Picture of Firering Strategic Minerals logo

FRG Firering Strategic Minerals News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsSpeculativeMicro CapSucker Stock

REG - Firering Strategic - Quicklime Project Update

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20240828:nRSb8515Ba&default-theme=true

RNS Number : 8515B  Firering Strategic Minerals PLC  28 August 2024

Firering Strategic Minerals plc / EPIC: FRG / Market: AIM / Sector: Mining

28 August 2024

Firering Strategic Minerals plc

("Firering" or "the Company")

 

Quicklime Operational Update

 

Rapidly advancing lime plant refurbishment

 

Firering Strategic Minerals plc, an emerging quicklime production and critical
mineral exploration company, is pleased to announce an operational update with
regards to its quicklime project in Zambia ("Limeco"), which is being
refurbished with the goal of commencing phased production during Q4 this year.

 

HIGHLIGHTS

Engineering work at quicklime plant advancing:

·    New kiln feed conveyor belt installed and commissioned.

·    New brakes installed at skip hoist motor.

·    Rebricking of damaged areas and repairing damaged bridges inside Kiln
1 completed.

·    Widening of the discharge end of Kiln 1 completed.

·    Foundation work for the first gasifier almost complete.

·    Excavation work for coal storage facility commenced.

·    First of two gasifiers on its way to Limeco; each gasifier supports 4
kilns.

·    Several dry runs completed successfully.

 

Crushing plant modifications fully operational:

·    Double roll crusher replaced with impact crusher.

·    Flow sheet partially optimised for efficient production of kiln
feedstock in the right size fraction.

·    Crushing of the correct quality limestone commenced to build a kiln
feed pile ahead of firing Kiln 1 in Q4 of 2024.

·    Waste stockpile renamed 'secondary stockpile' due to finding large
quantities of good material suitable for kiln feed.

 

On-site laboratory operational:

·    All new laboratory equipment arrived on site and installed.

·    Testwork focusing on calcium carbonate ("CaCO(3)") and quicklime
("CaO") content with high purity levels achieved.

·    Purity level specifications are required as part of ongoing
discussions with off-takers.

 

Yuval Cohen, Chief Executive of Firering and Limeco, said: "I am very pleased
with the progress being made at Limeco where engineers are rapidly completing
the modifications to the lime plant. Key to this plan has been the
manufacturing of the coal gasifier parts, which are now on their way to Limeco
having left the Port of Mundra, India, on 23 August 2024. Notably, work on the
gas ducting required to convey the hot gas from the gasifier to the kilns has
also started.

 

"Having replaced the double roll crusher with an impact crusher, the crushing
plant is performing well and being used to build a kiln feed pile of the right
quality limestone with a size fraction of -90mm to 60mm.  Undersize of -60mm
is guided back to the triple deck screen and split into three different
aggregate streams for sale to our customers.

 

"Major progress has also been made at Limeco's onsite laboratory with the
arrival of all outstanding test equipment. Accordingly, testwork to understand
the impact of the different limestone qualities and burning times on the
production of quicklime is in full swing with encouraging initial results
showing high available quicklime content.

 

"I look forward to further updating the market on the arrival of our first
gasifier and subsequent installation and commissioning of the system and the
firing of our first kiln using this new system during Q4 2024."

 

DETAILS

Lime plant

A new conveyor belt has been installed (Figure 1) that will feed crushed
limestone to the skip hoist, which transports the materials to a 25t hopper at
the top of the lime plant. From there, the limestone will be fed first to Kiln
1 and later, once operational, to Kiln 2.

 

Figure 1: View of newly installed conveyor belt (left) and feeding arrangement
into skip hoist (right).

Two new brakes for the skip hoist motor arrived on-site in early August 2024
and have since been installed (Figure 2), replacing the original single brake.
Brake testwork is planned for September 2024.

Figure 2: View of newly installed brakes for the skip hoist motor.

 

Repair work inside Kiln 1 has been completed including the repair of cracks,
burner port, the bridge and arches underneath the bridge. Additionally,
foundation work for the first gasifier is advancing (Figure 3) with the last
rebar reinforcement being installed and final concrete of 1050mm poured by the
first week of September 2024.

 

 

Figure 3: Preparation work at gasifier foundation ahead of final concrete
pour.

Excavation work for the coal storage facility that will hold the coal stock
that will be fed to the gasifier has commenced (Figure 4).

 

Figure 4: View of excavation work at coal storage facility.

