Picture of Hochschild Mining logo

HOC Hochschild Mining News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsSpeculativeMid CapHigh Flyer

REG - Hochschild MiningPLC - Q2 2022 Production Report

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20220720:nRST0448Ta&default-theme=true

RNS Number : 0448T  Hochschild Mining PLC  20 July 2022

 

 

 

 

 

_____________________________________________________________________________________

20 July 2022

 

Production and Project Development Report for the 6 months ended 30 June 2022

 

 

Hochschild Mining PLC ("Hochschild" or "the Company") (LSE: HOC) (OTCQX:
HCHDF) is pleased to announce its production report for H1 2022 and an update
on its project portfolio.

 

Ignacio Bustamante, Chief Executive Officer said:

"Following a strong second quarter, we remain on track to meet our full year
production and cost forecasts. Furthermore, this has been achieved despite
operational issues at Pallancata and San Jose and in an environment of
considerable economic challenges. We have also made good progress at our two
development projects in Brazil and Canada as well as our 2022 brownfield
drilling programme."

 

Operational highlights

§ Q2 2022 attributable production:(( 1 ))

o  49,133 ounces of gold

o  2.6 million ounces of silver

o  85,819 gold equivalent ounces

o  6.2 million silver equivalent ounces

§ H1 2022 attributable production

o  96,360 ounces of gold

o  5.1 million ounces of silver

o  166,708 gold equivalent ounces

o  12.0 million silver equivalent ounces

§ On track to deliver overall 2022 production target of 360,000-375,000 gold
equivalent ounces (26.0-27.0 million silver equivalent ounces)

§ 2022 all-in sustaining costs on track to meet guidance of $1,330-1,370 per
gold equivalent ounce ($18.5-19.0 per silver equivalent ounce)

Project & Exploration highlights

§ Mara Rosa project in Brazil advancing on schedule - total project progress
at the end of June was 7% with key final permit expected in Q3

§ Drilling commenced at Snip with encouraging results - pre-feasibility study
to be completed by end of 2022

§ Pallancata medium-term drill programme delivering positive results -
continuing to test short-term targets

ESG highlights

§ Lost Time Injury Frequency Rate of 1.28 (FY 2021: 1.26)(( 2 ))

§ Accident Severity Index of 72 (FY 2021: 676)(( 3 ))

§ Water Consumption of 175lt/person/day (FY 2021: 193lt/person/day)

§ Domestic waste generation of 1.01 kg/person/day (FY 2021:
1.00kg/person/day)

§ ECO score of 5.35 out of 6 (FY 2021: 5.29)(( 4 ))

Strong financial position

§ Total cash of approximately $205 million as at 30 June 2022 following
completion of the Amarillo acquisition ($387 million as at 31 December 2021)

§ Net debt of approximately $106 million as at 30 June 2022 (net cash of $86
million as at 31 December 2021)

§ Current Net Debt/LTM EBITDA of approximately 0.34x as at 30 June 2022

________________________________________________________________________________________

 

A conference call will be held at 2.30pm (London time) on Wednesday 20 July
2022 for analysts and investors.

Dial in details as follows:

International Dial in: +44 330 165 4012

UK Toll-Free Number: 0800 279 6877

US/Canada Toll Free: 800-289-0720

Pin: 1215129

Please dial into the call approximately ten minutes before the 2.30pm start
time.

A recording of the conference call will be available on demand on the
Company's website: www.hochschildmining.com (http://www.hochschildmining.com)

________________________________________________________________________________________

 

Overview

In Q2 2022, Hochschild delivered attributable production of 85,819 gold
equivalent ounces or 6.2 million silver equivalent ounces with a solid
performance from Inmaculada and an increase at San Jose versus the first
quarter. In the first half of 2022 as a whole, Hochschild produced 166,708
gold equivalent ounces or 12.0 million silver equivalent ounces (on an
attributable basis) with production increasing quarter-on-quarter. The Company
remains on track to meet its overall attributable production target for 2022
of 360,000-375,000 gold equivalent ounces or 26.0-27.0 million silver
equivalent ounces.

 

The Company reiterates that its all-in sustaining cost for 2022 is on track to
be in line with the guidance of between $1,330 and $1,370 per gold equivalent
ounce (or $18.5 and $19.0 per silver equivalent ounce).

 

TOTAL GROUP PRODUCTION

                                Q2 2022  Q1 2022  Q2 2021  H1 2022  H1 2021
 Silver production (koz)        3,346    2,759    3,700    6,105    7,021
 Gold production (koz)          60.27    53.68    62.76    113.94   125.07
 Total silver equivalent (koz)  7,685    6,624    8,219    14,309   16,027
 Total gold equivalent (koz)    106.74   92.00    114.15   198.74   222.59
 Silver sold (koz)              3,445    2,600    3,823    6,045    7,005
 Gold sold (koz)                63.06    49.64    63.18    112.70   124.32

Total production includes 100% of all production, including production
attributable to Hochschild's joint venture partner at San Jose.

