Picture of Cleantech Lithium logo

CTL Cleantech Lithium News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsHighly SpeculativeMicro CapSucker Stock

REG - CleanTech Lithium - Laguna Verde Operational Update

For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20241105:nRSE9005Ka&default-theme=true

RNS Number : 9005K  CleanTech Lithium PLC  05 November 2024

5(th) November 2024

CleanTech Lithium PLC ("CleanTech Lithium" or the "Company")

Laguna Verde Operational Update

 

 

CleanTech Lithium PLC (AIM: CTL, Frankfurt:T2N, OTCQX:CTLHF), an exploration
and development company advancing sustainable lithium projects in Chile,
provides an operational update on progress with the Laguna Verde
pre-feasibility study ("PFS"), the 2024 exploration programme and Direct
Lithium Extraction ("DLE") pilot plant process work to produce battery-grade
lithium carbonate.

Highlights:

Laguna Verde PFS Update

·    Location of preferred sites for carbonation plant in Copiapó and
port facilities for export of final lithium carbonate product have been
selected

·    Power supply study completed evaluating options for onsite renewables
which provides a competitive alternative to the base case of a transmission
line and grid connection

·    Option to utilise electric truck transport identified, lowers
emissions and noise pollution, and by hauling from high to low altitude
regenerative charging reduces power consumption

·    Decision to configure project based on locating DLE plant at Laguna
Verde and carbonation plant in Copiapó has numerous advantages contributing
to a more robust PFS

·    Engineering for this configuration has extended the expected PFS
delivery to Q1 2025

Exploration Programme and Pilot Plant Updates

·   Results from two completed wells and pump tests for the 2024 field
programme have been received increasing knowledge of the resource and
providing additional information for the hydrogeological model

·    Downstream processing work from our pilot plant is progressing well
with lithium carbonate production expected in November

Investor webinar

·    CTL to host investor webinar on Tuesday 5(th) November at 17:00 GMT.
Register here:
https://www.investormeetcompany.com/cleantech-lithium-plc/register
(https://www.investormeetcompany.com/cleantech-lithium-plc/register)

 

Steve Kesler, Executive Chairman and Interim Chief Executive Officer,
CleanTech Lithium PLC, said:

"With the recent announcement by the Chilean Government to prioritise six salt
flats, including Laguna Verde, to start the process of awarding Special
Operating Lithium Contracts (CEOLs), we are focused on the key aspects to
advance the project, being permitting, completion of the PFS and production of
battery grade lithium carbonate from our pilot plant.

Progress has continued on central elements of the PFS with evaluation of plant
location, power supply and transport options. As a leader in developing DLE
based projects in Chile, we aim to enter production in 2027 when the lithium
market is expected to rebalance, providing a strong long term growth outlook."

 

Further Information

 

Sites Selected for Carbonation Plant and Port for Export of Final Product

As part of the ongoing PFS for the Laguna Verde project, a trade-off analysis
was completed which determined the DLE plant and eluate concentration stages
should be located at the Laguna Verde site, and the carbonation plant at the
nearby mining centre of Copiapó. This was reported to the market on July 2,
2024.  The re-configuration required a change in pre-engineering design
provided by Lanshen Technology, the Company selected to provide the lithium
processing plant design and equipment.  This has extended the expected PFS
completion, which was originally targeted for Q4 2024, into Q1 2025.

The Company has since undertaken studies to determine the ideal location of
the carbonation plant in Copiapó and selected a site.  After evaluating
several options, a site in an industrial zone which by-passes to the
south-east of Copiapó was chosen, as shown in Figure 1.  This location has
existing power and water supply options and provides a direct route to port.

 

Figure 1: Carbonation Plant Location Map
                Figure 2: Carbonation Plant Design Layout

A trade-off analysis was undertaken to evaluate transport corridors and port
facilities providing four different options for export of final lithium
product. The study indicated that the nearby Caldera Port provides the most
suitable option either utilising existing infrastructure which is currently
utilised for seasonal shipment of agricultural products, shown in Figure 3.
 Other port options are also available and may come into consideration
however Caldera Port is the current preference.

Figure 3: Caldera Port Existing Facilities

 

Power Supply Alternative of Onsite Renewable Generation

The Company engaged Chilean consultant Clean Power Hunters to undertake a
power supply study to evaluate the option of using renewable power generated
at the project site as an alternative to the base case of a transmission line
and grid connection. Laguna Verde is located in the region with the highest
solar irradiance in the world, as shown in Figure 4. Analysis of estimated
Capex and Opex was provided based on different configurations of onsite
renewables, either solar plus a battery energy storage system (BESS) or solar
plus wind plus BESS. Figure 5 shows the lowest Capex corresponds to combining
solar with three wind turbines plus BESS.

 

Figure 4: Solar Irradiance Map
 
          Figure. 5: Solar + Wind + BESS Scenarios Capex Split

The Company has received proposals including from major global solar plus BESS
suppliers, consistent with the costs estimated in the study and competitive
with the grid connection option. The financing model for both the grid
connection model or the alternative of onsite renewables is expected to be
based on a power purchase agreement and a build own operate basis by
established suppliers. These proposals will be built into the PFS and the
commercial analysis of the project.

 

Truck Transport Study

Based on the outcome of the plant location study the Company will transport 6%
Li in solution post the DLE and concentration stages at Laguna Verde to the
carbonation plant. Use of standard and electric trucks is being compared with
the latter providing several potential benefits in addition to cutting CO(2)
emissions. Electric trucks are well suited to hauling loads from high to low
altitudes by taking advantage of regenerative charging to reduce power
consumption and required battery capacity. Minimal noise and elimination of
tailpipe emissions is particularly attractive considering the transport route
traverses an indigenous community settlement approximately 100km from the
project site, a community the company has been working with closely.

The Company has gathered insight from several potential suppliers. Chinese
company XCMG is a leader in electric trucks and is actively expanding its
offering in Chile, with its E7-49T model which has a haulage load of 49 tonnes
potentially providing a suitable option. The technology is evolving rapidly
and is expected to provide a strongly cost competitive option in line with the
project development timeline.

