REG - Central Asia Metals - Q3 2022 Operations Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20221010:nRSJ2440Ca&default-theme=true

RNS Number : 2440C  Central Asia Metals PLC  10 October 2022

 

 

 

 

10 October 2022

 

CENTRAL ASIA METALS PLC

('CAML' or the 'Company')

Q3 2022 Operations Update

Central Asia Metals plc (AIM: CAML) today provides a Q3 2022 operations update
for the Kounrad dump leach, solvent extraction and electro-winning ('SX-EW')
copper recovery plant in Kazakhstan ('Kounrad') and the Sasa zinc-lead mine in
North Macedonia ('Sasa').

Summary

·    No lost time injuries ('LTIs') at either Kounrad or Sasa during Q3
2022

·    Kounrad

o  Q3 2022, 4,067 tonnes of copper produced

o  First nine months of 2022, 10,685 tonnes of copper produced

·    Sasa

o  Q3 2022 zinc in concentrate, 5,746 tonnes produced

o  Q3 2022 lead in concentrate, 6,899 tonnes produced

o  First nine months of 2022 zinc in concentrate, 16,211 tonnes produced

o  First nine months of 2022 lead in concentrate, 20,726 tonnes produced

 

Outlook

·    On course to achieve increased 2022 guidance for Kounrad's copper
production (13,500 to 14,000 tonnes)

·    On course to meet Sasa 2022 production guidance

o  Zinc in concentrate, 20,000-22,000 tonnes

o  Lead in concentrate, 27,000-29,000 tonnes

 

CAML production summary

 Metal production (tonnes)  Q3 2022  Q2 2022  Q1 2022  9m 2022  9m 2021
 Copper                     4,067    3,593    3,024    10,685   10,360
 Zinc                       5,746    5,225    5,240    16,211   17,033
 Lead                       6,899    7,091    6,736    20,726   20,734

 

Nigel Robinson, Chief Executive Officer, commented:

"I am pleased to report safe and strong production from both of our operations
during Q3 2022, with zero LTIs. At Kounrad, we announced increased 2022
production guidance with our H1 2022 results, and we are on track to deliver
this and meet our production targets at Sasa.

"Since recently announcing that we had received approval of the Cut and Fill
Project Environmental and Social Impact Assessment ('ESIA'), we have now begun
construction of the paste backfill plant. Construction of this part of Sasa's
Cut and Fill Project therefore remains on schedule to be completed in H1 2023.

"In August, we made our final repayment of the $187 million debt which we
secured to acquire Sasa less than five years ago. These repayments have been
made while we remained consistently among the sector leading dividend payers,
delivered value for all our stakeholders, and invested in our operations."

Health and Safety

There were no LTIs at either Kounrad or Sasa during Q3 2022.

Kounrad

Production and sales update

Kounrad Q3 2022 copper production of 4,067 tonnes brings output for the first
nine months of 2022 to 10,685 tonnes. Copper sales during Q3 2022 were 4,093
tonnes, bringing the total for the first nine months of the year to 10,499
tonnes.

Sasa

Production and sales update

In Q3 2022, mined and processed ore were 200,379 tonnes and 200,087 tonnes
respectively, bringing the total for the first nine months of 2022 to 602,587
tonnes of ore mined and 604,478 tonnes of ore processed. The average head
grades for the quarter were 3.34% zinc and 3.67% lead, and for the first nine
months of the year were 3.16% and 3.66% respectively.

Sasa produces a zinc concentrate and a separate lead concentrate. In Q3 2022,
11,364 tonnes of concentrate containing 50.6% zinc and 9,665 tonnes of
concentrate containing 71.4% lead were produced. Total production for the
first nine months of the year was 32,323 tonnes of zinc concentrate at an
average grade of 50.2% and 29,172 tonnes of lead concentrate at an average
grade of 71.0%.

Sasa typically receives from smelters approximately 84% of the value of its
zinc in concentrate and approximately 95% of the value of its lead in
concentrate. Accordingly, Q3 2022 payable production of zinc was 4,837 tonnes
and of lead was 6,554 tonnes, bringing total payable production for the
nine-month period to 13,625 tonnes of zinc and 19,690 tonnes of lead.

Given that deliveries from Sasa to the smelters occur on a regular basis,
payable base metal in concentrate sales for the nine-month period were similar
at 13,539 tonnes of zinc and 19,470 tonnes of lead.

During the first nine months of 2022, Sasa sold 237,636 ounces of payable
silver to Osisko Gold Royalties, in accordance with its streaming agreement.

                             Units    Q3 2022  9m 2022  9m 2021
 Ore mined                   t        200,379  602,587  614,807
 Plant feed                  t        200,087  604,478  626,906
 Zinc grade                  %        3.34     3.16     3.19
 Zinc recovery               %        85.9     84.9     85.1
 Lead grade                  %        3.67     3.66     3.54
 Lead recovery               %        94.0     93.7     93.4
 Zinc concentrate            t (dry)  11,364   32,323   34,003
 -      Grade                %        50.6     50.2     50.1
 -      Contained zinc       t        5,746    16,211   17,033
 Lead concentrate            t (dry)  9,665    29,172   28,856
 -      Grade                %        71.4     71.0     71.9
 -      Contained lead       t        6,899    20,726   22,300

 

Cut and Fill Project update

The permits required to begin construction of the paste backfill plant have
been received and, in September, initial earthworks began. Construction of the
paste backfill plant is on schedule to be completed in H1 2023, with the dry
stack tailings component scheduled for completion during H2 2023. Development
of the central decline continues to progress well, with 711 metres developed
during the first nine months of 2022, and 1,218 metres in total.

 

For further information contact:

 Central Asia Metals                             Tel: +44 (0) 20 7898 9001
 Nigel Robinson
 CEO
 Gavin Ferrar
 CFO
 Louise Wrathall                                 louise.wrathall@centralasiametals.com
 Director of Corporate Development
 Emma Chetwynd Stapylton                         emma.chetwyndstapylton@centralasiametals.com
 Investor Relations Manager

 Peel Hunt (Nominated Advisor and Joint Broker)  Tel: +44 (0) 20 7418 8900
 Ross Allister
 David McKeown

 BMO Capital Markets (Joint Broker)              Tel: +44 (0) 20 7236 1010
 Thomas Rider
 Pascal Lussier Duquette

 BlytheRay (PR Advisors)                         Tel: +44 (0) 20 7138 3204
 Tim Blythe
 Megan Ray
 Rachael Brooks

Note to editors:

 

Central Asia Metals, an AIM-listed UK company based in London, owns 100% of
the Kounrad SX-EW copper project in central Kazakhstan and 100% of the Sasa
zinc-lead mine in North Macedonia.

For further information, please visit www.centralasiametals.com
(http://www.centralasiametals.com/)  and follow CAML on Twitter at
@CamlMetals and on LinkedIn at Central Asia Metals Plc.

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDFLFVRIRLDIIF