustment to the Oyu Tolgoi shareholder loan interest rate during Q3.
• Production ramp-up remains on track to reach an average of around 500 thousand tonnes of copper per year (100% basis and stated as recoverable metal) from 2028 to 20361, inclusive of ongoing sustaining capital expenditure associated with ramp-up activities.
1 The ~500 thousand tonnes per annum copper production target (stated as recoverable metal) for the Oyu Tolgoi underground and open pit mines for the years 2028 to 2036 was previously reported in a release to the ASX dated 11 July 2023 “Investor site visit to Oyu Tolgoi copper mine, Mongolia”. All material assumptions underpinning that production target and those production profiles continue to apply and have not materially changed.
Pilbara operations
Rio Tinto share of production (Wet million tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs 9 MTHS
2025
Pilbara Blend and SP10 Lump1
23.2
-3 %
-1 %
69.0
+4 %
Pilbara Blend and SP10 Fines1
32.9
-1 %
+1 %
96.8
+3 %
Robe Valley Lump
1.6
-2 %
-5 %
4.9
0 %
Robe Valley Fines
2.3
+19 %
-6 %
6.8
+10 %
Yandicoogina Fines (HIY)
11.2
+3 %
+3 %
32.4
+4 %
Total Pilbara production
71.2
-1 %
0 %
209.9
+3 %
Total Pilbara production (100% basis)
83.4
-1 %
0 %
245.7
+3 %
Rio Tinto share of sales (Wet million tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs 9 MTHS
2025
Pilbara Blend Lump
17.6
0 %
-1 %
50.4
+31 %
Pilbara Blend Fines
33.0
-1 %
-1 %
94.3
+28 %
Robe Valley Lump
1.3
0 %
-12 %
4.0
+3 %
Robe Valley Fines
2.5
+12 %
-14 %
7.7
+8 %
Yandicoogina Fines (HIY)
11.3
+5 %
0 %
31.0
+1 %
SP10 Lump1
3.4
+16 %
+47 %
8.5
-56 %
SP10 Fines1
5.2
+64 %
+83 %
11.7
-57 %
Total Pilbara sales2
74.3
+4 %
+3 %
207.7
+4 %
Total Pilbara sales (100% basis)2
85.7
+2 %
0 %
243.3
+4 %
Total Pilbara sales (consolidated basis)2, 3
76.2
+4 %
+3 %
213.4
+4 %
Production figures are sometimes more precise than the rounded numbers shown, hence small rounding differences may appear.
1 SP10 includes other lower grade products.
2 Sales includes material shipped from the Pilbara to our portside trading facility in China which may not be sold onwards by the group in the same period.
3 While Rio Tinto has a 53% net beneficial interest in Robe River Iron Associates, it recognises 65% of the assets, liabilities, sales revenues and expenses in its accounts (as 30% is held through a 60% owned subsidiary and 35% is held through a 100% owned subsidiary). The consolidated basis sales reported here include Robe River Iron Associates on a 65% basis to enable comparison with revenue reported in the financial statements.
• Q3 production: strong mine performance continued through Q3 supported by ongoing productivity initiatives.
• Q3 sales: +2% YoY, supported by mine performance and sustained healthy port inventories.
◦ Port outload capacity will be impacted during some quarters in 2027 and 2028 with several scheduled major capital projects underway (including Parker Point reclaimers) to improve system flexibility and prepare for the Rhodes Ridge project.
• Q3 sales: 9% of sales priced by reference to the prior quarter’s average index lagged by one month:
◦ Remainder sold either on current quarter average, month average or on the spot market.
◦ 26% of sales were made on a free on board (FOB) basis, with remainder sold including freight.
• Q3 portside sales in China: 4.7 Mt (4.9 Mt in Q3 2025)
◦ 71% of our portside sales were either screened or blended in Chinese ports.
◦ End-September inventory levels at portside were 3.7 Mt, including 2.4 Mt of Pilbara product.
Iron Ore Company of Canada (IOC)
Production and sales (Wet million tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs
2025
Pellets and concentrate production (Rio Tinto Share)
2.2
-5 %
+30 %
6.0
-16 %
Pellets and concentrate production (100%)
3.8
-5 %
+30 %
10.2
-16 %
Pellets and concentrate sales1 (100%)
3.8
-6 %
+20 %
10.2
-14 %
1 Sales includes material shipped from IOC to our portside trading facility in China which may not be sold onwards by the group in the same period.
• Q3 production: up 30% QoQ (down 5% YoY). Operational focus remains on progressively improving pit health. This has been supported by mine sequencing and an increase in total material movement.
• Q3 sales: up 20% QoQ (down 6% YoY) reflecting higher concentrator feed and a return to normal in-load rates at the port following the ore dumper replacement.
Simandou
Production and sales (Wet million tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs
2025
Fines production (Rio Tinto share)1,2
1.1
NA
+273 %
1.7
NA
Fines production (100%)1,2
2.5
NA
+273 %
3.7
NA
Fines shipped (100%)
2.2
NA
+36 %
4.4
NA
Fines sales (100%)
1.3
NA
+210 %
1.7
NA
1 Simandou production represents ore ready for train loading at the SimFer mine gate.
2 2.3 Mt (100% SimFer) of crushed iron ore (1 Mt, Rio Tinto share) was produced in 2025 and was recorded for the first time in Q4 2025, some of which required reprocessing in 2026.
• Q3 production: a ~10 Mtpa (100%) production run-rate was achieved in Q3. Fixed-plant commissioning and operational readiness continued to progress as planned, supporting the transition to permanent plant infrastructure in Q4.
• Stockpiles: as at the end of September, 7.9 Mt of uncrushed ore was stockpiled at the mine, which contributes to 11.1 Mt across the entire system including the Guinean port, on ships and in China ports.
• Q3 sales: 2.2 Mt (100%) was shipped to China and sales totalled 1.3 Mt.
◦ Simandou value chain to China: at full production targeting a ~75-to-90-day cycle, with customer collection up to a further 30 days (mine to recognised sales).
Aluminium
Rio Tinto share of production (‘000 tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs 9 MTHS
2025
Bauxite
15,745
-4 %
+4 %
44,225
-6 %
Bauxite third party shipments1
11,574
-2 %
+9 %
31,409
-5 %
Alumina2
2,071
+10 %
+3 %
6,111
+9 %
Aluminium
842
-2 %
0 %
2,518
0 %
Recycled aluminium
69
+3 %
-1 %
200
-4 %
1 Reminder: Sangaredi's third-party bauxite shipments for 2025 and Q1 2026 were restated following a reclassification between internal and third-party shipments. This has no impact on total bauxite shipments.
2 As stated in our Q1 2026 report, we have included QAL on a 100% basis from 2026.
Bauxite
• Q3: production increased 4% QoQ, as Weipa operations continued to recover from the Q1 weather disruption, partially offset by timing of a major maintenance on the off-loading line (10 days) at CBG (Sangaredi) in Guinea. Production was 4% lower YoY, primarily reflecting planned shutdowns at Weipa in August.
Alumina
• Q3: production increased 3% QoQ, with reliability improving at QAL, Yarwun and Vaudreuil. Production increased 10% YoY, primarily reflecting QAL being reported on a 100% basis from 2026.
• Yarwun production is expected to reduce by 40% in Q4 2026, as announced in November 2025, due to tailings constraints. The change is expected to reduce annual production by approximately 1.2 Mt and extend the refinery life to 2035.
Aluminium
• Q3: production was stable QoQ (down -2% YoY) with the completion of the planned Arvida smelter closure offset by improved performance across the remaining portfolio.
◦ Kitimat: production increased YoY as the smelter operated at higher pot and amperage levels, supported by improved underlying performance and reservoir levels.
◦ Boyne: production increased YoY, reflecting improved operating stability and higher output.
◦ AP60 and Arvida: AP60 continued to ramp up, while the final Arvida potlines closed in June 2026 as planned.
• Pacific smelter repowering arrangements: now well progressed, following the Tomago and Bell Bay power agreements in Q3 (see further details on page 18).
Tariffs
• Q3: all produced metal was shipped, with sales pricing, product mix and shipping destinations flexed to optimise outcomes in a changing market environment.
H1 2026
Q3 2026
Total RTA shipments - US destination, kt1
585
255
Total RTA tariff cost, $m
773
430
Average mid-west premium duty paid2, $/tonne
2,406
2,420
Average realised tariff costs - US destination, $/tonne
1,322
1,685
1 Including both tariff impacted and exempt products.
2 Mid-west premium duty paid applies to approximately 32% of our total volumes in Q3 2026.
Recycled aluminium
• Q3: recycled aluminium production was broadly stable QoQ and increased 3% YoY. Improved output at the remaining US facilities more than offset lower Canadian production. YTD volumes remained 4% below 2025, reflecting the closure of the Canton, Ohio facility in mid-2025 as part of the reshaping of the downstream portfolio.