Figure. 6: XCMG´s range of electric transport trucks       Figure. 7:
Paved Highway to Laguna Verde

2024 Exploration Programme Update

CleanTech Lithium´s 2024 drilling programme anticipated to drill five new
resource wells, as shown in Figure 8, with the aim of upgrading the existing
Measured and Indicated resource into maiden Reserves for the Laguna Verde
project.  The existing JORC compliant resource estimate of 1.8 million tonnes
of lithium carbonate equivalent (LCE) is based on six wells completed in 2022
and 2023.  The Company engaged Montgomery & Associates Consultores
Limitada ("Montgomery" or "M&A"), a leading hydrogeological consultant,
for the programme. During 1H 2024, two of the five resource wells were
completed being LV07 and LV11, along with three observation wells drilled to
support observations during pumping tests, before winter conditions curtailed
the programme in June 2024. The full 2024 programme is paused until further
funding is available following the Company´s planned ASX fund raising and as
a result Montgomery has produced an interim report on work completed.

      Figure 8: Laguna Verde Drilling Wells Map - Show original figure

Drilling activities for exploration borehole LV07 reached a final depth of
650m below land surface. This well was drilled with PQ3 diameter from land
surface to 300m, and with HQ3 diameter from 300m to 650m. Packer samples were
obtained during drilling for 2-meter packer intervals and the volume of the
well was purged at least one time before obtaining the sample. Assuming a
lithium cut-off grade of 100 mg/L, the average lithium grade of the packer
samples corresponds to 139 mg/L with the well encountering lower density water
in the upper 150m.

In contrast to LV07, drilling at LV11 did not reach the anticipated depth due
to the presence of hydrothermal waters (under pressure) which were encountered
during drilling, with a final depth of 412.8m below land surface. Assuming a
lithium cut-off grade of 100 mg/L, the average lithium grade of the packer
results would correspond to 131 mg/L. In general, it is believed that lithium
grades decrease below 220m at LV11 due to the presence of dilute hydrothermal
waters which were encountered during drilling. The presence of hydrothermal
waters in the eastern portion of the Project are more dilute than the average
lithium grade measured in other exploration wells.

Figure 9: Drilling at LV07 in 1H 2024

Lithology and Drainable Porosity

Based on core retrieved from drilling, the most predominant lithology
encountered corresponds to a volcanic tuff with variable levels of
consolidation and welding based on the depth and location. As determined by
relative brine release testing at Geosystems Analysis (GSA) laboratory in
Tuscon, USA, drainable porosity values of collected core samples from LV07 and
LV11 range from 0.3% to 9.2%, with an arithmetic average of approximately 4%;
this is considered by Montgomery to be reasonable for the encountered
lithologic units based on visual inspection of the core.

Figure 10: Example of Drill Core from Exploration Borehole LV11 (132 to 136m)

Hydrogeological Evaluation

In addition to resource drilling, the 2024 campaign aimed to complete pump
tests to evaluate the feasibility of lithium brine extraction for the Project
and to also estimate aquifer parameters. Prior to the winter break, three
observation wells were completed and initial variable rate step tests and a
constant rate flow test undertaken. The intended long duration pump tests at
well LV05 was not able to be completed, however a 7-day pumping test was
successfully completed at LV06. With data obtained to date, Montgomery is able
to continue refining the hydrogeological modelling that will feed into the
design of the extraction and reinjection well fields for the PFS.  A key
aspect is to ensure no impact on surface water bodies.

Recommendations and Next Steps

Based on the obtained results from the 2024 exploration programme, recommended
priorities for continued exploration include additional drilling and testing
in the western portion of the Project concessions. A long-term pump test at
LV05 (as part of the planned reinjection test) will also aid in demonstrating
feasible extraction and reinjection to the west of the basin. A long-term test
at LV05 will also allow for a better understanding of the hydraulic connection
between the deep and shallow aquifers in that area.

On the completion of the 5 well programme as originally planned for 2024, the
existing JORC compliant resource estimate of 1.8 million tonnes will be
updated and a Reserve estimate will be calculated for the project.  The
Reserve calculation is the economically mineable part of the Measured and/or
Indicated resource and this will be defined by the PFS data demonstrating that
extraction could reasonably be justified.  Progress continues on the PFS and
the remaining planned wells will be completed as funds are available following
completion of the planned ASX capital raising.

Pilot Plant Update

Downstream conversion of concentrated eluate from the Company´s pilot plant
into battery grade lithium commenced last week at the facilities of Conductive
Energy in Chicago, USA.  The initial volume of 88m(3) of concentrated eluate
from Laguna Verde, equal to approximately one tonne of lithium carbonate
equivalent ("LCE"), will be processed in four batches with the first batch
expected to produce a volume of battery-grade sample product in November. With
this product, the Company plans to engage with strategic partners for product
qualification.

 For further information contact:
 CleanTech Lithium PLC
 Steve Kesler/Gordon Stein/Nick Baxter          Jersey office: +44 (0) 1534 668 321

                                                Chile office: +562-32239222
                                                Or via Celicourt
 Celicourt Communications                       +44 (0) 20 7770 6424

 Felicity Winkles/Philip Dennis/Ali AlQahtani   cleantech@celicourt.uk (mailto:cleantech@celicourt.uk)
 Beaumont Cornish Limited (Nominated Adviser)   +44 (0) 20 7628 3396

 Roland Cornish/Asia Szusciak
 Fox-Davies Capital Limited (Joint Broker)      +44 (0) 20 3884 8450

 Daniel Fox-Davies                              daniel@fox-davies.com (mailto:daniel@fox-davies.com)
 Canaccord Genuity (Joint Broker)               +44 (0) 20 7523 4680

 James Asensio

 

Competent Persons

 

The following professionals act as Competent Persons (CPs), as defined in the
AIM Note for Mining, Oil and Gas Companies (June 2009) and JORC Code (2012):

 

Mike Rosko and Brandon Schneider of M&A are Registered Members of the
Society of Mining, Metallurgy, and Exploration and have functioned as CPs for
lithium brine projects under Canadian, Australian, and United States technical
reporting standards. Their relevant experience includes:

 

·    Mike Rosko has been estimated lithium brine resources since 2010, and
has functioned as a CP for Lithium One's Sal de Vida project, Millennial
Lithium's Pastos Grandes project, Lithium Chile's Salar de Arizaro project,
NOA Lithium's Rio Grande project, Lithium America's Cauchari project, Wealth
Minerals' Salar de Ollague project, Gangfeng's Mariana project, Eramine's
Centenario/Ratones project, Posco Lithium's Sal de Oro project, Pepennini's
Salar de Pular project, and others, and has prepared numerous third party due
diligence and independent geologist reports in Argentina, Chile, and the
United States.

