Dec 20 (Reuters) - Soma Gold Corp SOMA.V :
* UPDATE ON EL LIMON MILL
* SOMA GOLD CORP: INCREASED PRODUCTION AT CORDERO MINE WILL
NOW
SUPPORT RESTART OF OPERATIONS AT EL LIMON MILL
* SOMA GOLD CORP: MILL RESTART PROCESS IS SCHEDULED TO
COMMENCE IN
EARLY JANUARY, WITH AN ESTIMATED COMPLETION TIME OF 3-4 MONTHS
* SOMA GOLD CORP: ANTICIPATES RESUMING MINE PRODUCTION AT
HISTORICALLY PRODUCING AND FULLY PERMITTED AURORA MINE BY END OF
F2024
Source text for Eikon: ID:nCNWzVfQma