 

Crushing plant

The new impact crusher arrived at Limeco in May and has been successfully
installed (Figure 5). The primary stockpile feed first goes through the
primary crusher before being processed by the impact crusher. The resulting
material is then directed to a double-deck screen, with -90mm to 60mm
fractions conveyed to the kiln feed pile (Figures 6 and 7), and undersized
material (-60mm) sent to a triple-deck screen for sorting into three aggregate
streams for Limeco's clients.

Figure 5: View of the newly installed impact crusher.

 

 

 

Figure 6: Belt feeding the -90mm to 60mm size fraction to the kiln feed pile.

 

Figure 7: View of the kiln feed stockpile.

 

The stockpile near the quarry, originally referred to as the waste stockpile,
was opened up for further examination to assess its contents. Observations
(Figure 8) and testwork on samples from this stockpile revealed that a large
portion comprises good quality limestone suitable for kiln feed. As a result,
the stockpile has been renamed 'secondary' stockpile with the 'primary'
stockpile located near the ramp leading to the jaw crusher.

 

 

Figure 8: View of good quality oversize on the 'secondary' stockpile and lime
plant.

 

Laboratory

Limeco's laboratory has received all outstanding equipment required to carry
out testwork and populate a database for its limestone qualities.  Figure 9
shows part of the laboratory equipment and the new oven that was recently
installed.

 

As part of ongoing discussions with off takers, purity level specifications
are required. Accordingly, Limeco's laboratory staff successfully produced the
first 10kg of quicklime, part of which will be sent to an external accredited
laboratory for independent analysis (Figure 10).

 

Figure 9: View of some of the lab equipment (left) and new oven (right).

 

 

Figure 10: Laboratory staff showing the first 10kg of quicklime produced at
the lab.

 

Issue of Equity

Application will be made to the London Stock Exchange for the admission of a
total of 454,545 ordinary shares of €0.001 each ("Ordinary Shares") issued
to an adviser at an issue price of 3.3 pence in settlement of fees for
services provided of £15,000 ("Admission"). It is expected that Admission
will become effective on or around 4 September 2024. Following Admission, the
Company's issued share capital will consist of 184,246,077 Ordinary Shares
which may be used by shareholders as the denominator for the calculations by
which to determine if they are required to notify their interest in, or a
change to their interest in, the Company under the FCA's Disclosure Guidance
and Transparency Rules.

 

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION AS STIPULATED UNDER THE UK
VERSION OF THE MARKET ABUSE REGULATION NO 596/2014 WHICH IS PART OF ENGLISH
LAW BY VIRTUE OF THE EUROPEAN (WITHDRAWAL) ACT 2018, AS AMENDED.  ON
PUBLICATION OF THIS ANNOUNCEMENT VIA A REGULATORY INFORMATION SERVICE, THIS
INFORMATION IS CONSIDERED TO BE IN THE PUBLIC DOMAIN.

 

*** ENDS ***

 

For further information visit www.fireringplc.com or contact:

 

 Firering Strategic Minerals                          E: info@firering-holdings.com

 Yuval Cohen
 SPARK Advisory Partners Limited (Nominated Adviser)  T: +44 20 3368 3550

 Neil Baldwin / James Keeshan / Adam Dawes
 Optiva Securities Limited (Joint Broker)             T: +44 20 3137 1903

 Christian Dennis / Daniel Ingram
 Shard Capital Partners LLP (Joint Broker)            T: +44 20 7186 9950

 Damon Heath / Erik Woolgar
 St Brides Partners Limited (Financial PR)            E: firering@stbridespartners.co.uk

 Isabel de Salis / Susie Geliher

Notes

Firering Strategic Minerals plc is an AIM-listed resource company set to
commence commissioning its significant quicklime project in Zambia in Q4 2024
to produce 600-800 tonnes of quicklime per day along with ancillary products.
With over US$100 million in historical investment, the project is
strategically positioned to support the expanding copper producers in the
Zambian Copper Belt, which are currently reliant on imported quicklime from
South Africa.  Firering currently holds an SPA over a 20.5% stake in Limeco
Resources Limited ("Limeco") with 10% already paid and an option to increase
this to 45%. Additionally, the Company is advancing the Atex Lithium-Tantalum
Project in northern Côte d'Ivoire, an exploration project rich in lithium and
tantalum-niobium, with drilling results indicating significant resource
potential in this established mining jurisdiction.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  UPDQKOBNDBKDOFB

Recent news on Firering Strategic Minerals

See all news