Anglo Asian Mining - Q1 2026 Production and Sales Review

RNS Number : 4754A

Anglo Asian Mining PLC

15 April 2026

 

 

 

15 April 2026

  

Q1 2026 Production and Sales Review

Copper production of 3,711 tonnes and gold of 6,062 ounces

Net cash increased by $15.4 million to $17.7 million

 

Anglo Asian Mining plc ("Anglo Asian" or the "Company"), the AIM listed copper, gold and silver producer focused in Azerbaijan, is pleased to provide the following production and sales review for the three months to 31 March 2026 ("Q1 2026" or the "Quarter").

 

Q1 2026 production overview

·    Copper production of 3,711 tonnes (Q1 2025: 534 tonnes):

o 1,462 tonnes from flotation and SART at Gedabek

o 2,249 tonnes from flotation at Demirli

·    Gold production of 6,062 ounces (Q1 2025: 6,028 ounces):

o 4,842 ounces contained within gold doré

o 1,220 ounces from flotation and SART production

·    Silver production totalled 42,796 ounces (Q1 2025: 30,315 ounces):

o 5,607 ounces contained within gold doré

o 37,189 ounces from flotation and SART processing

 

Q1 2026  sales overview

·    Total gold bullion sales of 4,100 ounces at an average of $4,728 per ounce (Q1 2025: 4,753 ounces at an average of $2,843 per ounce)

·    Total concentrate sales of 18,553 dry metric tonnes with a value of $45.6 million

o Gedabek - 7,890 dry metric tonnes ("dmt") with a value of $24.2 million (Q1 2025: 2,327 dmt with a value of $4.1 million)

o Demirli -  10,663 dmt with a value of $21.4 million

 

Q1 and 31 March 2026 financial overview

·    Cash of $37.2 million ($30.2 million at 31 December 2025), no restricted cash

·    Debt of $19.5 million ($27.9 million at 31 December 2025)

o No outstanding advances from Trafigura at 31 March 2026 or 31 December 2025

·    Net cash of $17.7 million ($2.3 million at 31 December 2025)

·    Unsold gold doré and copper concentrate inventory of $30.8 million at 31 March 2026

 