·    Brandon Schneider specializes in lithium brine reserve estimates,
variable density flow modeling, and optimization of brine pumping in salt
flats of Argentina and Chile. He has functioned as a CP for the Sal de Vida
Project of Arcadium Lithium and Salar de Arizaro Project of Lithium Chile and
was responsible for the reserve estimate and projected wellfield design. He
also collaborates on the lithium brine exploration phases, resource
estimation, and due diligence reviews for lithium brine projects.

 

Beaumont Cornish Limited ("Beaumont Cornish") is the Company's Nominated
Adviser and is authorised and regulated by the FCA. Beaumont Cornish's
responsibilities as the Company's Nominated Adviser, including a
responsibility to advise and guide the Company on its responsibilities under
the AIM Rules for Companies and AIM Rules for Nominated Advisers, are owed
solely to the London Stock Exchange. Beaumont Cornish is not acting for and
will not be responsible to any other persons for providing protections
afforded to customers of Beaumont Cornish nor for advising them in relation to
the proposed arrangements described in this announcement or any matter
referred to in it.

 

Notes

CleanTech Lithium (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF) is an exploration and
development company advancing lithium projects in Chile for the clean energy
transition. Committed to net-zero, CleanTech Lithium's mission is to become a
new supplier of battery grade lithium using Direct Lithium Extraction
technology powered by renewable energy.

CleanTech Lithium has two key lithium projects in Chile, Laguna Verde and
Viento Andino, and exploration stage projects in Llamara and Arenas Blancas
(Salar de Atacama), located in the lithium triangle, a leading centre for
battery grade lithium production. The two most advanced projects: Laguna Verde
and Viento Andino are situated within basins controlled by the Company,
which affords significant potential development and operational advantages.
All four projects have good access to existing infrastructure.

CleanTech Lithium is committed to utilising Direct Lithium Extraction with
reinjection of spent brine resulting in no aquifer depletion. Direct Lithium
Extraction is a transformative technology which removes lithium from brine
with higher recoveries, short development lead times and no extensive
evaporation pond construction. www.ctlithium.com (https://ctlithium.com/)

 

**ENDS**

 

APPENDIX

Section 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

 

 Criteria                                                           JORC Code explanation                                                            Commentary
 Sampling techniques                                                ·   Nature and quality of sampling (eg cut channels, random chips, or
                                                                    specific specialised industry standard measurement tools appropriate to the

                                                                    minerals under investigation, such as down hole gamma sondes, or handheld XRF    ·   Sub-surface brine samples were obtained using six different methods:
                                                                    instruments, etc). These examples should not be taken as limiting the broad      Packer sampling, PVC airlift sampling, disposable bailer sampling, electric
                                                                    meaning of sampling.                                                             valve bailer sampling, HydraSleeve sampling, and composite brine sampling

                                                                                during pumping tests.
                                                                    ·   Include reference to measures taken to ensure sample representativity

                                                                    and the appropriate calibration of any measurement tools or systems used.        ·   Brine water samples were taken from the surface of the lagoon, in an

                                                                                800 m sampling grid, including eight sampling duplicates at random locations.
                                                                    ·   Aspects of the determination of mineralisation that are Material to the      The samples were taken from a 0.5 m depth, and for positions with a depth
                                                                    Public Report.                                                                   above 5 m, a bottom sample was also obtained.

                                                                    ·   In cases where 'industry standard' work has been done this would be          ·   In the field, electrical conductivity and temperature were measured for
                                                                    relatively simple (eg 'reverse circulation drilling was used to obtain 1 m       every sample with a Hanna Multiparameter device. All materials and sampling
                                                                    samples from which 3 kg was pulverised to produce a 30 g charge for              bottles were first flushed with brine water before being filled.

                                                                    fire assay'). In other cases more explanation may be required, such as where
                                                                    there is coarse gold that has inherent sampling problems. Unusual commodities

                                                                    or mineralisation types (eg                                                      ·   For every sample, 2 liters of brine were obtained with a 1-liter double
                                                                                                                                                     valve bailer, using a new bailer for each sampling position. All materials and
                                                                                                                                                     sampling bottles were first flushed with 100 cc of brine water before
                                                                                                                                                     receiving the final sample. Electrical conductivity was measured for every
                                                                                                                                                     sample with a Hanna Multiparameter model HI98192. The last two samples that
                                                                                                                                                     had similar stabilized electrical conductivity values were identified as the
                                                                                                                                                     primary and duplicate samples.

                                                                                                                                                     ·   For the packer sampling, a packer bit tool provided by the drilling
                                                                                                                                                     company (Big Bear) was used. Once the sampling support was sealed, a
                                                                    submarine nodules) may warrant disclosure of detailed information.               purging operation took place until no drilling mud was detected. After the
                                                                                                                                                     purging operation, a half an hour waiting period took place to let brine enter
                                                                                                                                                     to the packer tool before sampling with a double valve bailer.

                                                                                                                                                     ·   Successive 1-liter samples were taken every 30 minutes with a double
                                                                                                                                                     valve bailer.

                                                                                                                                                     ·   Packer samples were obtained approximately every 18 m.

                                                                                                                                                     ·   PVC casing suction brine samples were extracted after well development.
                                                                                                                                                     Once the well was clean and enough water was purged (at least three times the
                                                                                                                                                     well volume), the PVC casing suction samples were taken from bottom to top
                                                                                                                                                     while the 2-inch PVC was extracted from the well. A 20-liter bucket was filled
                                                                                                                                                     with brine and samples were obtained from the bucket once the remaining fine
                                                                                                                                                     sediments were decanted.

                                                                                                                                                     ·    Brine airlift samples were taken every 6 m.

