Picture of Shuka Minerals logo

SKA Shuka Minerals News Story

0.000.00%
gb flag iconLast trade - 00:00
EnergyHighly SpeculativeMicro CapSucker Stock

REG - Shuka Minerals PLC - Placing and Operational Update

For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20260113:nRSM7153Oa&default-theme=true

RNS Number : 7153O  Shuka Minerals PLC  13 January 2026

13 January 2026

 

Shuka Minerals Plc

 

("Shuka" or the "Company")

 

Placing and Operational Update

 

Shuka Minerals Plc (AIM/AltX: SKA), an African focused mine operator and
developer, is pleased to advise it has raised gross proceeds of £1,000,000
through the placing ("Placing") of 25,000,000 new ordinary shares (the
"Placing Shares") at a placing price of 4 pence ("p") per share ("Placing
Price"). The Placing was undertaken by the Company's broker Tavira Financial
Limited.

 

Participants in the Placing will be issued one warrant for each Placing Share
("Investor Warrants"), exercisable at 8p per ordinary share valid for three
years from the date of Admission (as defined below). The Investor Warrants, if
exercised in full, would result in the Company raising an additional £2
million.

 

The Company has granted Tavira Financial Limited 1,500,000 broker warrants,
exercisable at 4p for a period of three years from Admission, as part of their
remuneration for arranging the Placing.

 

GMI Loan and Placing to fund Kabwe

 

As announced earlier today, following receipt of funds under the GMI Loan, the
Company expects to shortly complete the acquisition of a 100% interest in
Leopard Exploration and Mining Limited ("LEM") and the world-class Kabwe Zinc
Project (the "Project" or "Kabwe") in Zambia. Proceeds from the Placing will
be used towards developing the Project and for general working capital
purposes. A breakdown of the Project work programme is provided below.

 

Background on Kabwe and Acquisition

 

Kabwe remains one of the world's richest and most notable zinc mines, with
grades of up to 43% zinc and historical production averaging around 25%.
Production commenced in 1904 and over 14.56Mt of ore has been produced
to-date, much of which was produced by ZCCM, working with Anglo American
Technical Services, during its circa 50-year operatorship of the Project. Over
1.8Mt tonnes of zinc, 800Kt of lead, 2.8Moz of silver and 7.8Kt of vanadium
have been produced historically, equivalent to US$8.3 billion at 2021
commodity prices. The mine was closed in 1994 due to prevailing commodity
prices at that time.

 

In 2023, market leader, Behre Dolbear, independently estimated 5.723Mt of
resources remained at Kabwe based on historical data, including 700Kt tonnes
of zinc and 100Kt tonnes of lead. At prevailing metal prices, these resources
have a value of in excess of US$2 billion extractable in-situ metal. Behre
Dolbear also assessed a phase 1 development of the well-established No.2
Orebody and Mine Club & Speaks Orebodies, which generated pre-tax cash
flows of US$1.84 billion and a NPV(10) of US$561 million.

 

On 13 December 2024, the Company entered into a sale and purchase arrangement
with the existing owners of the Project, LEM, to acquire 100% of LEM for a
consideration of US$4.5 million. The consideration is to be settled as to
US$1.5 million in cash and US$3 million in new shares in the Company, to be
satisfied by the issuance of an aggregate 28,640,042 shares (the
"Acquisition"), of which US$450,000 cash and 6,364,454 shares have already
been paid or issued to the LEM vendors.  Following today's receipt of funds
from the GMI Loan, the balance of cash consideration will be transferred, and
consideration shares issued, to LEM and the Company will assume 100% ownership
of the Project.

 

2026 Work Programme and Beyond

 

There is substantial value in the current resource inventory at Kabwe as
reported by Behre Dolbear, however, the Company will seek to build additional
value by conducting further exploration. The current resource remains open at
depth and with the advantage of modern exploration techniques, including
gravity and magnetic studies, that have never been undertaken at Kabwe, there
is considerable scope to build value by increasing the mineral resource
inventory.

 

The Company plans to undertake the following programme ("2026 Programme") from
funds raised:

 

·    Confirmatory and step-out diamond drilling

·    Construction of a sample laboratory on site

·    Airbourne and ground magnetics

·    Geophysics and geotechnical studies

·    Assays of new and historical data

·    Infrastructure upgrades at site

·    Environmental baseline studies

 

The Company believes the 2026 Programme will enable it to accomplish the
following:

 

·    further define the identified ore bodies;

·    refine exploration targets beyond the existing licence; and

·    update the JORC Resource later in 2026 following this exploration
phase.

 

Further information will be provided on the various workstreams and their
objectives via separate RNS when appropriate.

 

Update on Rukwa Coal Mine

 

During 2025 the Company continued to upgrade its Rukwa coal project in
Tanzania. Whilst it is clearly dwarfed by the opportunity and focus at Kabwe,
for modest expenditure the Company believes it can realise consistent cash
flow.

 

The pit has now been dewatered and road and bridge repairs completed, along
with equipment servicing, parts replacement and wash plant testing. The
Company intends to acquire two new loaders and one new excavator, with other
yellow metal being leased. This has reduced required additional investment
into Rukwa to an estimated US$150,000 to achieve a planned staged ramp up to
approximately 5,000 tonnes per month of washed coal. The Company is in the
process of finalising offtake agreements with East African and Rwandan cement
plants for coal produced at Rukwa.

 

Internal management estimates calculate a staged ramp up generating an NPV10
of US$12.6 million and an IRR of 80% based on a US$45 per tonne sales price
and US$25 per tonne margin.

 

Further capital investment of circa US$1 million is expected to enable the
Company to increase throughput to over 7,500 tonnes per month, however a
decision to proceed with any material additional capital investment would only
be made once there is stable cash flow and revenue generation from Rukwa and
if there are sufficient cash resources within the Company.

 

Placing Details, Admission & Total Voting Rights

 

The Company has today entered into a placing agreement with Tavira Financial
Limited in relation to the Placing, which has not been underwritten. The
Placing Shares, which are being issued under existing authorities, will
represent approximately 20.8% of the Company's issued share capital, as
enlarged by the Placing and Kabwe Consideration Shares announced earlier
today.

 

The  Placing Shares will rank pari passu with the Company's existing
ordinary shares in all respects.

 

Application has been made to the London Stock Exchange for the Placing Shares
to be admitted to trading on AIM ("Admission").  It is expected that
Admission will become effective and that dealings in the Placing Shares on AIM
will commence on or around 8.00 a.m. on 19 January 2026.

 

Following the Admission, and inclusive of the Placing Shares and the Kabwe
Consideration Shares (announced earlier today), the total issued share capital
of the Company will be 120,498,639 ordinary shares, each with voting rights.
The above figure may be used by shareholders as the denominator for the
calculations by which they will determine if they are required to notify their
interest in, or a change to their interest in, the Company, under the FCA's
Disclosure Guidance and Transparency Rules.

 

Shuka Minerals CEO, Richard Lloyd, commented:

 

"I am delighted to announce we now have funding in place not only to complete
the acquisition of Kabwe, but also to commence work immediately on the ground
in both Zambia and Tanzania. I appreciate it has taken slightly longer to
close the Acquisition, but I would like to thank our major shareholder GMI for
their continued support and to the Company's new and existing shareholders for
their patience and support.

 

It is clear Kabwe is an asset of global significance and history. We have
structured a deal that has enabled the Company to acquire 100% of this
world-class mine for minimal dilution. We expect to provide updates going
forward on operations and any strategic initiatives that may arise, as we seek
to unlock this multi-billion dollar resource for the benefit of all our
shareholders."

 

This announcement contains inside information for the purposes of Article 7 of
the Market Abuse Regulation (EU) 596/2014 as it forms part of UK domestic law
by virtue of the European Union (Withdrawal) Act 2018 ("MAR") and is disclosed
in accordance with the Company's obligations under Article 17 of MAR.

 

Capitalised terms in this announcement have the same meaning as in the
Company's announcement 1 July 2025, unless otherwise defined.

 

Shuka Minerals plc has its primary listing on the London Stock Exchange (AIM)
and a secondary listing on the AltX of the JSE Limited

 

For Enquiries:

 Shuka Minerals Plc                     +44 (0) 7990 503007

 Richard Lloyd - CEO

 Strand Hanson Limited

 Financial and Nominated Adviser        +44 (0) 20 7409 3494

 James Harris | Richard Johnson

 AcaciaCap Advisors Propriety Limited   +27 (11) 480 8500

 JSE Sponsor and Listing Advisor

 Michelle Krastanov

 Tavira Financial Limited               +44 (0) 20 7100 5100

 Joint Broker

 Oliver Stansfield | Jonathan Evans

 Peterhouse Capital Limited

 Joint Broker                           +44 (0)20 7469 0930

 Charles Goodfellow | Duncan Vasey

 Investor Relations

 Faith Kinyanjui Mumbi                  +254 746 849 110

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCGPUUCGUPQGUW



            Copyright 2019 Regulatory News Service, all rights reserved

Recent news on Shuka Minerals

See all news