Brief: TC Energy's Increased Demand Forecast Largely Driven By Power Generation Including Accelerated Data Center Demand
BRIEF-TC Energy's Increased Demand Forecast Largely Driven By Power Generation Including Accelerated Data Center Demand July 30 (Reuters) - TC Energy Corp TRP.TO:
TC ENERGY EXPECTS SUSTAINED GROWTH IN INVESTMENT PACE STARTING IN 2029 - CONF CALL
TC ENERGY SAYS PENDING-APPROVAL PROJECTS ROSE TO NEARLY C$7 BILLION FROM C$6 BILLION Q-O-Q - CONF CALL
TC ENERGY LIKELY TO SANCTION C$6-8 BILLION IN CAPITAL SPENDING IN 2026, DOUBLE A TYPICAL YEAR - CONF CALL
TC ENERGY'S INCREASED DEMAND FORECAST LARGELY DRIVEN BY POWER GENERATION, INCLUDING ACCELERATED DATA CENTER DEMAND - CONF CALL
TC ENERGY EXPECTS 2035 NORTH AMERICAN GAS-FIRED POWER DEMAND OUTLOOK TO 60 BCF/D FROM 54 BCF/D - CONF CALL
Further company coverage: TRP.TO