                                                                                                                                                     ·    Disposable bailer samples were obtained by JCP Ltda. specialists in
                                                                                                                                                     water sampling. Samples were taken from the interest depths with a double
                                                                                                                                                     valve disposable bailer. The bailer was lowered and raised with an electric
                                                                                                                                                     cable winch to maintain a constant velocity and avoid bailer valves opening
                                                                                                                                                     after taking the sample. A new bailer was used for each well.

                                                                                                                                                     ·    Disposable bailer samples were obtained every 6 m.

                                                                                                                                                     ·    In the first quarter of 2023, electric bailer samples were taken from
                                                                                                                                                     wells LV05, LV06, and LV02 after their proper development. Depth-specific
                                                                                                                                                     samples were obtained with a 1- liter electric bailer. This sampling process
                                                                                                                                                     was undertaken by Geodatos specialists.

                                                                                                                                                     ·   On all sampling procedures the materials and
                                                                                                                                                     sampling bottles were first flushed with 100 cc of brine water before
                                                                                                                                                     receiving the final sample.

                                                                                                                                                     ·   Packer samples were taken in wells LV01, LV02, LV03, LV07, and LV11.
                                                                                                                                                     Airlift samples were obtained from wells LV01, LV04, LV05, and LV06.
                                                                                                                                                     Disposable bailer samples were taken in wells LV01 and LV02. Electronic bailer
                                                                                                                                                     samples were obtained from wells LV02, LV05, and LV06. HydraSleeve samples
                                                                                                                                                     were taken from LV04 and LV11. Composite brine samples from pumping tests were
                                                                                                                                                     taken at wells LV05 and LV06.
 Drilling techniques                                                ·   Drill type (eg core, reverse circulation, open-hole hammer, rotary air
                                                                    blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple or

                                                                    standard tube, depth of diamond tails, face-sampling bit or other type,          ·   Diamond drilling with a PQ3 diameter was used to drill wells LV01 and
                                                                    whether core is oriented and if so, by what method, etc).                        LV03 to a depth of 320

                                                                                                                                                     m. Below that depth, the drilling diameter was reduced to HQ3.

                                                                                                                                                     ·   At wells LV02 and LV04, diamond drilling with a PQ3 diameter was used
                                                                                                                                                     to their final depth.

                                                                                                                                                     ·   For both diameters, a triple tube core barrel was used for the core
                                                                                                                                                     recovery.

                                                                                                                                                     ·   Except for drillhole LV04, custom-made packer bits provided by Big Bear
                                                                                                                                                     were used to obtain brine samples.

                                                                                                                                                     ·   Drillholes LV01, LV02 and LV04 were cased with 3" PVC and silica
                                                                                                                                                     gravel. LV03 was not cased due to well collapse and tool entrapment.

                                                                                                                                                     ·   Wells LV05 and LV06 were drilled using the flooded reverse drilling
                                                                                                                                                     method with a 14 ¾ inch diameter to their final depths. Both wells were cased
                                                                                                                                                     with 8-inch PVC and gravel pack.

                                                                                                                                                     ·   Diamond drillholes LVM05a and LVM06c were drilled with a HQ3 diameter
                                                                                                                                                     from surface to the final depth. LVM05b was drilled with Tricone 3 7/8"
                                                                                                                                                     diameter from land surface to 41.5 m.
                                                                                                                                                     ·   Diamond drillhole LV07 was drilled with PQ3 diameter from land surface
                                                                                                                                                     to 300 m, and with HQ3 diameter from 300 to 650 m.

                                                                                                                                                     ·   Diamond drillhole LV11 was drilled with PQ3 diameter from land surface
                                                                                                                                                     to 254 m with no recovery in the first 50 meters, and it was drilled with HQ3
                                                                                                                                                     diameter from 254 to 412.85 m.

                                                                                                                                                     Development operations

                                                                                                                                                     ·   After PVC casing and silica gravel installation took place at the
                                                                                                                                                     exploration wells, a development process was undertaken to ensure clean
                                                                                                                                                     aquifer water was available during sampling. The well development included
                                                                                                                                                     injection of a hypochlorite solution to break the drilling additives, and
                                                                                                                                                     purging via airlifting of a minimum three well volumes was undertaken to clean
                                                                                                                                                     the cased well from drilling mud.

                                                                                                                                                     ·   The developing process was made using a small rig, a high-pressure
                                                                                                                                                     compressor and 2-inch threaded PVC that can be coupled to reach any depth. The
                                                                                                                                                     purging/cleaning operation was made from top to bottom, injecting air with a
                                                                                                                                                     hose inside the 2-inch PVC and "suctioning" the water to emulate a reverse
                                                                                                                                                     circulation (airlift) system.
 Drill sample recovery                                              ·   Method of recording and assessing core and chip sample recoveries and        ·   Diamond core recovery was ensured by direct supervision and continuous
                                                                    results assessed.                                                                geological logging in the field.

                                                                    ·   Measures taken to maximise sample recovery and ensure representative         ·   For wells drilled using the flooded reverse drilling method, drill
                                                                    nature of the samples.                                                           cuttings were collected in 10 kg sample bags for geological logging and tests

                                                                                purposes. Direct supervision and continuous geological logging were applied to
                                                                    ·   Whether a relationship exists between sample recovery and grade and          ensure reliable recovery and descriptions.
                                                                    whether sample bias may have
                                                                    occurred due to preferential loss/gain of fine/coarse material.
 Logging                                                            ·   Whether core and chip samples have been geologically and geotechnically      ·   Geological logging took place continuously during drilling in the
                                                                    logged to a level of detail to support appropriate Mineral Resource              field. Descriptions were done by CleanTech and M&A.
                                                                    estimation, mining studies and metallurgical studies.

                                                                                ·   Logging forms were prepared prior to field work and were used to ensure
                                                                    ·   Whether logging is qualitative or quantitative in nature. Core (or           the same information and style was used regardless of the field geologist.
                                                                    costean, channel, etc) photography.

