Brief: Vale says Salobo CPF project advances to execution phase
BRIEF-Vale says Salobo CPF project advances to execution phase Aug 12 (Reuters) - Vale S.A. VALE3.SA:
EXPECTS THE PROJECT TO ADD 6 MILLION METRIC TONS IN ANNUAL ORE PROCESSING CAPACITY AT SALOBO PLANT
SALOBO CPF PROJECT ADVANCES TO EXECUTION PHASE
VALE BASE METALS EXPECTS TO START THE PROJECT'S OPERATION IN H1 OF 2028, ONE YEAR BEFORE THE INITIAL SCHEDULE
WHEATON AGREED TO PROVIDE $40 MILLION TO VBM TO PARTIALLY FUND THE PROJECT
VBM SEES PROJECT'S CAPEX AT $215 MILLION, OR $175 MILLION CONSIDERING WEATHON'S FUNDING, VS $225-$275 MILLION PREVIOUSLY
Source text: ID:nBVSHd1Ffa
Further company coverage: VALE3.SA
(Reporting by Sao Paulo newsroom)
((Andre.Romani@thomsonreuters.com;))
Recent news on Vale
See all newsBrief: Vale Files Application For Panda Bond Program In China
Austrian investor rushes to boost copper production at old Chile mine
Media: Vale mulls raising over $500 million in debut panda bond sale - Bloomberg News
Vale to buy 30% stake in Ligga as it seeks additional Carajas iron ore
Brief: Vale says it has not made any decision over new issuance of debt securities