BEIJING, March 9 (Reuters) - The world's first Westinghouse
AP1000 nuclear reactor will go into operation in June next year,
more than three years behind the original schedule, the head of
China's leading state nuclear project developer said.
"We are forecasting that if everything goes smoothly, the
first unit will go into operation in June 2017, and the second
unit at the end of 2017," said Sun Qin, the chairman of the
China National Nuclear Corporation, speaking to Reuters on the
sidelines of the annual session of parliament.
"Construction has been delayed three years. At first we
planned on December 2013 but there was just no way, with key
pieces of equipment not available," he said.
The "third-generation" reactor, designed by the U.S.-based
Westinghouse, has been plagued by delays brought about by design
flaws and problems with key components. Sun said new coolant
pumps for the two reactor units only arrived at the end of last
year.
Westinghouse is a unit of Japan's Toshiba Corp 6502.T .
A rival third-generation design, the European Pressurised
Reactor (EPR), has faced similar problems, with projects in
France, Finland and China all delayed.
But Sun said he was hopeful that China's own
third-generation model, known as the Hualong 1, will progress
more smoothly.
China's first Hualong 1 reactor unit, under construction at
Fuqing in southeast China's Fujian province, is expected to be
completed by around June 2016, he said.
China has also started construction on an identical Hualong
1 unit in Pakistan.
(Reporting by David Stanway and Kathy Chen; Editing by Richard
Pullin)