** Shares of Element 25 Ltd E25.AX fall as much as 10.6%
to A$1.05, post their steepest intraday pct drop since Nov. 10
** Mineral explorer says processing plant at its Butcherbird
Manganese Project in Western Australia experienced a logwasher
shaft failure on Nov. 18 urn:newsml:reuters.com:*:nASX2vM2FN
** Says it has temporarily shut the plant to solve the
problem
** Adds total production volumes will reduce to about 43,000
tonnes from expected 47,000 tonnes due to the outage
** Says there were no injuries or damage to other plant
components, and estimates full plant restart by mid-December
** Shares hit their lowest since Nov. 11
** As of last close, stock down 22.2% this year
(Reporting by Himanshi Akhand in Bengaluru)