Lithium
Rio Tinto share of production (‘000 tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
9 MTHS
2025
vs 9 MTHS
2025
Lithium carbonate
12.2
+9 %
-12 %
38.4
26.7
+44 %
Lithium hydroxide
5.8
-4 %
+9 %
16.6
13.3
+25 %
Spodumene
0.0
NA
NA
0.0
9.1
NA
Other specialities (LCE)
1.2
-32 %
+11 %
3.0
3.4
-10 %
Total lithium carbonate equivalent (LCE) production1,2
13.0
+4 %
-11 %
40.3
30.4
+33 %
1 The lithium value chain is vertically integrated and as a result production volumes are not additive. Lithium Carbonate Equivalent (LCE) is derived from volumes of lithium carbonate, lithium chloride, and spodumene concentrate. These compounds are used as feedstock in downstream production.
2 Year-to-date 2025 represents production since March following completion of the Arcadium acquisition. Q1 2025 LCE production was 5.6kt (6.5kt on a 100% basis); LCE shipments were 3.8kt (5.0kt on a 100% basis).
• Q3: impacted by planned maintenance and weather.
◦ Olaroz: production was affected by planned annual maintenance and lower lithium concentration in the ponds following weather events.
◦ Fenix: line 1B ramp-up is progressing well. Planned annual maintenance on Lines 0 and 1A, and severe weather in July, affected production during the quarter.
◦ Sal de Vida: ramp-up is progressing slower than anticipated due to available uptime of key equipment.
• YTD: 2025 YTD reflects Mt Cattlin in operation in Q1 2025 (now in care and maintenance since end of March 2025).
• To note: full year production expected at the low end of the guidance range, primarily reflecting the slower ramp-up at Sal de Vida.
Rio Tinto share of production (’000 tonnes)
Q3
2026
vs Q3
2025vs Q2
20269 MTHS
2026
vs 9 MTHS
2025
Borates - B2O3 content
132
+3 %
-4 %
396
+5 %
Titanium dioxide slag - TiO2
217
-17 %
-4 %
662
-12 %
We are advancing our strategic reviews and are actively testing the market for our Borates business and evaluating options for Rio Tinto Iron & Titanium.
Borates
• Q3: delivered solid production supported by continued strong market conditions.
Iron & Titanium
• Q3: continued to align production with market demand, operating six (of nine) furnaces in Quebec and three (of four) furnaces at Richards Bay Minerals.
9. Capital Projects
Project
Total
capital cost
(100% unless
otherwise stated)
Status/Milestones
Copper
Project: Kennecott open pit extension
Location: Utah, United States
Ownership: Rio Tinto (100%)
Approval: 2019
To note: The project scope includes mine stripping activities and some infrastructure development, including tailings facility expansion. The project will allow mining to continue into a new area of the orebody between 2026 and 2032.
$1.8bn
• Stripping will continue through 2027 with sustainable ore production from the second phase of the pushback expected to be reached in H2 2027.
Project: Kennecott North Rim Skarn (NRS) underground development1
Location: Utah, United States
Ownership: Rio Tinto (100%)
Capacity: around 250 kt through to 20332 Approval: June 2023
First production: Achieved Q4 2025
To note: Original approval for $0.5bn with a further $0.1bn approved in December 2024 for additional infrastructure and geotechnical controls.
$0.6bn
• Through to early September, underground production continued to ramp-up, with improving stope availability and higher ore movement through the quarter, while development advanced into more favourable ground conditions.
• A seismic event occurred on 10 September. The mine plan sequence and potential impacts are being assessed following an external geotechnical review.
Iron ore
Project: Brockman (Brockman Syncline 1)
Location: WA, Australia
Ownership: 100%
Capacity: 34 Mtpa
Approval: March 2025
Planned first production: 2027
To note: The project is to extend the life of the Brockman regions in WA.
$1.8bn
• Bulk earthworks progressed, with the final supporting infrastructure package, the administration building, awarded in July 2026.
• Critical path items advancing, focus shift to construction execution and module delivery management.
• First production remains on track for 2027.
Project: Hope Downs 2 (incl. Bedded Hilltop)
Location: WA, Australia
Ownership: Rio Tinto (50%) and Hancock Prospecting (50%)
Capacity: 31 Mtpa
Approval: June 2025
Planned first production: 2027
To note: The project is to extend the life of the Hope Downs 1 operation in WA.
$0.8bn
(Rio Tinto share)
• Construction remains ahead of plan, with strong progress across civil works, haul roads and non-process infrastructure.
• Key infrastructure delivered - Hope Downs 2 Satellite Facility, Great Northern Highway realignment opening.
• First production from haulage remains on track for 2027.
Project: West Angelas Sustaining
Location: WA, Australia
Ownership: Rio Tinto (53%), Mitsui Iron Ore (33%) and Nippon Steel (14%)
Capacity: 35 Mtpa
Approval: October 2025
Planned first production: 2027
To note: The project is to extend the life of the West Angelas hub in WA.
$0.4bn
(Rio Tinto share)
• Construction activities progressed in line with plan.
• All major contracts awarded with non-process infrastructure and services contractors mobilised to site in Q3 2026.
• First production remains on track for 2027.
Project
Total
capital cost
(100% unless
otherwise stated)
Status/Milestones
Iron ore
Project: Simandou
Location: Guinea, Africa
SimFer mine ownership: SimFer (85%), Government of Guinea (GoG) (15%)
SimFer mine capacity: 60 Mtpa3 (27 Mtpa RT share)
Approval: July 2024
Start date: first shipment in December 2025
To note: Investment in the Simandou high-grade iron ore project in Guinea in partnership with CIOH, a Chinalco-led consortium (the SimFer joint venture) and co-development of the rail and port infrastructure with Winning Consortium Simandou4 (WCS), Baowu and the Republic of Guinea (the partners) for the export of up to 120 Mtpa of iron ore mined by SimFer's and WCS's respective mining concessions.5 The SimFer joint venture6 will develop, own and operate a 60 Mtpa3 mine in blocks 3 & 4. WCS will construct the project's ~536 kilometre shared dual track main line, a 16 kilometre spur connecting its mine to the mainline as well as the WCS barge port, while SimFer will construct the ~70 kilometre spur line, connecting its mining concession to the main rail line, and the transhipment vessel (TSV) port.
$6.2bn
(Rio Tinto
share)
• Ore continues being railed from the SimFer mine to the main rail line via the SimFer rail spur and shipped through the WCS port while construction of the SimFer port is finalised. Commissioning of key infrastructure remains targeted through 2026, supporting ramp up towards full production rates during H2 2028.
• Non-managed infrastructure – our partners confirm that construction is progressing well and is on track.
• SimFer mine is progressing to plan, with ~84% completed - bulk earthworks and permanent facilities construction continues, with load commissioning and first ore through one of the two primary crushers expected in Q4 2026.
• SimFer rail infrastructure locomotive fleet continuing to expand in-line with plan to support production ramp-up.
• SimFer port and marine infrastructure continue to progress to plan with 92% completed - fabrication and assembly of trans-shipment vessels advancing with the first vessel arriving into Guinea late in the quarter. As part of commissioning activities, first ore through the Simfer port is expected in Q4 2026.
• Workforce across all the SimFer scope of mine, rail and port is 17,430 with 75% Guinean participation.
Aluminium
Project: Low-carbon AP60 aluminium smelter
Location: Quebec, Canada
Ownership: Rio Tinto (100%)
Capacity: Project will add 96 new AP60 pots, increasing AP60 capacity by 160,000 tonnes of primary aluminium per annum
Approval: June 2023
Start date: First hot metal achieved in March 2026.
To note: The investment includes up to $113 million of financial support from the Quebec government. This new capacity is expected to be in addition to 30,000 tonnes of new recycling capacity at Arvida, which has been rescheduled to open in H1 2027.
$1.5bn
• Construction is nearing completion and demobilisation is underway.
• Pot commissioning and ramp-up will continue through 2026, with full capacity targeted during 2027.
Lithium
Project: Rincon expansion
Location: Salta province, Argentina
Ownership: Rio Tinto (100%)
Capacity: 60ktpa (battery grade lithium carbonate)
Approval: December 2024
Planned first production: 2028 with three-year ramp-up to full capacity
To note: Project consists of the 3ktpa starter plant and 57ktpa expansion program. The mine is expected to have a 40-year7 life and operate in the first quartile of the cost curve.
