Aug 18 (Reuters) - Grupa Azoty SA ATTP.WA:
SAID ON THURSDAY ITS UNIT GRUPA AZOTY POLYOLEFINS HAS WITHDRAWN FROM POLIMERY POLICE PROJECT EPC AGREEMENT WITH HYUNDAI ENGINEERING (CONTRACTOR)
WITHDRAWAL DUE TO DELAYS IN RECEIPT OF KEY MILESTONES, FAILURE TO SUCCESSFULLY COMPLETE TEST RUNS ON TIME, REACHING THE LIMIT OF CONTRACTUAL PENALTIES CHARGED FOR DELAY AND FAILURE TO REACH AGREEMENT ON PARTIES' COUNTERCLAIMS
GRUPA AZOTY POLYOLEFINS DECIDED TO CHARGE CONTRACTOR WITH CONTRACTUAL PENALTIES OF EUR 111.8 MLN DUE TO AGREEMENT WITHDRAWAL