Picture of Serica Energy logo

SQZ Serica Energy News Story

0.000.00%
gb flag iconLast trade - 00:00
EnergySpeculativeMid CapContrarian

REG - Serica Energy PLC - Operations Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20240205:nRSE0037Ca&default-theme=true

RNS Number : 0037C  Serica Energy PLC  05 February 2024

Serica Energy plc

("Serica" or the "Company")

Operations Update

London, 5 February 2024 - Serica Energy plc (AIM: SQZ), a British independent
upstream oil and gas company with operations in the UK North Sea, provides the
following operations update.

 

Mitch Flegg, Chief Executive of Serica, said:

 

"Pro-forma production in 2023 after including volumes from the Tailwind assets
for the full year was just over 40,000 boe/d net to Serica. I am pleased that
we met our operating cost target with pro-forma operating costs of around
US$19 per boe despite the significant inflation being experienced by the
offshore sector generally. We are aiming to keep unit operating costs below
US$20 per boe during 2024.

 

Production in 2024 is expected to be higher than in 2023 with guidance between
41,000 boe/d and 48,000 boe/d for the year. This reflects a range of outcomes
in a year of significant activity including the speed with which the scheduled
drilling and well work deliver incremental production.

 

Serica's strategy of investing in its assets continues to be central to our
record of consistently achieving high levels of reserves replacement, combined
with increased levels of production. We are looking forward, therefore, to the
start of the four well Triton area drilling programme in March, with the
benefits of added production expected to start coming through in the second
half of the year. During 2024 there is also an extensive programme of
interventions in both platform and subsea wells on the Bruce and Keith fields.
The objectives include re-establishing consistent production from the Keith
field.

 

In addition, Serica has a healthy portfolio of potential new projects. This
includes the possible developments of the Buchan and Belinda fields, which
offer the prospect of further replacement of produced reserves and incremental
production from 2026 onwards. Our plans for drilling two Bruce infill wells,
the first new wells on the field since 2012, are progressing and, during the
next eighteen months, we will be participating in the Parkmead operated
Skerryvore exploration well situated in the UK Central North Sea. As a UK
taxpayer, Serica will benefit from tax relief for its share of the associated
development and exploration costs.

 

Serica is extremely well placed, therefore, to continue its track record of
replacing reserves and increasing production. This platform has been achieved
while maintaining a very strong balance sheet, which is both the result and
enabler of our strategy to invest and grow organically and through disciplined
M&A."

 

Production in 2023

 

Serica's pro-forma net production in 2023 which includes production from the
fields owned by Tailwind since 1 January 2023 averaged 40,121 boe/d. The
gas/liquids split of production in 2023 was 56:44.

 

                                FY 2023

                                boe/d
 Bruce                          6,487
 Rhum                           12,490
 Bittern                        4,012
 Gannet E                       6,098
 Evelyn                         3,780
 Guillemot West and North West  237
 Columbus                       2,178
 Erskine                        1,325
 Orlando                        3,514

 

Production in the second half of the year was lower than the first half due
mainly, as previously reported, to the planned summer shutdowns for both the
Bruce and Triton hubs overrunning to rectify safety related issues. There were
also a number of facilities issues on Bruce and Triton which caused short-term
interruptions to production late in the year and carrying over into early
January. These are now largely resolved.

 

Notwithstanding these issues, production in the fourth quarter of 2023
averaged 45,748 boe/d.

 

2024 Production Guidance

 

The production guidance for 2024 is 41,000 to 48,000 boe/d (net to Serica).
This represents an increase on pro-forma production for the combined Serica
and Tailwind portfolios in 2023.

 

2024 year to date production has averaged 43,184 boe/d 1 . Erskine has been
shut in since 25(th) January 2024 due to an issue with a compressor. It is
expected to restart during March.

 

As a result of the work completed during the extended Bruce summer shutdown in
2023, an extended shutdown is not planned in 2024. There is a planned one-week
outage which overlaps with scheduled shutdown of third-party infrastructure
downstream of the Bruce platform.

 

There is a planned six-week shutdown of the Triton FPSO during the summer of
2024. This will be accompanied by a 'walk to work' campaign designed to
further improve the performance of the facilities. It follows successful 'walk
to work' campaigns in 2022 and 2023.

 

These planned maintenance periods are incorporated into the production
guidance.

 

Investment programme

 

As previously announced, Serica is planning an ambitious programme of organic
investments during 2024 extending into 2025 and 2026.

 

The investments in 2024 include four wells in the Triton area (Bittern B1z
sidetrack, Gannet E GE-05, Guillemot North West EC1 and Evelyn EV-02) 2  and
well work on the Bruce and Keith fields.

 

The start date of the B1z sidetrack is now expected to be in March 2024. This
well and the subsequent three wells are scheduled to take about three months
each, meaning that drilling will continue into 2025. Serica has also exercised
an option to keep the rig for a further well following completion of the
fourth well in the programme (EV-02).