$2.5bn
• Construction is progressing across key areas, including major earthworks, concrete, tanks, and supporting infrastructure. The camp expansion is substantially complete, and first powerline has been energised.
• First production remains on track for 2028.
Project
Total
capital cost
(100% unless
otherwise stated)
Status/Milestones
Lithium
Project: Nemaska Lithium
Location: Quebec, Canada
Ownership: Rio Tinto (53.9%) and Government of Québec (46.1%).
Capacity: 28ktpa LCE (100%)
First production: planned in 2028
To note: product is integrated lithium hydroxide.
$1.1bn
(Rio Tinto share)
• Following the in-depth review of the Bécancour project, construction activity remains at reduced levels, while asset preservation and site integrity activities continue.
• The strategic review of the Whabouchi and Galaxy development alternatives continues with our partners, with a decision expected in Q4 2026.
Iron & Titanium
Project: Zulti South
Location: Richards Bay, South Africa
Ownership: Rio Tinto (74%), Blue Horizon Investments (24%) and Employee Share Participation Trust (ESPS) (2%)
Capacity: Extend mine life to 2050
Approval: March 2026
Planned first production: Q4 2028
To note: Construction commenced in H1 2026 and will take 30 months to be completed with initial commercial production expected in Q4 2028. This first phase will support Richards Bay Mineral’s (RBM’s) supply of zircon and ilmenite, while the second phase will follow as part of the long-term development strategy.
$0.35bn
(Rio Tinto share)
• Early construction and site establishment continue to advance.
- The NRS Mineral Resources and Ore Reserves, together with the Lower Commercial Skarn (LCS) Mineral Resources and Ore Reserves, form the Underground Skarns Mineral Resources and Ore Reserves.
- The 250 thousand tonne copper production target for the Kennecott underground mines over the years 2023 to 2033 was previously reported in a release to the Australian Securities Exchange (ASX) dated 20 June 2023 "Rio Tinto invests to strengthen copper supply in US”. All material assumptions underpinning that production target continue to apply and have not materially changed.
- The estimated annualised capacity of approximately 60 million dry tonnes per annum iron ore for the Simandou life of mine schedule was previously reported in a release to the Australian Securities Exchange (ASX) dated 6 December 2023 titled “Investor Seminar Presentation”. Rio Tinto confirms that all material assumptions underpinning that production target continue to apply and have not materially changed.
- WCS is the holder of Simandou North Blocks 1 & 2 (with the Government of Guinea holding a 15% interest in the mining vehicle and WCS holding 85%) and associated infrastructure. WCS was originally held by WCS Holdings, a consortium of Singaporean company, Winning International Group (50%) and Weiqiao Aluminium (part of the China Hongqiao Group) (50%). On 19 June 2024, Baowu Resources completed the acquisition of a 49% share of WCS mine and infrastructure projects with WCS Holdings holding the remaining 51%. In the case of the mine, Baowu also has an option to increase to 51% during operations. During construction, SimFer will hold 34% of the shares in the WCS infrastructure entities with WCS holding the remaining 66%.
- WCS holds the mining concession for Blocks 1 & 2, while SimFer holds the mining concession for Blocks 3 & 4. SimFer and WCS will independently develop their mines.
- SimFer Jersey Limited is a joint venture between the Rio Tinto Group (53%) and Chalco Iron Ore Holdings Ltd (CIOH) (47%), a Chinalco-led joint venture of leading Chinese SOEs (Chinalco (75%), Baowu (20%), China Rail Construction Corporation (2.5%) and China Harbour Engineering Company (2.5%)). SimFer S.A. is the holder of the mining concession covering Simandou Blocks 3 & 4, and is owned by the Guinean State (15%) and SimFer Jersey Limited (85%). SimFer Infraco Guinée S.A. will deliver SimFer’s scope of the co-developed rail and port infrastructure, and is co-owned by SimFer Jersey (85%) and the Guinean State (15%). SimFer Jersey will ultimately own 42.5% of La Compagnie du Transguinéen, which will own and operate the co-developed infrastructure during operations.
- The production target of approximately 53 kt of battery grade lithium carbonate per year for a period of 40 years was previously reported in a release to the ASX dated 4 December 2024 titled “Rincon Project Mineral Resources and Ore Reserves: Table 1”. Rio Tinto confirms that all material assumptions underpinning that production target continue to apply and have not materially changed. Plans are in place to build for a capacity of 60 kt of battery grade lithium carbonate per year with debottlenecking and improvement programs scheduled to unlock this additional throughput. Capacity of 60ktpa is comprised of 3ktpa starter plant, 50ktpa full scale plant and 7ktpa additional optimisation.
Project
Status
Copper: Resolution
Location: Arizona, US
Ownership: Rio Tinto (55%), BHP (45%)
To note: proposed underground copper mine in the Copper Triangle, in Arizona.
• Surface resource delineation and definition drilling are ongoing; additional rigs planned for November 2026 and January 2027.
• Underground cover-hole drilling commenced on 31 August, two months ahead of plan, with completion expected by end-October.
• Underground enabling works to upgrade the existing infrastructure in Shafts 9 and 10 in preparation for material handling associated with underground development are progressing.
• Engineering work to enable procurement of long lead items (power, hoisting) continue to advance following completion of the land exchange.
• Land exchange commitments/benefits and engagement with Native American Tribes, local communities and regulators continue to progress. This includes a $54M Native American Trust.
• On 29 September, the Ninth Circuit declined an en banc challenge to the land exchange; further appeal to the US Supreme Court remains possible.
Copper: Winu
Location: WA, Australia
Ownership: Rio Tinto (70%), Sumitomo Metal Mining (SMM) (30%)
To note: In late 2017, we discovered copper-gold mineralisation at the Winu project (Paterson Province in Western Australia). In 2021, we reported our first Indicated Mineral Resource. The pathway remains subject to regulatory and other required approvals. Project Agreement negotiations with the Martu Traditional Owner Group remains our priority.
• The Project Agreement with Nyangumarta Warrarn Aboriginal Corporation was signed on 8 September 2026, marking a key project milestone.
• The EPA released the Environmental Review Document for public review on 27 August 2026; the review period closes on 22 October 2026.
• The mining lease was granted on the 22 September 2026.
• The feasibility study for processing capacity up to 10 Mtpa remains on track for completion around the end of 2026.
• Discussions continue with the Martu Traditional Owner Group to secure airstrip and water access.
• Full potential exploration drilling underway.
Copper: La Granja
Location: Cajamarca, Peru
Ownership: Rio Tinto (45%), First Quantum Minerals (55%)
To note: In August 2023, we completed a transaction to form a joint venture with First Quantum Minerals (FQM) that will work to unlock the development of the La Granja project, one of the largest undeveloped copper deposits in the world, with potential to be a large, long-life operation. FQM acquired its stake for $105m. It will invest up to a further $546m into the joint venture to sole fund capital and operational costs to take the project through a feasibility study and toward development.
• Project development continues to focus on advancing permitting, baseline environmental and social studies and stakeholder engagement, following publication of the updated Mineral Resource in May 20261.
Iron Ore: Rhodes Ridge
Location: WA, Australia
Ownership: Rio Tinto (50%), Mitsui & Co. (40%), AMB Holdings Pty Ltd (10%)2
Capacity: 40 to 50 Mtpa
First ore: end of decade
To note: The Rhodes Ridge Joint Venture has approved a feasibility study to progress development of the first phase of the Rhodes Ridge project. The feasibility study will assess development of an operation with initial annual production capacity of 40 to 50 Mtpa. This study commenced in Q1 2026 as planned, and is expected to conclude in 2029. The development will use Rio Tinto’s rail, port and power infrastructure.
Following completion of the pre-feasibility study and with the environmental referral planned, we aim to progress toward reporting an initial Ore Reserve for Rhodes Ridge in 2026, contingent on continued review of all relevant modifying factors.
• The feasibility study remains on track to be completed in 2029 subject to relevant approvals.
Project
Status
Aluminium: Arctial partnership
Location: Finland
To note: Partnership agreement formed in 2025 with the Swedish investment company Vargas, Mitsubishi Corporation and other international and local industry partners to study a low carbon aluminium greenfield opportunity in Finland. As the strategic industrial partner, Rio Tinto will provide the Arctial partnership with access to its proven industry-leading AP60 technology and assist in what would be the first AP60 deployment in an aluminium smelter outside Quebec, Canada.
• The JV partners approved progressing the Arctial project into feasibility stage in Q3. A study team has been mobilised in Finland and work is underway.
• Engagements on environmental permits continue to progress in parallel.
