** Macquarie says Capricorn Metals' CMM.AX first-quarter
production came in better than expected, but flags softer cash
generation
** Capricorn Metals' stock down 3.7% at A$4.625
** Brokerage has a price target of A$4.8 for the Australian
gold miner
** Karlawinda (project) produced 29.7koz of gold in 1QFY24,
5% better than our estimate with mined volumes the key positive,
compared with our expectations - Macquarie
** Brokerage sees co's FY24 production of 121koz at an
all-in sustaining costs (AISC) of A$1,317/oz
** "CMM's cash/bullion build over 1QFY24 was A$23.3 mln,
down A$4.1 mln QoQ and A$9.2 mln below our estimate due to
timing of payments for a tails dam lift," Macquarie says
** CMM stock up 4.4% YTD, as of last close
(Reporting by Ayushman Ojha in Bengaluru)