REG - Gem Diamonds Limited - Life of Mine Plan & Extended Credit Facilities

For best results when printing this announcement, please click on link below:
https://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20241203:nRSC5058Oa&default-theme=true

RNS Number : 5058O  Gem Diamonds Limited  03 December 2024

3 December 2024
 
 

 

GEM DIAMONDS LIMITED

Letšeng Life of Mine Plan and Extended Revolving Credit Facilities

Gem Diamonds Limited (LSE: GEMD) ("Gem Diamonds" or the "Company" or the
"Group") is pleased to announce a revised Life of Mine Plan for Letšeng and a
two-year extension to the Group's revolving credit facilities.

Letšeng's Revised Life of Mine Plan Summary:

·    Steeper slope design for the final open pit cutback of the Satellite
pit completed and approved.

·    High-wall structural and lateral support designs completed.

·    Significant reduction of Satellite Cut 6 West ("SC6W") ore to waste
stripping ratio from 1 : 6.9 to

1 : 2.1 (87.9 million tonnes to 21.5 million tonnes).

·    Significant reduction in future waste-stripping costs of c.US$180
million.

·    SC6W ore reduced from 12.8 million tonnes to 10.4 million tonnes.

Extended Group Revolving Credit Facilities

·    The Group's revolving credit facilities of US$71.7 million, due to
expire on 21 December 2024, have been extended for two years to 21 December
2026.

1.      Letšeng's Revised Life of Mine Plan

The Group is pleased to announce Letšeng's revised Life of Mine Plan
following Board approval of the new slope design of SC6W, the final open-pit
cutback in the Satellite pit.

 

Waste profile

SC6W has been under review since mid-2023 with the objective to safely and
responsibly reduce the required waste stripping under the existing pit slope
design. The revised pit slope design incorporates steeper slopes in the
competent basalt hard-rock (waste) sectors of the Satellite pit. Geotechnical
experts completed a steeper overall pit and inter-ramp slope stability
analysis which was used to design necessary lateral support and potential
rockfall mitigation measures. These measures include:

·      strategically placed catchment fences,

·      rockfall barriers,

·      wire-mesh draping,

·      improved blasting techniques and mechanical scaling, and

·      removal, bolting and/or anchoring of unstable rock wedges/key
blocks.

 

These measures will ensure the safe and responsible mining of steeper slopes
in the competent basalt hard-rock sectors of the Satellite pit.

 

The revised mine plan results in an overall reduction of 65.8 million tonnes
of waste stripping when compared to the existing mine plan. This will have a
significant reduction in future waste-stripping costs of c.US$180 million. The
investment in the implementation of the additional support measures has been
budgeted at US$15 million over the five-year waste-stripping period.

 

The final cutback in the Main pit (MC4W) is currently under review to assess
the viability of a similar steeper slope design in the hard-rock basalt, the
outcome of which is expected to be a reduced waste stripping ratio, which will
be announced upon completion.

 

Ore profile

The pit slope design in the kimberlite (ore) of SC6W remains at the current
slope angle design. The revised SC6W waste slope design has, however, resulted
in a reduction of 2.4 million tonnes of accessible ore when compared to the
current design. An opportunity to steepen the kimberlite slopes is being
assessed, which will allow access to additional ore with little to no further
waste stripping required.

 

The Life of Mine Plan in the Main pit has been updated to include inferred ore
which will be accessible within the existing pit design with little to no
further waste stripping required.

 

The table below details the change in waste and ore tonnes in SC6W in the
Satellite pit:

 

 Letšeng - Satellite SC6W Comparison
                   SC6W (Revised)  SC6W (Existing)  Variance
 Waste mined (Mt)  21.5            87.9             (66.4)
 Ore mined (Mt)    10.4            12.8             (2.4)
 Strip Ratio       1 : 2.1         1 : 6.9

 

The table below details the overall Life of Mine waste and ore tonnes for
Satellite and Main pits:

 

 Letšeng - Main and Satellite Life of Mine Plan Comparison*
                   Revised Plan  Existing Plan  Variance
 Waste mined (Mt)  71.1          136.9          (65.8)
 Main Pit          49.4          48.9           0.5
 Satellite Pit     21.7          88.0           (66.3)

 Ore mined (Mt)    79.4          71.0           8.4
 Main Pit          66.1          55.3           10.8
 Satellite Pit     13.3          15.7           (2.4)

 * Waste and ore mined include tonnes from 1 January 2024 for comparative
purposes.

 

More details on the Life of Mine Plan can be found on the Company's website at
www.gemdiamonds.com (http://www.gemdiamonds.com) .

 

2.    Extended Group Revolving Credit Facilities

The Group's revolving credit facilities comprising US$30.0 million at Gem
Diamonds Limited (US$6.0 million drawn as at 30 November 2024) and M750.0
million (US$41.7million) at Letšeng (no drawdown as at 30 November 2024) were
due to expire on 21 December 2024. The facilities have been extended for a
two-year period to 21 December 2026. The terms of the extended facilities
remain largely in line with the current facilities but with improved covenant
ratios. These facilities will be reviewed during 2026 with the intention to
renew the facilities for an appropriate period from December 2026.

 

The Company will host an investor update presentation via live audio webcast
today at 9:30 GMT. Please use the following link to register for the
presentation: https://gemdiamonds.zoom.us/webinar/register/
(https://gemdiamonds.zoom.us/webinar/register/WN_-QEOIt_hSBK6BweCO_UZtg) .

Company website: www.gemdiamonds.com (http://www.gemdiamonds.com)

The Gem Diamonds Limited LEI number is 213800RC2PGGMZQG8L67

FOR FURTHER INFORMATION:

 

Gem Diamonds Limited

Kiki Constantopoulos, Company Secretary

ir@gemdiamonds.com (mailto:ir@gemdiamonds.com)

 

Celicourt Communications

Mark Antelme / Felicity
Winkles

Tel: +44 (0) 20 770 6424

This announcement contains inside information for the purposes of Article 7 of
Regulation (EU) No 596/2014.

The Gem Diamonds Limited LEI number is 213800RC2PGGMZQG8L67.

ABOUT GEM DIAMONDS:

Gem Diamonds is a leading global producer of high value diamonds. The Company
owns 70% of the Letšeng mine in Lesotho. The Letšeng mine is famous for the
production of large, exceptional white

diamonds, making it the highest dollar per carat kimberlite diamond mine in
the world.

www.gemdiamonds.com (http://www.gemdiamonds.com)

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  STRBCBDDRUGDGSD

Recent news on Gem Diamonds

See all news