Aluminium: Kangwinan
Location: Queensland, Australia
To note: Proposed expansion to increase annual bauxite production capacity from Rio Tinto’s Weipa Southern operations, by up to 20 million tonnes, in addition to the current 23 million tonnes, and expand export capacity through the Amrun port. This would largely replace the tonnages lost when Gove and Andoom come to the end of their mine lives. Early works commenced in May 2025, with first production targeted as early as 2029.
• Continuing to progress through studies, approvals and early works. Final investment decision expected in Q4 2026.
Lithium: 30 in 30
Location: Argentina future hubs
• Developing the blueprint in 2026 for two future hubs, targeting $30/kg capital intensity with a 30-month timeline for development and <$5/kg C1 operating costs.
Lithium: Maricunga and Altoandinos
Location: Atacama region, Chile
To note: Binding agreement to form a joint venture (JV) with Codelco to develop and operate the high-grade Salar de Maricunga project. Binding agreement with ENAMI to form a JV to develop the Salares Altoandinos project.
• Agreement closure expected in late 2026 / early 2027 (for both Maricunga and Altoandinos), subject to receipt of all applicable regulatory approvals and satisfaction of other customary closing conditions.
- The La Granja Mineral Resource estimate is sourced from First Quantum Minerals Ltd. Quote from the First Quantum release: “the Report was prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) with an effective date of December 31, 2025.”
- Mitsui holds its 40% interest through an entity named SPC Blue Pty Ltd and AMB holds its 10% interest through Rhodes Ridge Mining (No 1) Pty Ltd, a wholly owned subsidiary of Wright Prospecting Pty Ltd, that is managed and controlled by AMB.
11. Exploration and evaluation
Commodities
Advanced projects
Greenfield/ Brownfield programs
QoQ change
Copper
Nuevo Cobre, Chile
Comita, Colombia
Greenfield: Argentina1, Angola, Australia, Canada, Chile, China, Colombia, Kazakhstan, Peru, Papua New Guinea, Serbia1, Türkiye1, USA and Zambia
Activities concluded in Laos.
Strategic investment in Mogotes Metals relating to their Filo Sur1 project in Argentina.
Iron Ore
Pilbara, Australia
Greenfield and Brownfield: Pilbara, Australia
NA
Bauxite
Greenfield: Australia
NA
Lithium
Greenfield: Australia
Activities concluded in Rwanda.
Other
Chiri, Angola (diamonds)
Kasiya1, Malawi (titanium) removed as project as part of strategic review
- Non-operated.
• Overall, Rio Tinto has a strong portfolio of exploration projects with activity in 13 countries across five commodities. During the quarter, Rio Tinto continued to progress a range of high-quality copper exploration opportunities. This included making a strategic investment in Mogotes Minerals and forming a strategic & technical alliance covering the Filo Sur copper project in Argentina.
12. Third quarter public releases
22 July 2026 | Rio Tinto signs bio pellet supply agreement for Gladstone alumina refineries
27 July 2026 | Rio Tinto and WA Government sign agreements with Yindjibarndi WaterCo for proposed sale of Dampier Seawater Desalination Plant
29 July 2026 | Rio Tinto: Step-change in performance delivering higher shareholder returns
12 August 2026 | Perth Lynx and Rio Tinto strengthen commitment to growing basketball in WA
13 August 2026 | Rio Tinto welcomes agreement to secure long-term future of Tomago Aluminium
22 August 2026 | Perth Wildcats and Rio Tinto launch new elite development pathway for Pilbara basketballers
22 August 2026 | Rio Tinto celebrates 60 years in Western Australia
8 September 2026 | Ngarlawangga Aboriginal Corporation and Rio Tinto sign Interim Modernised Agreement
10 September 2026 | Nyangumarta Warrarn Aboriginal Corporation and Rio Tinto sign milestone agreement for Winu Project
15 September 2026 | Perth Wildcats and Rio Tinto strengthen partnership with three-year extension
21 September 2026 | Colours of our Country returns for its 21st year
22 September 2026 | ALNF and Rio Tinto partner to strengthen First Nations languages
28 September 2026 | Shougang Group and Rio Tinto commission an industrial-scale carbon capture trial facility for blast furnace gas
28 September 2026 | Rio Tinto and RevoCast partner to expand low-carbon aluminium billet supply in North America
Contacts
Please direct all enquiries to media.enquiries@riotinto.com
Media Relations,
United Kingdom
Matthew Klar
M +44 7796 630 637
David Outhwaite
M +44 7787 597 493
Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Alyesha Anderson
M +61 434 868 118
Rachel Pupazzoni
M +61 438 875 469
Bruce Tobin
M +61 419 103 454
Media Relations,
Canada
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152
Media Relations,
US & Latin America
Jesse Riseborough
M +1 202 394 9480
Investor Relations,
United Kingdom
Rachel Arellano
M +44 7584 609 644
Laura Brooks
M +44 7826 942 797
Weiwei Hu
M +44 7825 907 230
Investor Relations, Australia
Tom Gallop
M +61 439 353 948
Eddie Gan-Och
M +61 477 599 714
Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885
Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404
This announcement is authorised for release to the market by Matthew Whyte, Rio Tinto’s Group Company Secretary.
riotinto.com
UK LEI: 213800YOEO5OQ72G2R82
AU LEI: 529900X2VMAQT2PE0V24
Classification: 3.1 Additional regulated information required to be disclosed under the laws of a Member State
Forward-looking statements
This announcement includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical facts included in this announcement, including, without limitation, those regarding Rio Tinto’s financial position, production guidance, business strategy, plans and objectives of management for future operations (including development plans and objectives relating to Rio Tinto’s products, production forecasts and reserve and resource positions), are forward-looking statements. The words “intend”, “aim”, “project”, “anticipate”, “estimate”, “plan”, “believes”, “expects”, “may”, “should”, “will”, “target”, “set to” or similar expressions, commonly identify such forward-looking statement.
Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rio Tinto, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such forward-looking statements are based on numerous assumptions regarding Rio Tinto’s present and future business strategies and the environment in which Rio Tinto will operate in the future. A discussion of the important factors that could cause Rio Tinto’s actual results, performance or achievements to differ materially from those in the forward-looking statements can be found in Rio Tinto’s most recent Annual Report and accounts in Australia and the United Kingdom and the most recent Annual Report on Form 20-F filed with the United States Securities and Exchange Commission (the “SEC”) or Form 6-Ks furnished to, or filed with, the SEC. Forward-looking statements should, therefore, be construed in light of the risk factors discussed in such documents, and undue reliance should not be placed on forward-looking statements. These forward-looking statements speak only as of the date of this announcement. Rio Tinto expressly disclaims any obligation or undertaking (except as required by applicable law, the UK Listing Rules, the Disclosure Guidance and Transparency Rules of the Financial Conduct Authority and the Listing Rules of the Australian Securities Exchange) to release publicly any updates or revisions to any forward-looking statement contained herein to reflect any change in Rio Tinto’s expectations with regard thereto or any change in events, conditions or circumstances on which any such statement is based.
Nothing in this announcement should be interpreted to mean that future earnings per share of Rio Tinto plc or Rio Tinto Limited will necessarily match or exceed its historical published earnings per share. Past performance cannot be relied on as a guide to future performance.
Rio Tinto share of production
Quarter
9 Months
% change
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
2025
9 MTHS
2026
9 MTHS
Q3 26
vs
Q3 25
Q3 26
vs
Q2 26
9 MTHS 2026
vs
9 MTHS 2025
Principal commodities
Alumina
('000 t)
1,888
1,969
2,038
2,002
2,071
5,623
6,111
+10 %
+3 %
+9 %
Aluminium (Primary)
('000 t)
857
852
835
841
842
2,528
2,518
-2 %
0 %
0 %
Bauxite
('000 t)
16,392
15,397
13,281
15,200
15,745
47,002
44,225
-4 %
+4 %
-6 %
Copper (consolidated)
('000 t)
204
240
229
213
205
643
646
0 %
-4 %
+1 %
Iron Ore (a)
('000 t)
74,168
80,515
70,045
72,949
74,573
210,124
217,567
+1 %
+2 %
+4 %
Lithium carbonate equivalent (LCE) (b)
('000 t)
12.5
15.4
12.7
14.6
13.0
30.4
40.3
+4 %
-11 %
+33 %
Other Metals & Minerals
Borates
('000 t)
128
124
128
137
132
377
396
+3 %
-4 %
+5 %
Diamonds
('000 cts)
1,137
1,112
1,041
33
0
3,317
1,074
-100 %
-100 %
-68 %
Gold (consolidated)
('000 oz)
167.8
205.8
175.1
159.5
169.1
413.5
503.8
+1 %
+6 %
+22 %
Molybdenum
('000 t)
1.3
1.7
2.5
1.5
0.9
3.5
4.9
-31 %
-38 %
+41 %
Salt
('000 t)
1,197
1,342
951
1,176
828
3,408
2,955
-31 %
-30 %
-13 %
Silver - mined
('000 oz)
1,233
1,650
1,777
1,336
1,474
3,866
4,587
+20 %
+10 %
+19 %
Silver - refined
('000 oz)
254
439
632
327
335
1,399
1,293
+32 %
+2 %
-8 %
Titanium dioxide slag
('000 t)
261
222
218
227
217
753
662
-17 %
-4 %
-12 %
Throughout this report, figures in italics indicate adjustments made since the figure was previously quoted on the equivalent page or reported for the first time. Production figures are sometimes more precise than the rounded numbers shown, hence small differences may result between the total of the quarter figures and the year to date figures.