 

ATTRIBUTABLE GROUP PRODUCTION

                          Q2 2022  Q1 2022  Q2 2021  H1 2022  H1 2021
 Silver production (koz)  2,641    2,424    3,093    5,065    5,922
 Gold production (koz)    49.13    47.23    53.42    96.36    106.26
 Silver equivalent (koz)  6,179    5,824    6,939    12,003   13,573
 Gold equivalent (koz)    85.82    80.89    96.37    166.71   188.51

Attributable production includes 100% of all production from Inmaculada,
Pallancata and 51% from San Jose.

 

Production

Inmaculada

 Product                          Q2 2022                   Q1 2022                   Q2 2021  H1 2022  H1 2021
 Ore production (tonnes treated)  327,837                   329,364                   334,657  657,202  672,137
 Average grade silver (g/t)       137                       153                       163      145      160
 Average grade gold (g/t)         3.47                      3.75                      3.92     3.61     3.92
 Silver produced (koz)                      1,322           1,493                     1,358    2,815    2,777
 Gold produced (koz)                      34.86                       37.81           39.60    72.67    79.40
 Silver equivalent (koz)          3,831                     4,216                     4,209    8,047    8,494
 Gold equivalent (koz)            53.21                     58.55                     58.46    111.77   117.98
 Silver sold (koz)                1,422                     1,383                     1,355    2,805    2,769
 Gold sold (koz)                  37.56                     35.16                     39.85    72.72    79.49

 

Inmaculada's second quarter production was 34,855 ounces of gold and 1.3
million ounces of silver which amounts to a gold equivalent output of 53,214
ounces. Grades were lower than expected due to a temporary mine plan schedule
partially offset by higher than budgeted recoveries. Overall, in the first
half of 2022, Inmaculada produced 111,766 gold equivalent ounces (H1 2021:
117,975 ounces), driven by better-than-expected recoveries.

 

The Company is currently in the final stages of the permitting process of
Inmaculada's modified Environmental Impact Assessment with completion expected
during H2.

 

Pallancata

 Product                          Q2 2022                       Q1 2022                       Q2 2021                 H1 2022  H1 2021
 Ore production (tonnes treated)  134,276                       124,782                       162,052                 259,058  289,002
 Average grade silver (g/t)                    154                           165              234                     159      237
 Average grade gold (g/t)         0.69                          0.74                          0.86                    0.72     0.86
 Silver produced (koz)            586                           581                           1,103                   1,167    2,000
 Gold produced (koz)              2.69                          2.70                          4.09                    5.39     7.28
 Silver equivalent (koz)                      780                            776                       1,398          1,555    2,524
 Gold equivalent (koz)                     10.83                          10.77                        19.42          21.60    35.06
 Silver sold (koz)                584                           577                           1,229                   1,161    2,000
 Gold sold (koz)                  2.66                          2.69                          4.56                    5.36     7.29

 

In the second quarter, Pallancata produced 0.6 million ounces of silver and
2,692 ounces of gold bringing the silver equivalent total to 0.8 million
ounces. Overall, in H1 2022, Pallancata's output was 1.6 million silver
equivalent ounces (H1 2021: 2.5 million ounces). Grades have been lower than
expected throughout the first half and consequently, with the rapid fall in
the silver price in the period, the Company has updated the mine plan for 2022
and is considering all options with regards to future ore production from the
Pallancata mining area.

 

San Jose (the Company has a 51% interest in San Jose)

 Product                          Q2 2022               Q1 2022                 Q2 2021                   H1 2022  H1 2021
 Ore production (tonnes treated)  131,467               73,892                  144,849                   205,359  246,194
 Average grade silver (g/t)       383                   331                     304                       365      321
 Average grade gold (g/t)         6.09                  6.36                    4.69                      6.19     5.45
 Silver produced (koz)            1,438                 685                     1,239                     2,123    2,244
 Gold produced (koz)              22.72                 13.16                   19.07                     35.88    38.40
 Silver equivalent (koz)                  3,074                  1,632                    2,612           4,706    5,008
 Gold equivalent (koz)                    42.69                  22.67          36.27                     65.37    69.56
 Silver sold (koz)                1,440                 640                     1,239                     2,080    2,236
 Gold sold (koz)                  22.83                 11.79                   18.77                     34.62    37.54

 

Q2 production at San Jose was 1.4 million ounces of silver and 22,718 ounces
of gold which is 3.0 million silver equivalent ounces and brings the total for
the first half of the year to 4.7 million silver equivalent ounces (H1 2021:
5.0 million ounces). Gold grades were better than expected in the quarter
although this was offset by lower-than-expected tonnage.

 

As previously reported, in the first quarter the operation experienced further
Covid-related restrictions on labour availability in the country. In addition,
a fire in the crushing area temporarily affected operations but without any
impact on full year production forecasts or costs (which are expected to be
covered by insurance).

