Anglo Asian Mining - Q2 and H1 2026 Production and Sales Update
RNS Number : 3466MAnglo Asian Mining PLC15 July 2026
15 July 2026
Q2 and H1 2026 Production and Sales Update
Continued growth in copper production and Demirli ramp-up on track
Performance in line with Full Year 2026 expectations
Anglo Asian Mining plc ("Anglo Asian" or the "Company"), the AIM listed copper, gold and silver producer focused in Azerbaijan, is pleased to provide the following production, sales and operational review for the three months to 30 June 2026 ("Q2 2026" or the "Quarter") and six months to 30 June 2026 ("H1 2026" or the "Half Year").
Copper production continues to grow quarter-on-quarter to 5,129 tonnes in Q2 2026 (Q1 2026: 3,711 tonnes), as Demirli continues to ramp up to full production, which is expected to be achieved during Q3 2026. The Company also produced 6,272 ounces of gold in Q2 2026 (Q1 2026: 6,057 ounces) and remains highly cash generative, with net cash increasing by $39.9 million to $57.6 million as at 30 June 2026.
Continued strong production growth during Q2 2026
· Copper production of 5,129 tonnes (Q2 2025: 654 tonnes) as Demirli production continues to ramp up in line with expectations
o 1,879 tonnes at Gedabek
o 3,250 tonnes at Demirli
· Gold production of 6,272 ounces (Q2 2025: 6,086 ounces)
o 5,158 ounces contained within gold doré
o 1,114 ounces from flotation and SART production
· Silver production totalled 50,059 ounces (Q2 2025: 32,033 ounces)
o 5,775 ounces contained within gold doré
o 44,284 ounces from flotation and SART processing
Record production in H1 2026
· Copper production of 8,840 tonnes (H1 2025: 1,188 tonnes)
· Gold production of 12,329 ounces (H1 2025: 12,114 ounces)
· Silver production of 92,855 ounces (H1 2025: 62,348 ounces)
Key developments across the Company's portfolio
· Worley Europe Limited appointed to carry out feasibility studies for Xarxar and Garadag, marking a further step in the Company's strategy to continue to develop its portfolio
o Studies are expected to be finalised mid-2027 for Xarxar and H1 2028 for Garadag
· 90,000 metres core drilling programme announced for 2026 and 2027
· Gedabek flotation plant upgrade completed
o Nine high-efficiency Imhoflot pneumatic flotation cells installed
o All bottlenecks in leaching and flotation processing plants eliminated
· Demirli SAG and ball mills both operated throughout the Quarter
o Demirli ramp-up will be completed in Q3 2026 and reach steady state production
· Second stage of the final wall raise of the Gedabek tailings dam completed
H1 2026 sales and financial overview
· Total gold bullion sales of 7,126 ounces at an average of $4,664 per ounce (H1 2025: 9,781 ounces at an average of $3,077 per ounce)
· Total concentrate sales of 58,577 dry metric tonnes with a value of $125.9 million
o Gedabek - 26,882 dry metric tonnes ("dmt") with a value of $54.5 million (H1 2025: 6,210 dmt with a value of $11.1 million)
o Demirli - 31,695 dmt with a value of $71.4 million (H1 2025:nil)
· Cash of $69.8 million ($37.2 million at 31 March 2026) and debt of $12.2 million ($19.5 million at 31 March 2026)
o Net cash of $57.6 million ($17.7 million at 31 March 2026)
o No outstanding advances from Trafigura
· Unsold gold doré and copper concentrate inventory of $28.9 million at 30 June 2026
Key metrics for Q1 2026, Q2 2026, Q2 2025 and FY 2025
Q1 2026
Q2 2026
Q2 2025
Q2 2026 compared to Q2 2025
H/(L)
FY 2025
Production
Gold
ounces
6,057
6,272
6,208
64
25,061
Copper
Gedabek
tonnes
1,462
1,879
654
1,225
4,787
Demirli
tonnes
2,249
3,250
-
3,250
3,128
Total copper
tonnes
3,711
5,129
654
4,475
7,915
Silver
ounces
42,796
50,059
32,033
18,026
153,333
Doré sales
Doré
ounces
4,100
3,026
5,028
(2,002)
19,631
Sales value
$/ounce
4,728
4,579
3,299
1,280
3,441
Copper concentrate sales
Tonnes
tonnes
18,553
40,024
3,886
36,138
29,695
Sales value
$m
45.6
80.3
7.1
73.2
64.7
Increase in net cash
$m
15.1
39.9
0.8
39.1
17.3
Ending net cash / (debt)
$m
17.7
57.6
(13.0)
70.6
2.5
Market value of inventory
$m
30.8
28.9
7.0
21.9
37.7
Outlook
The Company is encouraged by the 2026 performance to date, which remains in line with expectations for FY 2026. It is expected that production in H2 2026 will increase compared to H1 2026 due to the Demirli ramp-up being achieved in Q3 2026 and seasonal factors. The Board therefore remains confident in meeting 2026 guidance of 20,000 to 25,000 tonnes of copper production, 28,000 to 33,000 ounces of gold, and 170,000 to 210,000 ounces of silver, and continuing to execute its medium-term growth strategy to become a mid-tier, copper focused producer.