(a) Iron Ore production for Pilbara operations and Iron Ore Company of Canada refers to saleable production (after crushing, screening and beneficiation). For Simandou, it represents ore ready for train loading at the SimFer mine gate: final (tertiary) crushing of Simandou ore takes place in China. Simandou value chain to China : at full production targeting a ~75-to-90-day cycle, with customer collection up to a further 30 days (mine to recognised sales).(b) Year-to-date 2025 represents production since March following completion of the Arcadium acquisition. Q1 2025 LCE production was 5.6kt (6.5kt on a 100% basis); LCE shipments were 3.8kt (5.0kt on a 100% basis).
Rio Tinto
interestQ3
2025Q4
2025Q1
2026Q2
2026Q3
20269 MTHS
20259 MTHS
2026
ALUMINA
Production ('000 tonnes)
Jonquière (Vaudreuil)
100 %
323
351
349
322
332
1,018
1,003
Jonquière (Vaudreuil) specialty Alumina plant
100 %
26
29
28
28
31
81
87
Queensland Alumina
80 %
697
710
839
859
898
2,081
2,596
São Luis (Alumar)
10 %
98
98
98
97
96
281
291
Yarwun
100 %
743
781
724
695
715
2,162
2,134
Rio Tinto total alumina production
1,888
1,969
2,038
2,002
2,071
5,623
6,111
ALUMINIUM
Primary production ('000 tonnes)
Australia - Bell Bay
100 %
49
48
47
47
48
142
142
Australia - Boyne Island
74 %
94
93
91
92
95
277
278
Australia - Tomago
52 %
75
76
73
74
76
220
222
Canada - six wholly owned
100 %
397
386
378
379
374
1,176
1,132
Canada - Alouette (Sept-Îles)
40 %
60
63
63
63
63
183
190
Canada - Bécancour
25 %
30
30
29
29
29
88
87
Iceland - ISAL (Reykjavik)
100 %
51
52
52
53
53
150
157
New Zealand - Tiwai Point
100 %
82
83
82
83
84
232
249
Oman - Sohar
20 %
20
20
20
20
20
60
60
Rio Tinto total primary aluminium production
857
852
835
841
842
2,528
2,518
Recycled production ('000 tonnes)
Matalco
50 %
68
62
61
70
69
207
200
Rio Tinto total recycled aluminium production
68
62
61
70
69
207
200
BAUXITE
Production ('000 tonnes) (a)
Gove
100 %
3,244
3,040
3,109
3,229
3,154
9,688
9,491
Porto Trombetas
22 %
690
659
523
578
685
1,884
1,786
Sangaredi
(b)
1,671
1,676
1,746
1,986
1,610
5,988
5,342
Weipa
100 %
10,788
10,021
7,903
9,407
10,296
29,442
27,605
Rio Tinto total bauxite production
16,392
15,397
13,281
15,200
15,745
47,002
44,225
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets.
(b) Rio Tinto has a 22.95% shareholding in the Sangaredi mine but benefits from 45.0% of production.
Rio Tinto share of production
Rio Tinto
interestQ3
2025Q4
2025Q1
2026Q2
2026Q3
20269 MTHS
20259 MTHS
2026
BORATES
Production ('000 tonnes B2O3 content)
Rio Tinto Borates - borates
100 %
128
124
128
137
132
377
396
COPPER
Mine production ('000 tonnes) (a)
Bingham Canyon
100 %
18.5
38.4
34.7
20.2
33.7
86.7
88.6
Escondida
30 %
96.7
89.9
88.7
84.2
75.8
291.8
248.8
Oyu Tolgoi
66 %
58.9
68.6
67.1
63.9
74.9
159.2
205.9
Rio Tinto total mine production
174.1
196.9
190.5
168.3
184.5
537.8
543.3
Refined production ('000 tonnes)
Escondida
30 %
14.0
14.0
16.4
19.9
16.4
42.1
52.8
Kennecott (b)
100 %
13.0
38.4
34.0
20.4
11.7
95.2
66.0
Rio Tinto total refined production
27.0
52.4
50.5
40.3
28.0
137.3
118.8
Copper production – consolidated basis (‘000 tonnes)
Kennecott (b) - Production of refined metal
13.0
38.4
34.0
20.4
11.7
95.2
66.0
Escondida - Mill production (metal in concentrates) (c)
88.3
83.9
76.5
76.0
63.0
264.2
215.5
Escondida - Refined production from leach plants
14.0
14.0
16.4
19.9
16.4
42.1
52.8
Oyu Tolgoi - Metal in concentrates
89.2
103.9
101.6
96.9
113.5
241.3
312.0
Rio Tinto total production - consolidated basis
204.4
240.3
228.6
213.2
204.5
642.8
646.3
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets.
(b) We continue to process third party concentrate to optimise smelter utilisation, including 5 thousand tonnes of cathode produced from purchased concentrate in Q3 2026. Purchased and tolled copper concentrates are excluded from reported production figures and guidance. Sales of cathodes produced from purchased concentrate are included in reported revenues.
(c) Mill production was previously reported together with recoverable copper in ore stacked for leaching as mined production.
Rio Tinto
interestQ3
2025Q4
2025Q1
2026Q2
2026Q3
20269 MTHS
2025
9 MTHS
2026
DIAMONDS
Production ('000 carats)
Diavik
100 %
1,137
1,112
1,041
33
0
3,317
1,074
GOLD
Metal in concentrates production ('000 ounces) (a)
Bingham Canyon
100 %
19.0
37.6
36.3
20.4
33.2
80.2
89.9
Escondida
30 %
10.6
9.6
15.7
11.9
12.3
36.1
39.9
Oyu Tolgoi
66 %
91.2
104.7
81.2
84.0
81.6
196.2
246.8
Rio Tinto total mine production
120.8
151.9
133.3
116.3
127.1
312.4
376.6
Refined production ('000 ounces)
Kennecott (b)
100 %
19.4
31.3
37.9
21.5
19.5
85.4
78.8
Metal in concentrates production ('000 ounces) (a) - consolidated basis
Bingham Canyon
19.0
37.6
36.3
20.4
33.2
80.2
89.9
Escondida
10.6
9.6
15.7
11.9
12.3
36.1
39.9
Oyu Tolgoi
138.2
158.6
123.1
127.3
123.6
297.2
374.0
Rio Tinto total mine production - consolidated basis
167.8
205.8
175.1
159.5
169.1
413.5
503.8
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets.
(b) We continue to process third party concentrate to optimise smelter utilisation, including 5 thousand tonnes of cathode produced from purchased concentrate in Q3 2026. Purchased and tolled copper concentrates are excluded from reported production figures and guidance. Sales of cathodes produced from purchased concentrate are included in reported revenues.