                                                                    ·   The total length and percentage of the relevant intersections logged.
 Sub- sampling techniques and          sample preparation           ·   If core, whether cut or sawn and whether quarter, half or all core           ·    During the brine batch preparation process, the samples were
                                                                    taken.                                                                           transferred to new sampling bottles. Quality control samples, including

                                                                                standards (internal standards composed of a known stable brine), duplicates,
                                                                    ·   If non-core, whether riffled, tube sampled, rotary split, etc and            and blank samples (distilled water) were randomly included in the batch. After
                                                                    whether sampled wet or dry.                                                      quality control sample insertion, all samples were re-numbered before

                                                                                submitting to laboratory. Before transferring each sample, the materials used
                                                                    ·   For all sample types, the nature, quality and appropriateness of the         for the transfer were flushed with distilled water and were then shaken to
                                                                    sample preparation technique.                                                    remove water excess, avoiding contamination.

                                                                    ·   Quality control procedures adopted for all sub-sampling stages to
                                                                    maximise representivity of samples.

                                                                    ·   Measures taken to ensure that the sampling is representative of the in
                                                                    situ material collected, including for instance results for field
                                                                    duplicate/second-half sampling.

                                                                    ·   Whether sample sizes are
                                                                    appropriate to the grain size of the material being sampled.
 Quality        of                                                  ·   The nature, quality and appropriateness of the assaying and laboratory       ·    Brine samples were assayed by ALS Life Science Chile laboratory

                                                                  procedures used and whether the technique is considered partial or total.        (ALS), for Li, K, B, Mg, Ca, Cu, and Na using the ICP-OES method described on
 assay      data and laboratory tests
                                                                                QWI-IO-ICP-OES- 01 Edition A, Modification 0 EPA 3005A; EPA 200.2.
                                                                    ·   For geophysical tools, spectrometers, handheld XRF instruments, etc,
                                                                    the parameters used in determining the analysis including instrument make and
                                                                    model, reading times, calibrations factors applied and their derivation, etc.

                                                                    ·   Nature of quality control procedures adopted (eg standards, blanks,
                                                                    duplicates, external laboratory checks) and whether acceptable levels of
                                                                    accuracy (ie lack of bias) and precision have been established.
                                                                                                                                                     ·    For density measurements, the method described by Thompson and Troeh
                                                                                                                                                     Y "Los suelos y su fertilidad." 2002. Editorial Reverté

                                                                                                                                                     S.A. Cuarta Edición. Págs.75-85, was used.
                                                                                                                                                     ·    Chlorine determination was done based on Standard Methods for the
                                                                                                                                                     Examination of Water and Wastewater, 23rd Edition 2017. Método 4500-Cl-B
                                                                                                                                                     QWI-IO-Cl-01 Emisión B, mod. 1. SM 4500-Cl- B, 22nd Edition 2012.
                                                                                                                                                     ·    Total Dissolved Solid (TDS) determination was done using the method
                                                                                                                                                     described on INN/SMA SM 2540 C Ed 22, 2012.
                                                                                                                                                     ·    Sulfate was analyzed according to the method described in INN/SMA SM
                                                                                                                                                     4500 SO4-D Ed 22, 2012.
                                                                                                                                                     ·    Duplicates were obtained randomly during brine sampling. Also, blanks
                                                                                                                                                     (distilled water) and standards were randomly inserted during the laboratory
                                                                                                                                                     batch preparation.
                                                                                                                                                     ·    The 2022 standards were prepared by the Universidad Católica del
                                                                                                                                                     Norte, Chile using a known stable brine. Standard nominal grade was calculated
                                                                                                                                                     in a round-robin process that included four laboratories. The ALS laboratory
                                                                                                                                                     was validated during the round-robin process.
                                                                                                                                                     ·    Check samples composed by standards, duplicates, and blanks were
                                                                                                                                                     inserted at a rate of

                                                                                                                                                     one for each 20 original samples during the year 2022.

 

                                                                                                                                                                ·    After the year 2023, quality control samples were inserted at a rate
                                                                                                                                                                of one every 10 original samples. For the 2023 QA/QC process, a new set of
                                                                                                                                                                standards was internally prepared using 200 liters of brine obtained from well
                                                                                                                                                                LV02 during the development process. Standard nominal lithium grade was
                                                                                                                                                                calculated in a round-robin process that included four laboratories.

                                                                                                                                                                ·    For the 2024 sampling campaign, duplicates, standards, and blanks
                                                                                                                                                                were utilized during brine sampling and were submitted for analysis. Standards
                                                                                                                                                                for the 2024 campaign were prepared in the University of Antofagasta. Quality
                                                                                                                                                                control samples were inserted at a rate of approximately one every 10 original
                                                                                                                                                                samples.

                                                                                                                                                                Geophysics:

                                                                                                                                                                ·    To determine the lake bathymetry, a Garmin Echomap CV44 and Eco Probe
                                                                                                                                                                CV20-TM Garmin were used. The equipment has a resolution of 0.3 ft and maximum
                                                                                                                                                                depth measurement of 2,900 ft. The bathymetry data was calibrated using a
                                                                                                                                                                density of 1.14 g/cm(3).

                                                                                                                                                                ·    For the TEM geophysical survey, a Zonge multipurpose digital receiver
                                                                                                                                                                model GDP-32 and TEM transmitter model ZT-30 were used.

                                                                                                                                                                ·    For the first survey campaign in May 2021, a coincident
                                                                                                                                                                transmission/reception loop was utilized with 11 lines and a 400 m separation.
                                                                                                                                                                167 stations where designated with a 100x100 m(2) loop and four stations with
                                                                                                                                                                a 200x200 m(2) loop; a survey depth of 300 m and 400 m was reached,
                                                                                                                                                                respectively.

                                                                                                                                                                ·    For the second TEM geophysical survey in March 2022, 32 TEM stations
                                                                                                                                                                were surveyed which utilized six lines and a 400 m separation. A coincident
                                                                                                                                                                loop Tx=Rx of 200 x 200 m(2)
                                                                                                                                                                allowed for the investigation to a depth of 400 m.

                                                                                                                                                                ·    For the third TEM geophysical survey in January 2023, 14 TEM stations
                                                                                                                                                                were surveyed with two lines and a 400 m separation. A coincident loop Tx=Rx
                                                                                                                                                                of 200x200 m(2) allowed for investigation to a depth of 400 m.