Reza Vaziri, CEO of Anglo Asian Mining, commented:
"The first six months of 2026 have been highly significant for Anglo Asian as we achieved our highest ever half-year of production. The ramp-up at Demirli continues to progress in line with our expectations, and will be completed during this quarter. Looking forward, we also continue to progress the development of our other assets as we execute our medium-term growth strategy, which we remain confident of delivering. Our excellent cash generation means we have the capital to continue to pursue our growth strategy at pace as well as rewarding shareholders. I am pleased to reiterate our 2026 guidance and look forward to a strong second half performance. "
Note that all references to "$" are to United States dollars.
Market Abuse Regulation (MAR) Disclosure
Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014, which was incorporated into UK law by the European Union (Withdrawal) Act 2018, until the release of this announcement.
For further information please contact:
Anglo Asian Mining plc
Reza Vaziri, Chief Executive Officer
Tel: +994 12 596 3350
Bill Morgan, Chief Financial Officer
Tel: +994 502 910 400
Stephen Westhead, Vice President
Tel: +994 502 916 894
Amir Vaziri, Chief Business Development Officer
Tel: +1 (301) 332 9938
Peel Hunt LLP (Broker)
Tel: +44 (0) 20 7418 8900
Ross Allister
David McKeown
Emily Bhasin
SP Angel Corporate Finance LLP (Nominated Adviser)
Ewan Leggat
Adam Cowl
Tel: +44 (0) 20 3470 0470
Hudson Sandler (Financial PR)
Charlie Jack
Harry Griffiths
Tel: +44 (0) 20 7796 4133
Notes to editors
Anglo Asian Mining plc (AIM:AAZ) is a copper and gold producer with a high-quality portfolio of production and exploration assets in Azerbaijan. The Company produced 7,915 tonnes of copper and 25,061 ounces of gold for the year ended 31 December 2025.
The Company's strategic plan for growth shows a clearly defined path for the Company to transition to a multi-asset, mid-tier, copper and gold producer by 2030, by which time copper will be the principal product of the Company, with forecast annual production of around 50,000 to 55,000 tonnes of copper. It plans to achieve this growth by bringing into production three new mines during the period 2027 to 2030 at Xarxar, Garadag and Zafar, in addition to the newly opened Gilar and Demirli mines. Production commenced at the Gilar mine in May 2025 and Demirli in July 2025. https://www.angloasianmining.com/
APPENDIX
OPERATING STATISTICS FOR Q2 AND H1 2026
Ore mined during H1 2026
Gedabek
Mine
3 months to
31 March 2026
3 months to
30 June 2026
Ore mined
(tonnes)
Average
gold grade
(g/t)
Average
copper
grade
(%)
Ore mined
(tonnes)
Average
gold grade
(g/t)
Average
copper
grade
(%)
Open pit
35,588
0.46
0.20
23,502
0.26
0.03
Gilar - u/g
208,032
1.30
1.36
225,602
1.39
1.67
Total
243,620
1.18
1.19
249,104
1.28
1.52
Demirli
3 Months to 31 March 2026
3 Months to 30 June 2026
Mine
Ore mined
Average
copper grade
Ore mined
Average
copper grade
(tonnes)
(%)
(tonnes)
(%)
Open pit
1,352,208
0.37
2,238,060
0.34
Gedabek processing, production and sales in H1 2026
Ore processed by leaching
Quarter ended
Ore processed
Gold grade of ore processed
Heap leach pad crushed ore
(tonnes)
Heap leach pad ROM
ore
(tonnes)
Agitation leaching plant*
(tonnes)
Heap leach pad crushed ore
(g/t)
Heap leach pad ROM
ore
(g/t)
Agitation leaching
plant*
(g/t)
31 March 2025
106,429
-
149,763
0.40
-
1.16
30 June 2025
133,153
-
154,948
0.40
-
1.13
30 September 2025
47,202
-
156,773
0.40
-
1.52
31 December 2025
-
-
163,541
-
-
1.27
FY 2025
286,784
-
625,025
0.40
-
1.26
31 March 2026
14,264
-
167,989
0.33
-
1.33
30 June 2026
23,277
-
183,929
0.25
-
1.40
H1 2026
37,541
-
351,918
0.29
-
1.37
* includes previously heap leached ore.
