RNS Number : 1249G  Zenith Energy Ltd  04 November 2025

November 4, 2025

ZENITH ENERGY LTD.

("Zenith" or the "Company")

Decision & Appeal of SMP Court Case

Zenith Energy Ltd. ("Zenith" or the "Company") (LSE: ZEN; OSE: ZENA; XSAT:
ZENA SDR), the listed international energy production and development company,
announces that the Paris Commercial Court (the "Court") has delivered a
decision in respect of the legal claim (the "Claim") brought before the Paris
Commercial Court (the "Court") by its fully owned subsidiary, Anglo African
Oil & Gas Congo S.A.U ("AAOGC") against SMP Energies (hereafter "SMP",
formerly Société de Maintenance Pétrolière - SMP) the rig contractor that
performed drilling services in wells TLP-103 and TLP-103C of the Tilapia
oilfield during 2018-2019.

 

Background

 

On July 15, 2019, formerly AIM quoted Anglo African Oil & Gas plc
("AAOG"), the previous owner of AAOGC  prior to its acquisition by Zenith in
May 2020, made an announcement confirming that AAOGC had initiated a claim
against SMP following poor performance in drilling wells TLP-103 and TLP-103C,
and the refusal by SMP to engage in negotiations to cover the significant cost
overruns that had been incurred by AAOGC as a direct consequence.

 

The Claim was initially launched in Court against SMP to recover costs
of US$3.1 million relating to SMP's unsatisfactory performance.

 

In taking the decision to launch the Claim for costs against SMP the following
reasons were considered significant at the time:

 

·       AAOGC had maintained extensive, contemporaneous technical
records of the failures of the Rig and the losses and delays that were caused
as a result;

 

·       SMP had not put forward evidence, of any kind, to suggest that
Rig performance was not the cause for cost overruns; and

 

·       Advice from International counsel in London, Paris and the
Republic of the Congo was that the Claim had merit.

 

Under the rules and conventions of the Court, mediation between the parties
engaged in a dispute is a recommended course of action. As a result, a
supervised mediation meeting took place during the Autumn of 2019.

 

On December 11, 2019, AAOG announced that mediation efforts had proven
unsuccessful and that, as a result, AAOGC would continue to pursue the Claim.

 

On November 11, 2020, Zenith provided an update on the Claim announcing that
SMP had retaliated to the Claim by obtaining a number of unjustified seizure
orders over the fixed assets of AAOGC in the Republic of the Congo, as well as
over its local bank accounts, and that whilst the initial granting of these
orders had no bearing on the Claim launched in the Paris Commercial Court, it
had been successful in fully revoking all of the wrongful seizure orders
initially obtained in the Republic of the Congo.

On February 17, 2023, Zenith announced that it AAOGC had increased the amount
of the Claim for SMP's failures during drilling activities to US$9
million, in consideration of the significant commercial damages suffered by
AAOGC, specifically the impossibility, as a direct result, to begin production
activities from the Tilapia oilfield.

Further, Zenith announced that AAOGC had intensified its legal activities in
support of the Claim by commissioning third-party reports from leading
experts.

On July 3, 2023, the Company announced that the Court had rejected SMP's
request for a stay of proceedings in France due to new proceedings having
been initiated in the Republic of Congo, stating that SMP's request contained
"all the characteristics of a dilatory request", and ordered SMP to pay an
amount of EUR 30,000 to AAOGC as initial procedural costs (the
"Initial Procedural Costs").

 

SMP unsuccessfully appealed this intermediate decision of the Court, resulting
in the Paris Court of Appeal upholding the decision of the Paris Commercial
Court and AAOGC receiving Procedural Costs in the amount of approximately EUR
30,000.

 

On October 4, 2024, the Company announced that it had appointed Charles
Russell Speechlys Paris as new legal counsel before the Court in connection
with the legal claim against SMP.

 

Decision

 

The Court has partially accepted a significant proportion of the legal
arguments advanced by AAOGC as part of the Claim, whilst solely recognising
160,000 EUR in compensation payable to AAOGC as a result of the
responsibilities ascribable to SMP.

However, the Court ruled that SMP's invoice, amounting to
approximately €630,000 - although fully contested by AAOGC - remains
payable on the basis that it was not disputed within six (6) calendar days, as
stipulated in the contract. This interpretation is firmly contested by AAOGC.

The Court has not provided for provisional enforcement of the decision.

 

Appeal

AAOGC has instructed Charles Russell Speechlys (Paris) to appeal the
decision, given its clearly contradictory nature and the limited level of
compensation awarded despite the Court's acknowledgment of many of AAOGC's
arguments.

The Company will provide a further update in due course as the appeal
progresses.

 

 

Andrea Cattaneo, Chief Executive Officer, commented:

 

"In light of the fact that AAOGC has been pursuing this claim for
approximately five years, the decision is disappointing.

It is important to underline that this case was initiated prior to our
acquisition of AAOGC, and that the underlying events occurred before the
current management assumed responsibility of this entity. Nevertheless, upon
acquiring AAOGC, we formed the view - which we continue to hold - that AAOGC's
claim had strong legal and factual merits.

The procedural conduct of SMP, as evidenced by the intermediate decision in
July 2023, has had the purpose of making every possible attempt to impede the
progress of the Claim.

With receivables exceeding US$5.3 million due from SNPC, the national oil
company of the Republic of the Congo, and given the absence of any
provisional enforcement in this decision, we shall proceed to appeal before
the Paris Court of Appeal.

We remain unwavering in our confidence in the Company's potential and look
forward to making further near-term progress on the key strategic
fronts that underpin the Company's value."

 

Further Information:

 Zenith Energy Ltd

Andrea Cattaneo, Chief Executive Officer  Tel: +1 (587) 315 1279

                                            E:       info@zenithenergy.ca (mailto:info@zenithenergy.ca)

 

Notes to Editors:

Zenith Energy Ltd. is a revenue generating, independent energy company with
energy production, exploration and development assets in North Africa, the US
and Europe. The Company is listed on the London Stock Exchange Main Market
(LSE: ZEN), the Euronext Growth of the Oslo Stock Exchange (OSE: ZENA) and
on the Spotlight Stock Market in Sweden (XSAT: ZENA SDR).

Zenith's strategic focus is on pursuing development opportunities through the
development of proven revenue generating energy production assets, as well as
low-risk exploration activities in assets with existing production.

For more information, please visit: www.zenithenergy.ca
(http://www.zenithenergy.ca)

Twitter: @zenithenergyltd

LinkedIn: https://bit.ly/3A5PRJb (https://bit.ly/3A5PRJb)

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCPKQBQKBDDFDK



            Copyright 2019 Regulatory News Service, all rights reserved

Recent news on Zenith Energy

See all news