Rio Tinto share of production
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
2025
9 MTHS
2026
IRON ORE
Production ('000 tonnes) (a)
Hamersley mines
(b)
58,574
63,972
55,828
57,369
58,073
165,633
171,270
Hope Downs
50 %
4,742
4,819
4,074
4,607
4,788
13,556
13,469
Iron Ore Company of Canada
59 %
2,348
2,187
2,023
1,714
2,236
7,152
5,973
Robe River - Pannawonica (Mesas J and A)
53 %
3,588
4,077
3,618
4,145
3,923
11,086
11,686
Robe River - West Angelas
53 %
4,917
4,436
4,246
4,817
4,444
12,697
13,506
Simandou
45% (g)
0
1,023
257
297
1,108
0
1,663
Rio Tinto iron ore production ('000 tonnes) (a)
74,168
80,515
70,045
72,949
74,573
210,124
217,567
Breakdown of Production:
Pilbara Blend and SP10 Lump (c)
24,003
25,557
22,326
23,487
23,220
66,574
69,032
Pilbara Blend and SP10 Fines (c)
33,357
35,974
31,468
32,455
32,897
94,187
96,820
Robe Valley Lump
1,663
1,672
1,539
1,714
1,630
4,879
4,882
Robe Valley Fines
1,924
2,405
2,079
2,431
2,294
6,207
6,804
Yandicoogina Fines (HIY)
10,873
11,697
10,354
10,850
11,189
31,125
32,393
Pilbara iron ore production ('000 tonnes)
71,820
77,305
67,766
70,937
71,229
202,972
209,932
IOC Concentrate
936
785
1,010
442
789
3,063
2,241
IOC Pellets
1,411
1,402
1,013
1,272
1,447
4,089
3,732
IOC iron ore production ('000 tonnes)
2,348
2,187
2,023
1,714
2,236
7,152
5,973
Simandou iron ore production ('000 tonnes) (f)
45% (g)
0
1,023
257
297
1,108
0
1,663
Sales (‘000 tonnes)
Breakdown of Sales:
Pilbara Blend Lump
17,668
19,081
14,976
17,832
17,589
38,602
50,397
Pilbara Blend Fines
33,353
34,602
27,792
33,501
33,034
73,697
94,327
Robe Valley Lump
1,330
1,371
1,173
1,503
1,326
3,874
4,002
Robe Valley Fines
2,233
2,615
2,276
2,909
2,505
7,103
7,689
Yandicoogina Fines (HIY)
10,764
12,421
8,485
11,284
11,276
30,749
31,044
SP10 Lump (c)
2,938
3,637
2,744
2,314
3,398
19,379
8,456
SP10 Fines (c)
3,155
4,975
3,740
2,831
5,175
27,019
11,746
Pilbara iron ore sales ('000 tonnes) (d)
71,441
78,702
61,186
72,173
74,302
200,423
207,661
Pilbara iron ore sales - consolidated basis ('000 tonnes) (d) (e)
73,431
80,586
62,998
74,197
76,204
205,954
213,399
IOC Concentrate
1,056
837
676
653
686
2,978
2,015
IOC Pellets
1,306
1,376
1,258
1,203
1,535
4,044
3,997
IOC Iron ore sales ('000 tonnes) (d)
2,363
2,212
1,934
1,856
2,221
7,022
6,011
Simandou iron ore sales (‘000 tonnes) (h)
45% (g)
0
0
0
190
589
0
779
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets. Iron Ore production for Pilbara operations and Iron Ore Company of Canada refers to saleable production (after crushing, screening and beneficiation). For Simandou, it represents ore ready for train loading at the SimFer mine gate: final (tertiary) crushing of Simandou ore takes place in China.
(b) Includes 100% of production from Paraburdoo, Mt Tom Price, Western Turner Syncline, Marandoo, Yandicoogina, Brockman, Nammuldi, Silvergrass, Channar, Gudai-Darri, Eastern Range and Western Range mines. Whilst Rio Tinto owns 54% of the Eastern Range and the Western Range mines, under the terms of the joint venture agreement, Hamersley Iron manages the operation and is obliged to purchase all mine production from the joint venture and therefore all of the production is included in Rio Tinto's share of production.
(c) SP10 includes other lower grade products.
(d) Sales includes material shipped to our portside trading facility in China which may not be sold onwards in the same period.
(e) While Rio Tinto has a 53% net beneficial interest in Robe River Iron Associates, it recognises 65% of the assets, liabilities, sales revenues and expenses in its accounts (as 30% is held through a 60% owned subsidiary and 35% is held through a 100% owned subsidiary). The consolidated basis sales reported here include Robe River Iron Associates on a 65% basis to enable comparison with revenue reported in the financial statements.
(f) Simandou production represents ore at the SimFer mine gate before train loading. Final crushing is undertaken in China, hence, Simandou mine gate production is not considered to be saleable production.
(g) Represents the Rio Tinto equity share of SimFer Jersey (53% owned by Rio Tinto), which owns 85% of the SimFer mine (Blocks 3&4).
(h) Simandou value chain to China: at full production targeting a ~75-to-90-day cycle, with customer collection up to a further 30 days (mine to recognised sales).
Rio Tinto share of production
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
2025
9 MTHS
2026LITHIUM
Production ('000 tonnes)
Lithium carbonate
(a)
11.2
13.9
12.4
13.9
12.2
26.7
38.4
Lithium hydroxide
100 %
6.0
5.1
5.5
5.3
5.8
13.3
16.6
Spodumene
100 %
0.0
0.0
0.0
0.0
0.0
9.1
0.0
Other lithium specialities (LCE)
100 %
1.7
1.3
0.8
1.1
1.2
3.4
3.0
Total lithium carbonate equivalent (LCE) production (b)
12.5
15.4
12.7
14.6
13.0
30.4 (c)
40.3
(a) Lithium carbonate quantities reflect Rio Tinto’s 66.5% ownership in Olaroz, 100% ownership in Fénix
(b) The lithium value chain is vertically integrated and as a result production volumes are not additive. Lithium Carbonate Equivalent (LCE) is derived from volumes of lithium carbonate, lithium chloride, and spodumene concentrate. These compounds are used as feedstock in downstream production.
(c) Year-to-date 2025 represents production since March following completion of the Arcadium acquisition. Q1 2025 LCE production was 5.6kt (6.5kt on a 100% basis); LCE shipments were 3.8kt (5.0kt on a 100% basis).
MOLYBDENUM
Mine production ('000 tonnes) (a)
Bingham Canyon
100 %
1.3
1.7
2.5
1.5
0.9
3.5
4.9
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets.
SALT
Production ('000 tonnes)
Dampier Salt
68 %
1,197
1,342
951
1,176
828
3,408
2,955
SILVER
Metal in concentrates production ('000 tonnes) (a)
Bingham Canyon
100 %
282
556
536
287
471
1,178
1,294
Escondida
30 %
583
653
834
658
537
1,690
2,029
Oyu Tolgoi
66 %
369
441
406
392
466
998
1,264
Rio Tinto total mine production
1,233
1,650
1,777
1,336
1,474
3,866
4,587
Refined production ('000 ounces)
Kennecott (b)
100 %
254
439
632
327
335
1,399
1,293
(a) Mine production figures for metals refer to the total quantity of metal produced in concentrates, leach liquor or doré bullion irrespective of whether these products are then refined onsite, except for the data for bauxite and iron ore which represent production of marketable quantities of ore plus concentrates and pellets.
(b) We continue to process third party concentrate to optimise smelter utilisation, including 5 thousand tonnes of cathode produced from purchased concentrate in Q3 2026. Purchased and tolled copper concentrates are excluded from reported production figures and guidance. Sales of cathodes produced from purchased concentrate are included in reported revenues.
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
2025
9 MTHS
2026TITANIUM DIOXIDE SLAG
Production ('000 tonnes)
Rio Tinto Iron & Titanium (a)
100 %
261
222
218
227
217
753
662
(a) Quantities comprise 100% of Rio Tinto Fer et Titane and Rio Tinto's 74% interest in Richards Bay Minerals (RBM).
Production figures are sometimes more precise than the rounded numbers shown, hence small differences may result between the total of the quarter figures and the year to date figures.
Rio Tinto percentage interest shown above is at 30 September 2026.
Rio Tinto
interestQ3
2025Q4
2025Q1
2026Q2
2026Q3
20269 MTHS
20259 MTHS
2026
ALUMINA
Smelter Grade Alumina - Aluminium Group
Alumina production ('000 tonnes)
Australia
Queensland Alumina Refinery - Queensland
80 %
871
887
839
859
898
2,601
2,596
Yarwun refinery - Queensland
100 %
743
781
724
695
715
2,162
2,134
Brazil
São Luis (Alumar) refinery
10 %
984
984
977
973
957
2,812
2,907
Canada
Jonquière (Vaudreuil) refinery - Quebec (a)
100 %
323
351
349
322
332
1,018
1,003
(a) Jonquière’s (Vaudreuil’s) production shows smelter grade alumina only and excludes hydrate produced and used for specialty alumina.