                                                                                                                                                                ·    The equipment used for the gravity survey was a Scintrex portable
                                                                                                                                                                digital model CG-5 Autograv, "microgravity meter", with a 0.001 mGal
                                                                                                                                                                resolution as well as a tidal, temperature, pressure, and automatic leveling
                                                                                                                                                                correction system.

                                                                                                                                                                ·    The topographic data measured during the gravity survey was acquired
                                                                                                                                                                with a double frequency differential positioning equipment, brand CHC NAV,
                                                                                                                                                                model I-80 GNSS, that consists of two synchronized instruments, the first of
                                                                                                                                                                which was fixed at a known topographic station, and the other that is mobile
                                                                                                                                                                through the surveyed gravimetric stations.

                                                                                                                                                                ·    In January 2023, a gravity survey was made consisting of 111
                                                                                                                                                                stations, with a separation of 200 m to 300 m, and arrangement through four
                                                                                                                                                                lines around the lagoon area.
 Verification of sampling and assaying                                          ·   The verification of significant intersections by either independent or      ·   The assay data was verified by M&A and C. Fedderson based on the
                                                                                alternative company personnel.                                                  assay certificates.

                                                                                ·   The use of twinned holes.                                                   ·   Data from bathymetry and geophysics was used as delivered by Servicios

                                                                               Geológicos Geodatos SAIC.
                                                                                ·   Documentation of primary data, data entry procedures, data

                                                                                verification, data storage (physical and electronic) protocols.                 ·   Geological logs were managed by the geology contractor GEOMIN and were

                                                                               checked by the Competent Persons.
                                                                                ·   Discuss any adjustment to assay data.

                                                                                                                                                                ·   Brine samples batches were prepared personally

                                                                                                                                                                by the competent person, JCP Ltda., Geomin SpA or according to Competent
                                                                                                                                                                Person's instructions. All data was stored in Excel files.
 Location      of data points                                                   ·   Accuracy and quality of surveys used to locate drill holes (collar and      ·   Sample coordinates were obtained with a non- differential hand-held GPS
                                                                                down-hole surveys), trenches, mine workings and other locations used in         unit.
                                                                                Mineral Resource estimation.

                                                                               ·   The bathymetry coordinates in Laguna Verde were obtained by a Thales
                                                                                ·   Specification of the grid system used.                                      Navigation differential GPS system, which consists of two GPS ProMark3 devices

                                                                               designed to work in geodesic, cinematic, and static modes of high precision,
                                                                                ·   Quality and adequacy of topographic control.                                where one of the instruments was installed as a base station and the other on
                                                                                                                                                                board of the craft.

                                                                                                                                                                ·   The TEM geophysical survey coordinates were obtained with a
                                                                                                                                                                non-differential hand-held GPS unit.

                                                                                                                                                                ·   Drillhole collars were obtained with a non- differential hand-held GPS
                                                                                                                                                                unit. Positions were verified by the mining concession field markings.

                                                                                                                                                                ·   Gravity stations were located with double frequency differential
                                                                                                                                                                positioning equipment, brand CHC NAV, model I-80 GNSS, that consists of two
                                                                                                                                                                synchronized pieces of equipment, one fixed at a known topographic station,
                                                                                                                                                                and the other mobile at the surveyed gravity stations.

                                                                                                                                                                ·   The coordinate system is UTM, Datum WGS84 Zone 19S.

                                                                                                                                                                ·   Topographic control is not considered critical as the lagoon and its
                                                                                                                                                                surroundings are generally flat lying and the samples were definitively
                                                                                                                                                                obtained from the lagoon.

                                                                                                                                                                ·   Location points were not surveyed at the Llamara and Atacama
                                                                                                                                                                concessions.
 Data spacing and distribution                                                  ·   Data spacing for reporting of Exploration Results.                          ·   The geochemical lagoon sample spacing was approximately 800 m, covering

                                                                               the entire lagoon area.
                                                                                ·   Whether the data spacing and distribution is sufficient to establish

                                                                                the degree of geological and grade continuity appropriate for the Mineral       ·   Packer brine samples were taken vertically every 18 m.
                                                                                Resource and Ore Reserve estimation procedure(s) and classifications applied.

                                                                                ·   Whether sample compositing has been applied.

                                                                                                                                                                ·   PVC bailer samples (disposable and electric) were taken vertically
                                                                                                                                                                every 6 m.

                                                                                                                                                                ·   For bathymetry, two grids were used, one of 400 m and the other of 200
                                                                                                                                                                m in areas where the perimeter has more curves.

                                                                                                                                                                ·   For TEM geophysical surveys, the distance between stations was 400 m.

                                                                                                                                                                ·   For the gravimetric survey, the distance between stations was 200 - 300
                                                                                                                                                                m.

                                                                                                                                                                ·   The author believes that the data spacing and distribution are
                                                                                                                                                                sufficient to establish the degree of geological and grade continuity
                                                                                                                                                                appropriate for the Resource Estimate.
 Orientation of       data     in relation       to geological                  ·   Whether the orientation of sampling achieves unbiased sampling of           ·   The lagoon in Laguna Verde is a free water body and no mineralized
 structure                                                                      possible structures and the extent to which this is known, considering the      structures are expected in the sub-surface deposits.
                                                                                deposit type.

                                                                                ·   If the relationship between the drilling orientation and the
                                                                                orientation of key mineralised structures is considered to have introduced a
                                                                                sampling bias, this should be assessed and reported if material.
 Sample security                                                                ·   The measures taken to ensure sample security.                               ·   All brine samples were marked and kept on site before transporting them
                                                                                                                                                                to the Copiapó city warehouse where the laboratory sample batch was prepared
                                                                                                                                                                and stored in sealed plastic boxes. Subsequently, the Laguna Verde samples
                                                                                                                                                                were sent via courier to the ALS laboratory in Antofagasta. The transport of
                                                                                                                                                                samples was directly supervised by the Competent Person.

                                                                                                                                                                ·   ALS laboratory personnel reported that the

                                                                                                                                                                samples were received without any problem or disturbance.
 Audits         or reviews                                                      ·   The results of any audits or reviews of sampling techniques and data.       ·   The assay data was verified by M&A and C. Fedderson against the
                                                                                                                                                                assay certificates.

