RNS Number : 3009T  Great Western Mining Corp. plc  14 November 2023

GREAT WESTERN MINING CORPORATION PLC

("Great Western", "GWM" or the "Company")

 

MILL SITE PROGRESS

& 121 MINING INVESTMENT FORUM

 

 

Great Western Mining Corporation PLC (AIM - GWMO, Euronext Growth - 8GW),
which is exploring and developing gold, silver and copper targets in Nevada,
provides the following update on its joint venture, Western Milling LLC
(Western Milling), which is currently constructing a process mill in Nevada
for recovery of precious metals from mining waste.

 

MILL SITE COMPLETION STATUS

 

Following delays outside the Company's control, including the difficulties of
securing concrete supplies in a remote location at a reasonable price and a
shortage of appropriately qualified personnel available in the area resulting
in a stop-go situation, now resolved, together with unusually severe weather
conditions in 2023, the mill project is nearing completion. Set out below is a
schedule of the progress on the main items.

 

·    Construction:  Gravity terraces, ramps, access road, lay down area
and containment are complete. Base for rod mill outstanding.

·    Process equipment:  Hydrocyclones, spirals and shaker tables are
being installed by a finishing team.  The Jaw crusher is waiting on parts but
timing is not critical as it will not be needed during the start-up stage.
The Rod Mill has been inspected but is currently offsite.  This 20-ton item
will be brought to site in the final stage pre-start up.

·    Safety Measures:  Safety barriers complete and safety procedures
established and written up in a manual in accordance with MSHA regulations.

·    Testing Laboratory:  A near site laboratory for testing materials
has been established and is now operational, providing for rapid analysis
during processing without reliance on external assay laboratories.

·    Utilities: A generator set-up will provide power for start of
operations.  Three-phase power line to be extended to site from nearby
infrastructure at a second stage.  Water rights are in the process of being
transferred and a well has now been drilled, achieving flow capability several
times in excess of requirements.  Four water monitoring wells have also been
drilled for ongoing verification that the water table is not affected by
operations. Water tanks have been installed.

·    Land Use:  A formal Surface Use Lease Agreement has been signed with
the joint venture partner for use of the mill site at a peppercorn rent and
registered with the county authorities.

·    Containment:  All steps considered necessary have been taken to
contain material within the site and prevent spillage in line with regulatory
requirements.   Double and triple containment has been constructed where
applicable in anticipation of the second phase of the project which will
involve chemical leaching.

·    Trucking of Material:  A 20 ton and a 40 ton truck, with drivers,
are on standby to bring raw material to site.  Initially these are being
rented but once the operation is up and running and the operating
practicalities have been assessed, the joint venture may exercise an option to
purchase one or the other or both.

·    Engineering Sign-off:  An independent consulting engineer has been
retained to inspect, verify and approve the project as-built prior to
production start-up.

 

PERMITTING STATUS

 

Once the project is ready to start operations, anticipated before the end of
the year, the timing of production start-up will depend on securing two
separate permits, application for both having been made and the approvals of
which are due and currently awaited.

 

1.    NDEP: Production start-up requires an environmental permit from NDEP
(The Nevada Department of Environmental Protection).  An application was
filed at the beginning of this year and the Company was advised that it would
be processed within six months.  Towards the end of the six-month period, the
joint venture was advised that there would be a delay of a further 2-3 months
due to staff shortages and work overload.  This further period has now
effectively elapsed and the Company has recently met with NDEP to determine if
there are any significant issues affecting the permit.  A response is awaited
but the Company is not so far aware of any outstanding issues beyond an
administrative backlog within NDEP.

2.    BLM:  A ground disturbance permit is required from the BLM (the
Federal Bureau of Land Management) to move mine waste from its current
locations to the mill site.  This is a standard permit, similar to those
routinely granted for drilling operations.  Again, there appears to be an
administrative backlog and, although no problems are anticipated, material
cannot be moved until the permit has been issued.

 

JOINT VENTURE AGREEMENT

 

Final documentation between the joint venture partners, including the Surface
Use Lease Agreement and a Bill of Sale for the inventory of equipment being
provided by the joint venture partner, has been signed and submission has been
made to the State of Nevada for formal registration of Great Western's 50%
shareholding in Western Milling LLC.