Speciality Alumina - Aluminium Group
Speciality alumina production ('000 tonnes)
Canada
Jonquière (Vaudreuil) plant – Quebec
100 %
26
29
28
28
31
81
87
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026
ALUMINIUM
Primary Aluminium
Primary aluminium production ('000 tonnes)
Australia
Bell Bay smelter - Tasmania
100 %
49
48
47
47
48
142
142
Boyne Island smelter - Queensland
74 %
127
127
124
125
130
377
379
Tomago smelter - New South Wales
52 %
145
148
141
143
147
426
431
Canada
Alma smelter - Quebec
100 %
122
123
120
122
123
362
365
Alouette (Sept-Îles) smelter - Quebec
40 %
149
158
158
159
158
458
474
Arvida smelter - Quebec
100 %
34
24
20
13
0
106
33
Arvida AP60 smelter - Quebec
100 %
15
16
15
17
22
45
53
Bécancour smelter - Quebec
25 %
118
119
117
117
115
351
349
Grande-Baie smelter - Quebec
100 %
58
58
57
57
58
171
172
Kitimat smelter - British Columbia
100 %
103
101
105
108
110
305
322
Laterrière smelter - Quebec
100 %
64
63
62
62
63
188
187
Iceland
ISAL (Reykjavik) smelter
100 %
51
52
52
53
53
150
157
New Zealand
Tiwai Point smelter
100 %
82
83
82
83
84
232
249
Oman
Sohar smelter
20 %
101
100
99
102
101
301
302
Recycled Aluminium
Recycled aluminium production ('000 tonnes)
Matalco
50 %
135
124
121
140
139
415
400
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026
BAUXITE
Bauxite production ('000 tonnes)
Australia
Gove mine - Northern Territory
100 %
3,244
3,040
3,109
3,229
3,154
9,688
9,491
Weipa mine - Queensland
100 %
10,788
10,021
7,903
9,407
10,296
29,442
27,605
Brazil
Porto Trombetas (MRN) mine
22 %
3,134
2,997
2,379
2,627
3,113
8,563
8,118
Guinea
Sangaredi mine (a)
23 %
3,712
3,725
3,880
4,414
3,578
13,307
11,872
Rio Tinto share of bauxite shipments
Share of total bauxite shipments ('000 tonnes)
16,396
15,102
13,427
15,305
15,871
46,456
44,603
Share of third party bauxite shipments ('000 tonnes) (b)
11,843
10,638
9,221
10,614
11,574
33,131
31,409
(a) Rio Tinto has a 22.95% shareholding in the Sangaredi mine but benefits from 45.0% of production.
(b) Sangaredi's third-party bauxite shipments for 2025 and Q1 2026 were restated following a reclassification between internal and third-party shipments. This has no impact on total bauxite shipments.
Rio Tinto
interestQ3
2025Q4
2025Q1
2026Q2
2026Q3
20269 MTHS
20259 MTHS
2026BORATES
US
Borates ('000 tonnes) (a)
100 %
128
124
128
137
132
377
396
(a) Production is expressed as B2O3 content.
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026COPPER & GOLD
Escondida
30 %
Chile
Sulphide ore to concentrator ('000 tonnes)
36,721
35,628
34,225
35,862
31,429
106,100
101,517
Average copper grade (%)
0.94
0.91
0.88
0.85
0.81
0.99
0.85
Contained copper ('000 tonnes)
294.2
279.7
255.1
253.5
210.0
880.8
718.5
Contained gold ('000 ounces)
35.3
31.9
52.5
39.7
40.9
120.2
133.1
Contained silver ('000 ounces)
1,942
2,176
2,780
2,193
1,790
5,634
6,764
Recoverable copper in ore stacked for leaching ('000 tonnes) (a)
28.1
20.0
40.7
27.3
42.8
91.9
110.8
Refined production from leach plants:
Copper cathode production ('000 tonnes)
46.5
46.7
54.8
66.4
54.7
140.4
175.8
Sales of metals:
Copper in concentrates ('000 tonnes) (b)
258
278
252
234
211
853
696
Copper cathode ('000 tonnes)
38
50
50
72
48
138
170
Gold ('000 ounces) (b)
35
32
52
40
41
120
133
Silver ('000 ounces) (b)
1,942
2,176
2,780
2,193
1,790
5,634
6,764
(a) The calculation of copper in material mined for leaching is based on ore stacked at the leach pad.
(b) Payable metals in concentrates.
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026
COPPER & GOLD (continued)
Kennecott
Bingham Canyon mine
100 %
Utah, US
Ore treated ('000 tonnes)
5,928
11,249
10,168
6,640
9,726
25,897
26,534
Average ore grade:
Copper (%)
0.37
0.41
0.41
0.36
0.40
0.40
0.40
Gold (g/t)
0.16
0.18
0.17
0.13
0.20
0.15
0.17
Silver (g/t)
2.11
2.31
2.32
1.95
2.23
2.04
2.19
Molybdenum (%)
0.047
0.027
0.046
0.049
0.028
0.034
0.040
Copper concentrates produced ('000 tonnes)
75
162
152
83
139
381
375
Average concentrate grade (% Cu)
24.6
23.2
22.8
24.2
24.2
22.7
23.6
Production of metals in copper concentrates:
Copper ('000 tonnes) (a)
18.5
38.4
34.7
20.2
33.7
86.7
88.6
Gold ('000 ounces)
19.0
37.6
36.3
20.4
33.2
80.2
89.9
Silver ('000 ounces)
282
556
536
287
471
1,178
1,294
Molybdenum concentrates produced ('000 tonnes):
3.3
4.2
5.7
3.7
2.6
8.5
12.0
Molybdenum in concentrates ('000 tonnes)
1.3
1.7
2.5
1.5
0.9
3.5
4.9
Kennecott smelter & refinery
100 %
Copper concentrates smelted ('000 tonnes)
131
194
98
167
151
417
416
Copper anodes produced ('000 tonnes) (b)
27.8
37.9
19.7
25.4
13.8
97.5
58.9
Production of refined metal:
Copper ('000 tonnes) (c)
13.0
38.4
34.0
20.4
11.7
95.2
66.0
Gold ('000 ounces) (d)
19.4
31.3
37.9
21.5
19.5
85.4
78.8
Silver ('000 ounces) (d)
254
439
632
327
335
1,399
1,293
Sales of refined metal:
Copper ('000 tonnes) (c)
10.2
41.9
33.4
20.9
10.5
92.7
64.8
Gold ('000 ounces)
17.7
29.7
36.0
20.8
18.5
82.2
75.2
Silver ('000 ounces)
230
427
604
328
325
1,355
1,257
(a) Includes a small amount of copper in precipitates.
(b) New metal excluding recycled material.
(c) We continue to process third party concentrate to optimise smelter utilisation, including 5 thousand tonnes of cathode produced from purchased concentrate in Q3 2026. Purchased and tolled copper concentrates are excluded from reported production figures and guidance. Sales of cathodes produced from purchased concentrate are included in reported revenues.
(d) Includes gold and silver in intermediate products.
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026
COPPER & GOLD (continued)
Oyu Tolgoi mine
66 %
Mongolia
Ore Treated ('000 tonnes) - Open Pit
7,282
7,926
7,334
6,639
7,390
21,588
21,363
Ore Treated ('000 tonnes) - Underground
2,870
3,406
3,500
3,263
3,768
8,503
10,531
Ore Treated ('000 tonnes) - Total
10,153
11,332
10,834
9,902
11,159
30,090
31,894
Average mill head grades:
Open Pit
Copper (%)
0.54
0.55
0.54
0.53
0.51
0.48
0.53
Gold (g/t)
0.58
0.62
0.46
0.52
0.38
0.40
0.45
Silver (g/t)
1.13
1.16
1.08
1.11
1.12
1.07
1.10
Underground
Copper (%)
2.16
2.20
2.16
2.28
2.36
2.11
2.27
Gold (g/t)
0.63
0.59
0.61
0.61
0.65
0.60
0.62
Silver (g/t)
4.87
4.94
4.81
4.98
5.14
4.71
4.98
Total
Copper (%)
1.00
1.05
1.06
1.11
1.14
0.94
1.10
Gold (g/t)
0.59
0.61
0.51
0.55
0.47
0.45
0.51
Silver (g/t)
2.19
2.29
2.29
2.38
2.48
2.10
2.38
Copper concentrates produced ('000 tonnes)
394.9
464.3
465.3
406.6
493.4
1,079.9
1,365.3
Average concentrate grade (% Cu)
22.6
22.4
21.8
23.8
23.0
22.3
22.9
Production of metals in concentrates:
Copper in concentrates ('000 tonnes)
89.2
103.9
101.6
96.9
113.5
241.3
312.0
Gold in concentrates ('000 ounces)
138.2
158.6
123.1
127.3
123.6
297.2
374.0
Silver in concentrates ('000 ounces)
559
668
616
594
706
1,512
1,915
Sales of metals in concentrates (a):
Copper in concentrates ('000 tonnes)
80.9
92.4
105.1
98.8
106.8
225.0
310.6
Gold in concentrates ('000 ounces)
121.2
144.2
137.5
127.7
118.4
269.9
383.5
Silver in concentrates ('000 ounces)
474
557
614
568
623
1,327
1,805
(a) Sales of metals in concentrates refer to the payable metals in concentrates collected by customers from the Mongolia/China border.