 

Production from the B1z sidetrack is expected to start shortly after the
completion of drilling. Production from each of the other three wells is
expected to start around thirty days after the completion of drilling each
well.

 

The Bruce and Keith Light Well Intervention Vessel ("LWIV") campaign is on
track to take place between March and May. This follows previous campaigns in
2022 and 2023, which have delivered low-cost incremental production. It is
hoped to restart production from the Keith field during 2024 following
successful preparation work on the Keith subsea facilities carried out in
2023. Additional well interventions from the Bruce platform are scheduled for
the second half of 2024.

 

The estimated cost to Serica of the currently approved capital investment in
its producing assets in the Bruce and Triton hubs is approximately £210
million, before tax relief. Most of the expenditures are expected to be
incurred in 2024.

 

Looking further forward, both the Buchan field redevelopment and Belinda field
development projects are moving towards potential sanction. The Environmental
Statement and draft Field Development Plan for the Buchan project have been
submitted, with completion of Serica's acquisition of a 30% interest is
expected to occur during February. As previously reported, the Belinda draft
Field Development Plan was submitted in September 2023.

 

Serica is also maturing plans for two infill wells on the Bruce field with the
aim of drilling in 2026.

 

The Skerryvore joint venture, in which Serica holds a 20% interest, is working
towards drilling a licence commitment exploration well during late 2024 or the
first half of 2025.

 

Abandonment costs in 2024 are forecast to be about £14 million (pre-tax) net
to Serica. These will be incurred mainly on the final decommissioning of the
Arthur field, situated in the UK Southern North Sea, which was held by
Tailwind Energy.

 

Operating costs

 

Despite the significant inflationary pressures being experienced by all
operators in the UK North Sea, Serica achieved unit operating costs in 2023 of
around US$19/boe based on pro-forma production of 40,121 boe/d.

 

The Company's target in 2024 is to maintain unit operating costs at below
US$20/boe.

 

Balance Sheet

 

Year-end cash and cash equivalents stood at £291 million and borrowings at
£210 million. This is after payment during 2H 2023 of:

·      two instalments of 2023 taxes totalling £139 million (final
payment approximately £58 million in Q1 2024), and

·      dividends of £89 million being the total of the 2022 final and
2023 interim amounts.

 

Cash and cash equivalents included £28 million of cash security temporarily
lodged with a third party in respect of decommissioning obligations pending
the issue of letters of credit to replace the security. This is expected to
occur shortly.

 

Organisation

 

Martin Copeland has assumed the role of Serica's CFO and has been appointed to
the Board effective today, 5 February 2024. Martin succeeds Andy Bell, who has
resigned from the Board. Andy will continue to support Serica during the
transition and preparation of the 2023 Annual Report.

 

Sell-side Analysts Event

 

A presentation will be published later this week on Serica's website to
accompany the previously reported event for sell-side analysts being hosted by
the Company on 7(th) and 8(th) February.

 

Regulatory

 

This announcement is inside information for the purposes of Article 7 of
Regulation 596/2014.

 

 

Enquiries:

 

 Serica Energy plc                                                      +44 (0)20 7390 0230
 Mitch Flegg (CEO) / Stephen Lambert (VP Legal and External Relations)

 Peel Hunt (Nomad & Joint Broker)                                       +44 (0)20 7418 8900
 Richard Crichton / David McKeown / Georgia Langoulant

 Jefferies (Joint Broker)                                               +44 (0)20 7029 8000
 Sam Barnett / Will Soutar

                                                                        +44 (0)20 7390 0230

 Vigo Consulting (PR Advisor)
 Patrick d'Ancona / Finlay Thomson                                      serica@vigoconsulting.com

 

 

NOTES TO EDITORS

Serica Energy is a British independent oil and gas exploration and production
company with a portfolio of UKCS assets.

Serica has a balance of gas and oil production. The Company is responsible for
about 5% of the natural gas produced in the UK, a key element in the UK's
energy transition.

Serica's producing assets are focused around two main hubs: the Bruce, Keith
and Rhum fields in the UK Northern North Sea, which it operates, and a mix of
operated and non-operated fields tied back to the Triton FPSO. Serica also has
operated interests in the producing Columbus (UK Central North Sea) and
Orlando (UK Northern North Sea) fields and a non-operated interest in the
producing Erskine field in the UK Central North Sea.

Serica's portfolio of assets includes several organic investment opportunities
which are currently being pursued or are under consideration.

Further information on the Company can be found at www.serica-energy.com
(http://www.serica-energy.com) . The Company's shares are traded on the AIM
market of the London Stock Exchange under the ticker SQZ and the Company is a
designated foreign issuer on the TSX. To receive Company news releases via
email, please subscribe via the Company website.

 1  1 January to 2 February 2024

 2  Serica interests are 64.63% in Bittern, 100% in Gannet E (operator), 10%
in Guillemot W/NW and 100% in Evelyn (operator)

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDFIFVRFDIEIIS

Recent news on Serica Energy

See all news