 

121 MINING INVESTMENT FORUM

 

Great Western is participating in The 121 Mining Investment Forum in London on
20-21 November and the Company's presentation will be published shortly before
the event.

 

 

Great Western Chairman Brian Hall commented:  "All the directors of Great
Western are shareholders in the Company and we share the frustration expressed
recently by a number of independent  shareholders over the delays that have
arisen in completing this project.  However, it should be noted that the
basic design has not changed since inception and the concept remains sound
with costs under control.  It should also be noted that, despite delays, the
project is likely to be achieved at a fraction of the cost of a green field
site using new plant and equipment, which was an earlier option considered by
the Company. The original and continuing objective of the mill is to generate
revenues for the Company from easily accessible mine waste, for which an
independent resource has been commissioned, and we expect to achieve this in
the near future.

 

"While generation of first revenues will be an exciting development for the
Company which will support operations, I want to point out that the main
driver for Great Western's growth is not the process mill but the enormous
upside potential of our large inventory of claims in the Walker Lane Belt of
Nevada, which we are working on fruitfully and moving to the next stage."

 

For further information:

 

 Great Western Mining Corporation PLC
 Brian Hall,                                                                                                              +44 207 933 8780
 Chairman
 Max Williams, Finance                                                                                                    +44 207 933 8780
 Director

 Davy (NOMAD, Euronext Growth Listing Sponsor & Joint Broker)

 Brian Garrahy                                                                                                            +353 1 679 6363

 SP Angel Corporate Finance LLP (Joint Broker)

 Ewan Leggat/Harry Davies-Ball                                                                                            +44 203 470 0470

 Walbrook PR (PR advisers)

 Nick                                                                                                                     +44 207 933 8783
 Rome

 

Notes to Editors

The Company has a large tract of acreage in Mineral County, Nevada. The area
consists of rugged, mountainous terrain, which means that large parts of it
remain under-explored. Mineral potential is hosted by the regional Walker Lane
Structural Belt, the largest structural and metallogenic belt in Nevada, yet
one of the least explored in recent times, with gold, silver and copper
currently produced in Mineral County.  Great Western has seven distinct
concession areas which offer the potential for exploiting (1) short term gold
and silver deposits and (2) long-term, world-class copper deposits.

 

Six of the Company's properties are in the west of Mineral County and are 100%
owned and operated.  The Company has an option to acquire a seventh property,
the Olympic Gold Project, in the east of the county.  Great Western's small
exploration team is supported by locally based consultants and contractors.

 

The state of Nevada is generally considered to be one of the world's most
mining friendly jurisdictions.  While tightly regulated and environmentally
conscious, Nevada welcomes the mining industry.  Great Western takes care to
ensure that its claims are maintained in good standing and all regulations
observed.

 

There are numerous gold and silver prospects on the Company's acreage,
including extensive historic mine workings which offer the opportunity for
secondary recovery. The Company is party to a 50-50 joint venture known as
Western Milling LLC which is constructing a mill to process pre-mined material
for secondary recovery of gold and silver.

 

Furthermore, through extensive drilling over a five-year period, GWM has
established a Mineral Resource on its first target area known as M2, of 4.3
million tonnes at 0.45% copper, for 19,000 tonnes of contained copper metal.
This resource has been independently reported in accordance with JORC
guidelines.

 

GWM has established an Inferred Resource Estimate of 31,000 tonnes grading 1.6
g/t gold and 3.0 g/t silver in tailings for the OMCO Mine at the Olympic Gold
Project.  It has also established Exploration targets.  In addition, the
Company has reported an Exploration Target as follows:

 

·    3,400 - 6,400 tonnes grading between 0.5 and 1.2 g/t Au and 1.2 and
2.1 g/t Ag in the substrate beneath the tailings volume at the Olympic Mine.

·    9,000 - 12,000 tonnes grading between 0.9 and 2.4 g/t Au and 2.0 and
5.1 g/t Ag in a coarse stockpile at Olympic Mine.

·    4,200 - 7,700 tonnes grading between 40 and 140 g/t Ag and 0.3 and
0.3 g/t Au in spoil heaps at Mineral Jackpot.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  MSCGPGCAGUPWGRW

Recent news on Great Western Mining

See all news