                                                                                                                                                                ·    The July 2021 JORC technical report was reviewed by Montgomery &
                                                                                                                                                                Associates Vice President and CP Michael Rosko, MS PG, SME Registered Member
                                                                                                                                                                #4064687. In the report, he concludes that "The bulk of the information for
                                                                                                                                                                the Laguna Verde exploration work and resulting initial lithium resource
                                                                                                                                                                estimate was summarized Feddersen (2021). Overall, the CP agrees that
                                                                                                                                                                industry-standard methods were used, and that the initial lithium resource
                                                                                                                                                                estimate is reasonable based on the information available".

                                                                                                                                                                ·    The September 2022 JORC Report Laguna Verde Updated Resource
                                                                                                                                                                Estimation Report, and data acquisition and QA/QC protocols were audited on
                                                                                                                                                                October, 2022 by Don Hains, P. Geo. from Hains Engineering Company Limited (D.
                                                                                                                                                                Hains October 2022 QA/QC Procedures, Review, Site Visit Report).

                                                                                                                                                                ·    Hains concluded that "The overall QA/QC procedures employed by
                                                                                                                                                                CleanTech are well documented and the exploration data collected and analysed
                                                                                                                                                                in a comprehensive manner. There are no significant short comings in the
                                                                                                                                                                overall programme."

                                                                                                                                                                ·    With respect to the exploration program, Hains
                                                                                                                                                                stated that "the overall exploration program has been well designed and well
                                                                                                                                                                executed. Field work appears to have been well managed, with excellent data
                                                                                                                                                                collection. The drill pads have been restored to a very high standard. The TEM
                                                                                                                                                                geophysical work has been useful in defining the extensional limits of the
                                                                                                                                                                salar at Laguna Verde".

                                                                                                                                                                ·    With respect to specific yield, Hains stated that "RBRC test work at
                                                                                                                                                                Danial B. Stevens Associates has been well done. It is recommended obtaining
                                                                                                                                                                specific yield data using a second method such as centrifuge, nitrogen
                                                                                                                                                                permeation or NMR. The available RBRC data indicates an average Sy value of
                                                                                                                                                                5.6%. This is a significant decrease from the previously estimated value of
                                                                                                                                                                approximately 11%. The implications of the lower RBRC value in terms of the
                                                                                                                                                                overall resource estimate should be carefully evaluated".

                                                                                                                                                                ·    Several recommendations were made by Mr. Hains in his report to
                                                                                                                                                                improve the QA/QC protocols, data acquisition, assays, presentation, and
                                                                                                                                                                storage. His recommendations have been

                                                                                                                                                                considered and included in the exploration work schedule since October 2022.

Section 2 Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section.)

 

 Criteria                                                                       JORC Code explanation                                                            Commentary
 Mineral tenement and              land tenure status                           ·   Type, reference name/number, location and ownership including                ·   In Laguna Verde, CleanTech, through Atacama Salt Lakes SpA, has 66
                                                                                agreements or material issues with third parties such as joint ventures,         pedimentos constituidos which cover an area of 17,200 hectares, 7 solicitudes
                                                                                partnerships, overriding royalties, native title                                 de mensura which cover an area of 682 hectares, and 35 pertenencias which

                                                                                cover an area of 3,860 hectares. Lithium exploration can occur on each with
                                                                                interests, historical sites, wilderness or national park                         the exception of the pedimentos constituidos where another mining company has
                                                                                                                                                                 preference.
                                                                                and environmental settings.                                                      ·   All concession acquisition costs and taxes have been reportedly fully

                                                                                paid by CleanTech, and there are no claims or liens against them.
                                                                                ·   The security of the tenure held at the time of reporting along with any

                                                                                known impediments to obtaining a licence to operate in the area.                 ·   In Laguna Verde, CleanTech is also in the application process for a
                                                                                                                                                                 Contrato Especial de Operation de Litio (CEOL) from the Chilean Government,
                                                                                                                                                                 which would grant them the sole right to explore and exploit lithium in the
                                                                                                                                                                 basin.
 Exploration done           by other parties                                    ·   Acknowledgment and appraisal of exploration by other parties.                ·   In Laguna Verde, exploration work has also been done by Pan American
                                                                                                                                                                 Lithium and Wealth Minerals Ltda.
 Geology                                                                        ·   Deposit type, geological setting and style of mineralization.                ·   Laguna Verde is a hypersaline lagoon that is classified as an immature
                                                                                                                                                                 clastic salar. The deposit is composed of a surface brine resource, including
                                                                                                                                                                 the brine water volume of the surface lagoon. The sub-surface resource formed
                                                                                                                                                                 by brine water hosted in volcano-clastic sediments that lie beneath the
                                                                                                                                                                 lagoon.
 Drill         hole Information                                                 ·   A summary of all information material to the understanding of the            ·   The following drillhole are in the WGS84 zone 19 S coordinate system:
                                                                                exploration results including a tabulation of the following information for

                                                                                all Material drill holes:                                                        ·   LV01 E549,432 N7,027,088 ELEV 4,429 m a.s.l.

                                                                                o easting and northing of the drill hole collar                                  Azimuth 0°, dip -90°, Length 474 m

                                                                                o elevation or RL (Reduced Level - elevation above sea level in metres) of the   ·   LV02 E 553,992 N 7,024,396 ELEV 4,354 m a.s.l.
                                                                                drill hole collar

                                                                                Azimuth 0°, dip -90°, Length 339.4 m
                                                                                o dip and azimuth of the hole

                                                                                ·   LV03 E 549,980 N 7,028,434 ELEV 4,402 m a.s.l.
                                                                                o down hole length and interception depth

                                                                                Azimuth 120°, dip -60°, Length 547.5 m
                                                                                o hole length.

                                                                                ·   LV04 E 556,826 N 7,024,390 ELEV 4,350 m a.s.l.
                                                                                ·   If the exclusion of this information is justified on the basis that the

                                                                                information is not Material                                                      Azimuth 0°, dip -90°, Length 311 m

                                                                                                                                                                 ·   LV05 E 550,972 N 7,027,908 ELEV 4,355 m a.s.l.
                                                                                and this exclusion does not detract from the understanding of the report, the    Azimuth 0°, dip -90°, Length 434.6 m
                                                                                Competent Person should clearly explain why this is the case.