Rio Tinto
interest
Q3
2025
Q4
2025
Q1
2026
Q2
2026
Q3
2026
9 MTHS
20259 MTHS
2026
DIAMONDS
Diavik Diamonds
100 %
Northwest Territories, Canada
Ore processed ('000 tonnes)
515
489
442
0
0
1,419
442
Diamonds recovered ('000 carats)
1,137
1,112
1,041
33
0
3,317
1,074
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025Q4
2025
Q1
2026
Q2
2026Q3
20269 MTHS
20259 MTHS
2026IRON ORE
Rio Tinto Iron Ore
Western Australia
Pilbara Operations
Saleable iron ore production ('000 tonnes)
Hamersley mines
(a)
58,574
63,972
55,828
57,369
58,073
165,633
171,270
Hope Downs
50 %
9,484
9,639
8,148
9,214
9,576
27,112
26,938
Robe River - Pannawonica (Mesas J and A)
53 %
6,769
7,693
6,826
7,820
7,403
20,917
22,049
Robe River - West Angelas
53 %
9,276
8,370
8,011
9,088
8,385
23,956
25,484
Total production ('000 tonnes)
84,104
89,674
78,813
83,491
83,437
237,618
245,741
Breakdown of total production:
Pilbara Blend and SP10 Lump (b)
28,545
29,678
26,031
27,644
27,381
78,371
81,056
Pilbara Blend and SP10 Fines (b)
37,917
40,606
35,603
37,176
37,464
107,205
110,243
Robe Valley Lump
3,138
3,155
2,903
3,234
3,075
9,206
9,212
Robe Valley Fines
3,631
4,538
3,923
4,586
4,328
11,711
12,837
Yandicoogina Fines (HIY)
10,873
11,697
10,354
10,850
11,189
31,125
32,393
Breakdown of total shipments:
Pilbara Blend Lump
21,142
21,362
16,799
20,858
20,025
46,106
57,683
Pilbara Blend Fines
38,477
39,448
32,170
37,831
36,947
86,760
106,948
Robe Valley Lump
2,510
2,588
2,214
2,835
2,503
7,310
7,551
Robe Valley Fines
4,214
4,934
4,294
5,488
4,726
13,402
14,507
Yandicoogina Fines (HIY)
10,764
12,421
8,485
11,284
11,276
30,749
31,044
SP10 Lump (b)
3,643
4,720
3,996
3,559
4,522
21,665
12,076
SP10 Fines (b)
3,597
5,787
4,430
3,409
5,683
28,982
13,521
Total shipments ('000 tonnes) (c)
84,346
91,259
72,387
85,264
85,681
234,973
243,331
Iron Ore Company of Canada
59 %
Newfoundland & Labrador and Quebec in Canada
Saleable iron ore production:
Concentrates ('000 tonnes)
1,594
1,337
1,720
753
1,344
5,216
3,816
Pellets ('000 tonnes)
2,403
2,388
1,724
2,166
2,464
6,964
6,355
IOC Total production ('000 tonnes)
3,998
3,725
3,444
2,919
3,808
12,180
10,171
Shipments:
Concentrates ('000 tonnes)
1,799
1,425
1,151
1,112
1,168
5,072
3,431
Pellets ('000 tonnes)
2,225
2,343
2,143
2,049
2,614
6,886
6,806
IOC Total Shipments ('000 tonnes) (c)
4,024
3,768
3,294
3,161
3,782
11,958
10,237
Simandou
45% (e)
Simandou iron ore production ('000 tonnes) (d)
0
2,271
570
660
2,460
0
3,691
Simandou iron ore sales (‘000 tonnes)
0
0
0
422
1,307
0
1,729
Global Iron Ore Totals
Iron Ore Production (‘000 tonnes) (f)
88,102
95,670
82,828
87,070
89,705
249,798
259,604
Iron Ore Sales (‘000 tonnes) (g)
88,369
95,027
75,681
88,847
90,770
246,931
255,297
(a) Includes 100% of production from Paraburdoo, Mt Tom Price, Western Turner Syncline, Marandoo, Yandicoogina, Brockman, Nammuldi, Silvergrass, Channar, Gudai-Darri, Eastern Range and Western Range mines. Whilst Rio Tinto owns 54% of the Eastern Range and the Western Range mines, under the terms of the joint venture agreement, Hamersley Iron manages the operation and is obliged to purchase all mine production from the joint venture and therefore all of the production is included in Rio Tinto's share of production.
(b) SP10 includes other lower grade products.
(c) Sales includes material shipped to our portside trading facility in China which may not be sold onwards in the same period.
(d) Simandou production represents crushed ore at the SimFer mine gate before train loading. Final crushing is undertaken in China, hence, Simandou mine gate production is not considered to be saleable production. There is 7.9Mt (100% SimFer) stockpiled uncrushed ore at the Simfer mine.
(e) Represents Rio Tinto’s equity share of SimFer Jersey (53% owned by Rio Tinto), which owns 85% of the SimFer mine (Blocks 3&4).
(f) Iron Ore production for Pilbara operations and Iron Ore Company of Canada (IOC) refers to saleable production (after crushing, screening and beneficiation). For Simandou, it represents ore ready for train loading at the SimFer mine gate: final (tertiary) crushing of Simandou ore takes place in China.
(g) Includes all shipments from Pilbara and IOC, including those to our Portside trading business; excludes shipments from our Portside trading business. For the Simandou value chain to China: at full production targeting a ~75-to-90-day cycle, with customer collection up to a further 30 days (mine to recognised sales).
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
Rio Tinto operational data
Rio Tinto
interest
Q3
2025Q4
2025
Q1
2026
Q2
2026Q3
20269 MTHS
20259 MTHS
2026LITHIUM
Lithium production (‘000 tonnes)
Lithium carbonate (a)
(a)
14.0
17.1
14.9
16.4
14.2
32.9
45.5
Lithium hydroxide
100 %
6.0
5.1
5.5
5.3
5.8
13.2
16.6
Spodumene
100 %
0.0
0.0
0.0
0.0
0.0
9.1
0.0
Other lithium specialities (LCE)
100 %
2.1
0.9
0.8
1.1
1.2
3.7
3.0
Total lithium carbonate equivalent (LCE) production (b)
15.2
18.4
15.3
17.1
15.0
33.7 (c)
47.4
Third party shipments (‘000 tonnes)
Lithium carbonate (a)
(a)
11.5
14.9
9.8
10.4
10.6
21.4
30.8
Lithium hydroxide
100 %
4.6
6.4
4.1
4.8
4.7
10.7
13.6
Spodumene
100 %
30.6
0.0
0.0
0.0
0.0
53.2
0.0
Other lithium specialities (LCE)
100 %
0.4
0.4
0.6
0.7
0.8
1.1
2.1
Total lithium carbonate equivalent shipments (‘000 LCE)
20.2
21.4
14.2
15.7
15.8
39.4 (c)
45.8
(a) Lithium carbonate quantities reflect our 100% share of Olaroz shipments, of which Rio Tinto's ownership is 66.5%.
(b) The lithium value chain is vertically integrated and as a result production volumes are not additive. Lithium Carbonate Equivalent (LCE) is derived from volumes of lithium carbonate, lithium chloride, and spodumene concentrate. These compounds are used as feedstock in downstream production.
(c) Year-to-date 2025 represents production since March following completion of the Arcadium acquisition. Q1 2025 LCE production was 5.6kt (6.5kt on a 100% basis); LCE shipments were 3.8kt (5.0kt on a 100% basis).
SALT
Dampier Salt (a)
68 %
Western Australia
Salt production ('000 tonnes)
1,751
1,963
1,392
1,720
1,211
4,986
4,322
TITANIUM DIOXIDE SLAG
Rio Tinto Iron & Titanium
100 %
Canada and South Africa
(Rio Tinto share) (a)
Titanium dioxide slag ('000 tonnes)
261
222
218
227
217
753
662
(a) Quantities comprise 100% of Rio Tinto Fer et Titane and Rio Tinto's 74% interest in Richards Bay Minerals' production. Ilmenite mined in Madagascar is being processed in Canada.
Rio Tinto percentage interest shown above is at 30 September 2026. The data represents production and sales on a 100% basis unless otherwise stated.
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.ENDDRLUOUARNRURAUA
Recent news on Rio Tinto
See all newsRio Tinto - Director/PDMR Shareholding
Rio Tinto - Director/PDMR Shareholding
UK stocks slip as banks drag; earnings in focus
Brief: Hochtief's Thiess Wins Long-Term Mining Services Contracts In Mongolia
China's state iron ore buyer agrees new annual supply contract with Rio Tinto, sources say (updated)