Feb 21 (Reuters) - Titan Mining Corp TI.TO :
* TITAN MINING FOCUSES ON MINE DEVELOPMENT AND DISTRICT
EXPLORATION AT THE EMPIRE STATE MINE
* TITAN MINING CORP - EMPIRE STATE MINE OPERATION IS BEING
RESTRUCTURED
* TITAN MINING CORP - REVISED MINE PLAN IS EXPECTED TO BE
COMPLETED IN MID-2019.
* TITAN MINING CORP - IN Q4 OF 2018, PRODUCTION AT ESM WAS
PARTLY
IMPACTED BY TRANSITION FROM CONTRACTOR-MINING TO OWNER-MINING
* TITAN MINING CORP - ESM MILL THROUGHPUT WAS 48,302 TONS,
OR 525
TONS PER DAY, AND MILLED GRADE WAS 6.2% ZINC IN Q4
Source text for Eikon: ID:nGNXbDfRjB
Further company coverage: TI.TO