                                                                                                                                                                 ·   LV06 E 555,912 N 7,026,004 ELEV 4,335 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 405 m
                                                                                                                                                                 ·   LVM05a E 550,921 N 7,027,908 ELEV 4,355 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 221.5 m
                                                                                                                                                                 ·   LVM05b E 550,946 N 7,027,951 ELEV 4,355 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 41.5 m
                                                                                                                                                                 ·   LVM06c E 555,959 N 7,026,032 ELEV 4,335 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 40 m
                                                                                                                                                                 ·   LV07 E 552,561 N 7,025,296 ELEV 4,345 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 650 m
                                                                                                                                                                 ·   LV11 E 555,582 N 7,024,793 ELEV 4,345 m a.s.l.

                                                                                                                                                                 Azimuth 0°, dip -90°, Length 412.8 m
 Data aggregation methods                                                       ·   In reporting Exploration Results, weighting averaging techniques,            ·   For the surface brine results, no low-grade truncation or high-grade
                                                                                maximum and/or minimum grade truncations (eg cutting of high grades) and         capping has been implemented due to the consistent nature of the brine assay
                                                                                cut-off grades are usually Material and should be stated.                        data.

                                                                                ·   Where aggregate intercepts incorporate short lengths of high grade           ·   For the sub-surface results, no low-grade truncation or high-grade
                                                                                results and longer lengths of low grade                                          capping has been implemented in the presented exploration data, however an

                                                                                average lithium grade of the packer brine samples is also provided with an
                                                                                results, the procedure used for such aggregation should                          assumed cut-off grade of 100 mg/L due to potential processing requirements and
                                                                                                                                                                 cost considerations.
                                                                                be stated and some typical examples of such aggregations should be shown in
                                                                                detail.

                                                                                ·   The assumptions used for any reporting of metal equivalent values
                                                                                should be clearly stated.
 Relationship between mineralizati on           widths and intercept            ·   These relationships are particularly important in the reporting of           ·   In Laguna Verde, the relationship between aquifer widths and intercept
 lengths                                                                        Exploration Results.                                                             lengths are direct with vertical wells, however LV03 was inclined with a dip

                                                                                of -60°.
                                                                                ·   If the geometry of the mineralisation with respect to the drill hole
                                                                                angle is known, its nature should be reported.

                                                                                ·   If it is not known and only the down hole lengths are reported, there
                                                                                should be a clear statement to this effect (eg 'down hole length, true width
                                                                                not known').
 Diagrams                                                                       ·   Appropriate maps and sections (with scales) and tabulations of
                                                                                intercepts should be included for any significant discovery being reported
                                                                                These should include, but not be limited to a plan view of drill hole collar
                                                                                locations and appropriate sectional views.
                                                                                                                                                                                                                       ·

                                                                                                                                                                                                                       Locat
                                                                                                                                                                                                                       ions
                                                                                                                                                                                                                       of
                                                                                                                                                                                                                       the
                                                                                                                                                                                                                       Lagun
                                                                                                                                                                                                                       a
                                                                                                                                                                                                                       Verde
                                                                                                                                                                                                                       Explo
                                                                                                                                                                                                                       ratio
                                                                                                                                                                                                                       n
                                                                                                                                                                                                                       Drill
                                                                                                                                                                                                                       holes

                                                                                                                                                                                                                       ·

                                                                                                                                                                                                                       Gener
                                                                                                                                                                                                                       alize
                                                                                                                                                                                                                       d
                                                                                                                                                                                                                       Strat
                                                                                                                                                                                                                       igrap
                                                                                                                                                                                                                       hic
                                                                                                                                                                                                                       Colum
                                                                                                                                                                                                                       n for
                                                                                                                                                                                                                       Lagun
                                                                                                                                                                                                                       a
                                                                                                                                                                                                                       Verde
                                                                                                                                                                                                                       Area
                                                                                                                                                                                                                       (base
                                                                                                                                                                                                                       d on
                                                                                                                                                                                                                       wells
                                                                                                                                                                                                                       LV01
                                                                                                                                                                                                                       to
                                                                                                                                                                                                                       LV06)
 Balanced reporting                                                             ·   Where comprehensive reporting of all Exploration Results is not              ·   Reported exploration results have not been filtered based on the
                                                                                practicable, representative reporting of both low and high grades and/or         exclusion of low or high grades. However, based on potential processing
                                                                                widths should be practiced to avoid                                              requirements and cost considerations, an average lithium grade for the packer

                                                                                brine samples is also presented with an assumed cut-off grade of 100 mg/L.
                                                                                misleading reporting of Exploration Results.
                                                                                                                                                                 ·   Pumping tests were conducted at wells LV05 and LV06.

                                                                                ·   Other exploration data, if meaningful and material, should be reported       ·   A 50 hp submergible electric pump, and piping with flowmeters were used

                                                                              including (but not limited to): geological observations; geophysical survey      for the pump tests. The tests consisted of a variable rate pumping to verify
 Other substantive exploration data                                             results; geochemical survey results; bulk samples - size and method of           the aquifer and pump capacity, as well as subsequently constant rate (48-hour
                                                                                treatment; metallurgical test results; bulk density, groundwater, geotechnical   to 7-day) pumping tests to obtain aquifer parameters and monitor observed
                                                                                and rock characteristics; potential deleterious or contaminating                 water levels and the extracted brine chemistry.

                                                                                substances.

                                                                                                                                                                 ·   In LV05, the pump was installed at 156 m and in LV06, at 150 m.
 Further work                                                                   ·   The nature and scale of planned further work (eg tests for lateral           ·    Exploration drilling and testing will continue in 2025. Areas of
                                                                                extensions or depth extensions or large-                                         additional exploration will include the western and northern/northeastern

   scale step-out drilling).                                                  portion of the current property concessions. A future long-term pumping and

                                                                          reinjection test is also planned in 2025.
   ·   Diagrams clearly highlighting the areas of possible extensions,
   including the main geological interpretations and future drilling areas,
   provided this information is not commercially sensitive.

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDEADFLEESLFAA

Recent news on Cleantech Lithium

See all news