Ore processed by flotation
Quarter ended
Ore processed*
Gold content
Silver content
Copper content
(tonnes)
(ounces)
(ounces)
(tonnes)
31 March 2025
155,406
535
9,516
729
30 June 2025
166,135
1,193
30,537
900
30 September 2025
151,359
3,185
85,123
1,793
31 December 2025
156,158
3,027
93,835
2,409
FY 2025
629,058
7,940
219,011
5,831
31 March 2026
162,109
2,806
69,040
1,703
30 June 2026
177,491
3,725
85,676
2,302
H1 2026
339,600
6,531
154,716
4,005
*the ore processed by flotation includes ore which had previously been treated by agitation leaching. For H1 2026, all ore processed had been previously treated by agitation leaching.
Gold and silver produced as gold doré and gold sales
Quarter ended
Gold produced*
Silver produced*
Gold sales**
Gold Sales price
(ounces)
(ounces)
(ounces)
($/ounce)
31 March 2025
5,758
8,206
4,753
2,843
30 June 2025
5,624
6,699
5,028
3,299
30 September 2025
5,814
4,655
5,181
3,430
31 December 2025
5,133
4,788
4,669
4,214
FY 2025
22,329
24,348
19,631
3,441
31 March 2026
4,842
5,607
4,100
4,728
30 June 2026
5,158
5,775
3,026
4,579
H1 2026
10,000
11,382
7,126
4,664
* including Government of Azerbaijan's share
** excluding Government of Azerbaijan's share
Gold and silver produced as gold doré - split between agitation and heap leaching
Quarter
ended
Gold
Silver
Agitation
leaching
(ounces)
Heap
leaching
(ounces)
Total
(ounces)
Agitation
leaching
(ounces)
Heap
leaching
(ounces)
Total
(ounces)
31 March 2025
4,017
1,741
5,758
5,717
2,489
8,206
30 June 2025
3,936
1,688
5,624
4,632
2,067
6,699
30 Sept 2025
4,681
1,133
5,814
3,735
920
4,655
31 Dec 2025
3,988
1,145
5,133
3,720
1,068
4,788
FY 2025
16,622
5,707
22,329
17,804
6,544
24,348
31 March 2026
3,780
1,062
4,842
4,379
1,228
5,607
30 June 2026
4,112
1,046
5,158
4,603
1,172
5,775
H1 2026
7,892
2,108
10,000
8,982
2,400
11,382
Copper concentrate production and sales
Concentrate
Copper
Gold
Silver
Concentrate
Concentrate
production*
content*
content*
content*
sales**
sales**
(dmt)
(tonnes)
(ounces)
(ounces)
(dmt)
($000)
Quarter ended
31 March 2025
3,072
534
270
22,109
2,324
4,050
30 June 2025
3,523
654
462
25,334
3,886
7,060
30 September 2025
6,769
1,577
984
36,968
6,852
17,760
31 December 2025
9,784
2,022
1,016
44,573
7,255
18,430
FY 2025
23,148
4,787
2,732
128,984
20,317
47,300
31 March 2026
7,311
1,462
1,215
37,189
7,890
24,206
30 June 2026
9,925
1,879
1,114
44,284
18,992
30,290
H1 2026
17,236
3,341
2,329
81,473
26,882
54,496
* including Government of Azerbaijan's share
** excludes Government of Azerbaijan's share
Demirli processing, production and sales H1 2026
Processed
Unit
Q1 2026
Q2 2026
Ore feed to plant
dry metric tonnes
647,835
855,104
Grade
per cent.
0.44
0.51
Copper content
tonnes
2,880
4,361
Production
Copper concentrate
tonnes
11,901
16,904
Copper content
tonnes
2,249
3,250
Sales
Concentrate sales
Dry metric tonnes
10,663
21,032
Value of sales
$ million
21.4
50.0
Q2 2026 Financial overview
The Company had a net inflow of funds of $39.9 million in the 3 months ended 30 June 2026. Cash increased by $32.6 million to $69.8 million and debt reduced by $7.3 million to $12.2 million at 30 June 2026. Net cash accordingly increased by $39.9 million to $57.6 million.
Net cash
Q1 2026
Q2 2026
$m
$m
$m
$m
I January / 1 April 2026
2.6
17.7
Sales proceeds
62.4
89.6
Interest income
0.3
0.4
VAT refund
-
2.9
Operating costs
(39.9)
(46.2)
Capital expenditure
(3.4)
(3.9)
Demirli lease payment
(3.8)
-
Debt servicing
(0.5)
(0.3)
Profits tax payment
-
(2.6)
Increase in net cash
15.1
39.9
31 March / 30 June 2026
17.7
57.6
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.ENDUPDRIMFTMTABBAF
Recent news on Anglo Asian Mining
See all newsBrief: Anglo Asian Mining Maintains FY2026 Guidance For Copper, Gold, and Silver Production
Anglo Asian Mining - Q3 2026 Production and Sales Update
RCS - Anglo Asian Mining - Notice of Investor Presentation
Anglo Asian Mining soars as H1 revenue triples
Azerbaijan's Anglo Asian Mining H1 revenue more than triples