Key metrics for Q1 2026 and Q1 2025 and FY 2025

Q1 2026Q1 2025Q1 2026 compared to Q1 2025
B/(W)
FY 2025
Production
Goldounces6,0626,0283425,061
Copper
Gedabektonnes1,4625389244,787
Demirlitonnes2,249-2,2493,128
Total coppertonnes3,7115383,1737,915
Silverounces42,79630,31512,481153,333
Dore sales
Doreounces4,1004,753(653)19,631
Sales value$/ounce4,7282,8431,8853,441
Copper concentrate sales
Tonnestonnes18,5532,32716,22629,695
Sales value$m45.64.141.564.7
Increase in net cash$m15.41.014.417.3
Ending net cash / (debt)$m17.7(13.8)31.52.5
Market value of inventory$m30.87.523.337.7
  Reza Vaziri, CEO of Anglo Asian Mining commented: "We are delighted with the progress and performance during the quarter.  The excellent copper production from Gedabek and Demirli demonstrates the successful continuing execution of our clear strategy to rapidly expand copper production and successfully transition to a multi-asset, mid-tier copper-focused producer. "   Note that all references to "$" are to United States dollars. Market Abuse Regulation (MAR) Disclosure Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014, which was incorporated into UK law by the European Union (Withdrawal) Act 2018, until the release of this announcement.   For further information please contact:  
Anglo Asian Mining plc
Reza Vaziri, Chief Executive OfficerTel: +994 12 596 3350
Bill Morgan, Chief Financial OfficerTel: +994 502 910 400
Stephen Westhead, Vice PresidentTel: +994 502 916 894
Amir Vaziri, Chief Business Development OfficerTel: +1 (301) 332 9938
Peel Hunt LLP(Broker)Tel: +44 (0) 20 7418 8900
Ross Allister
David McKeown
Emily Bhasin
SP Angel Corporate Finance LLP(Nominated Adviser)
Ewan Leggat
Adam Cowl
Tel: +44 (0) 20 3470 0470
Hudson Sandler(Financial PR)
Charlie Jack
Harry Griffiths
Tel: +44 (0) 20 7796 4133
  Notes to editors Anglo Asian Mining plc (AIM:AAZ) is a copper and gold producer with a high-quality portfolio of production and exploration assets in Azerbaijan. The Company produced 7,915 tonnes of copper and 25,061 ounces of gold for the year ended 31 December 2025.   The Company's strategic plan for growth shows a clearly defined path for the Company to transition to a multi-asset, mid-tier, copper and gold producer by 2030, by which time copper will be the principal product of the Company, with forecast annual production of around 50,000 to 55,000 tonnes of copper. It plans to achieve this growth by bringing into production three new mines during the period 2027 to 2030 at Xarxar, Garadag and Zafar, in addition to the newly opened Gilar and Demirli mines. Production commenced at the Gilar mine in May 2025 and Demirli in July 2025. https://www.angloasianmining.com/   Ore mined during Q1 2026   Gedabek
Mine3 months to
31 March 2026
Ore mined
(tonnes)
Average
gold grade
(g/t)
Average
copper
grade
(%)
Open pit35,5880.460.20
Gilar - u/g186,7091.351.48
Total222,2971.211.28
  Demirli
3 months to
31 March 2026
MineOre minedAverage
copper grade
(tonnes)(%)
Open pit1,352,2080.37
  Gedabek processing, production and sales in Q1 2026   Ore processed by leaching  
Quarter endedOre processedGold grade of ore processed
Heap leach pad crushed ore
(tonnes)
Heap leach pad ROM
ore
(tonnes)
Agitation leaching plant*
(tonnes)
Heap leach pad crushed ore
(g/t)
Heap leach pad ROM
ore
(g/t)
Agitation leachingplant*
(g/t)
31 March 2025106,429-149,7630.40-1.16
30 June 2025133,153-154,9480.40-1.13
30 September 202547,202-156,7730.40-1.52
31 December 2025--163,541--1.27
FY 2025286,784-625,0250.40-1.26
31 March 202614,264-167,9890.33-1.33
  * includes previously heap leached ore.   Ore processed by flotation
Quarter endedOre processed*Gold contentSilver contentCopper content
(tonnes)(ounces)(ounces)(tonnes)
31 March 2025155,4065359,516729
30 June 2025166,1351,19330,537900
30 September 2025151,3593,18585,1231,793
31 December 2025156,1583,02793,8352,409
FY 2025629,0587,940219,0115,831
31 March 2026162,1092,80669,0401,703
  *the ore processed by flotation includes ore which had previously been treated by agitation leaching. For Q1 2026, all ore processed had been previously treated by agitation leaching.   Gold and silver produced as gold doré and gold sales
Quarter endedGold produced*Silver produced*Gold sales**Gold Sales price
(ounces)(ounces)(ounces)($/ounce)
31 March 20255,7588,2064,7532,843
30 June 20255,6246,6995,0283,299
30 September 20255,8144,6555,1813,430
31 December 20255,1334,7884,6694,214
FY 202522,32924,34819,6313,441
31 March 20264,8425,6074,1004,728
  * including Government of Azerbaijan's share ** excluding Government of Azerbaijan's share   Gold and silver produced as gold doré - split between agitation and heap leaching  
Quarter
ended
GoldSilver
Agitation
leaching
(ounces)
Heap
leaching
(ounces)
Total
(ounces)
Agitation
leaching
(ounces)
Heap
leaching
(ounces)
Total
(ounces)
31 March 20254,0171,7415,7585,7172,4898,206
30 June 20253,9361,6885,6244,6322,0676,699
30 Sept 20254,6811,1335,8143,7359204,655
31 Dec 20253,9881,1455,1333,7201,0684,788
FY 202516,6225,70722,32917,8046,54424,348
31 March 20263,7801,0624,8424,3791,2285,607
  Copper concentrate production and sales  
ConcentrateCopperGoldSilverConcentrateConcentrate
production*content*content*content*sales**sales**
(dmt)(tonnes)(ounces)(ounces)(dmt)($000)
Quarter ended
31 March 20253,07253427022,1092,3244,050
30 June 20253,52365446225,3343,8867,060
30 September 20256,7691,57798436,9686,85217,760
31 December 20259,7842,0221,01644,5737,25518,430
FY 202523,1484,7872,732128,98420,31747,300
31 March 20267,3111,4621,22037,1897,89024,207
  * including Government of Azerbaijan's share ** excludes Government of Azerbaijan's share   Demirli processing, production and sales Q1 2026  
ProcessedUnitJanuary to March 2026
Ore feed to plantdry metric tonnes647,835
Gradeper cent.0.44
Copper contenttonnes2,880
Production
Copper concentratetonnes11,901
Copper contenttonnes2,249
 
Sales
Concentrate salesDry metric tonnes10,663
Value of sales$ million21.4
  Q1 2026 Financial overview The Company had a net inflow of funds of $15.4 million in the 3 months ended 31 March 2026. Cash increased by $7.0 million to $37.2 million and debt reduced by $8.4 million to $19.5 million at 31 March 2026. Net cash accordingly increased by $15.4 million to $17.7 million.   Net cash
Q1 2026
$m$m
I January 20262.3
Sales proceeds62.7
Interest income0.3
Operating costs(39.9)
Capital expenditure(3.4)
Demirli lease payment(3.8)
Debt servicing(0.5)
Inflow15.4
31 March 202617.7
  This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com. RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.   END     UPDSFAFWLEMSELL