 

Average realisable prices and sales

Average realisable precious metal prices in Q2 2022 (which are reported before
the deduction of commercial discounts) were $1,843/ounce for gold and
$22.0/ounce for silver (Q2 2021: $1,838/ounce for gold and $27.9/ounce for
silver). For H1 2022, average realisable precious metal prices were
$1,875/ounce for gold and $23.7/ounce for silver (H1 2021: $1,772/ounce for
gold and $26.3/ounce for silver).

 

Advanced Project: Mara Rosa

The Mara Rosa project in Brazil is progressing according to schedule with the
following key highlights:

§ Total project progress at the end of June 2022 was 7%

§ Detailed engineering 71% complete

§ Long lead-time equipment (e.g. ball mills and filters) have been purchased

§ Metso 3-stage crusher being delivered to site

§ EPCM, earthworks, diesel, and mining pre-stripping contracts being
progressed

§ Acquisition of site substation, transformers and water and sewage treatment
facilities completed

§ Construction powerline completed with project powerline construction
ongoing

§ Topsoil removal commenced in areas with no vegetation - approximately 30%
of project area

 

Development Project: Snip

Approximately 7,300m were drilled from underground in Q2, with all "twin"
holes completed by the end of the quarter. Work in the third quarter will be
focused on finishing the "infill" and" potential" holes in the programme and
logging the resultant core. Assay results are expected through to the end of
the year.

 

Work on the Pre-Feasibility Study continued with metallurgical test work, an
evaluation of ARD potential in waste samples, and a flowsheet trade-off study
all completed during the quarter. Processing plant designs and an updated
resources model are expected to be finalised in Q3. The full study remains on
track for completion at the end of the year. In addition, a new 2-year
Environmental Baseline program was approved and data collection began.

 

Assay results were received during the period, with the following highlights:

 

 Vein  Results (Twin hole)
 215   UG22-297: 2.3m @ 9.5g/t Au & 11g/t Ag
 215   UG22-289: 8.0m @ 20.2g/t Au & 10g/t Ag
 221   UG22-291: 3.8m @ 11.8g/t Au & 13g/t Ag
 226   UG22-289: 8.7m @ 5.8g/t Au & 6g/t Ag
 233   UG22-297: 4.6m @ 35.0g/t Au & 11g/t Ag
 246   UG22-293: 2.3m @ 18.8g/t Au & 8g/t Ag

 

Development Project: Volcan

During the second quarter, the Company's 100% owned subsidiary, Tiernan Gold
Corporation continued to advance the Volcan project. Work carried out during
the period included updating the Mineral Resource Estimate as well as
developing an optimised mine and project development plan.  During the third
quarter, the Company expects to advance several trade-off studies aimed at
creating additional project value. The results of the engineering work are
expected to be outlined in a new technical report.

 

Brownfield exploration

Inmaculada

In Q2 2022, 4,200m of drilling was carried out with the best result below from
the Josefa vein:

 

 Vein    Results (potential/resource drilling)
 Josefa  IMM22-139: 2.8m @ 1.9g/t Au & 43g/t Ag

 

During Q3, the plan is to carry out 6,000m of further drilling in the Josefa
vein.

 

Pallancata

At Pallancata, 12,500m of resource drilling was executed in the Laura-Demian,
Royropata and Miriam structures. Whilst the results are encouraging, the
structures are outside the current permitted area and will require new permits
before being brought into the mine plan. Quartz-sulfide veins were intercepted
with grades of between 250 and 1,600 silver equivalent grams per tonne.
Selected results are below:

 

 Vein         Results (resource drilling)
 Miriam       DHMIR-A16: 1.3m @ 1.0g/t Au & 155g/t Ag
 Demian       DLDE-A03: 3.8m @ 0.8g/t Au & 184g/t Ag

              DLRY-A08: 1.1m @ 4.1g/t Au & 820g/t Ag
 Laura        DLDE-A04: 6.1m @ 0.8g/t Au & 251g/t Ag

              DLLAU-A08: 1.3m @ 0.5g/t Au & 274g/t Ag

              DLLAU-A09: 0.9m @ 4.7g/t Au & 286g/t Ag

              DLLAU-A11: 1.9m @ 0.9g/t Au & 298g/t Ag
 Royropata    DLDE-A06: 4.2m @ 0.6g/t Au & 224g/t Ag

              DLRY-A08: 1.5m @ 1.1g/t Au & 345g/t Ag
 Royropata 2  DLDE-A06: 1.3m @ 3.0g/t Au & 1,039g/t Ag

              DLRY-A08: 3.0m @ 1.8g/t Au & 596g/t Ag
 Royropata 4  DLDE-A06: 17.8m @ 1.2g/t Au & 384g/t Ag

              DLRY-A08: 5.1m @ 2.3g/t Au & 647g/t Ag
 Royropata 5  DLDE-A06: 2.3m @ 3.0g/t Au & 1,446g/t Ag

 

During Q3, there will be 2,000m of further drilling in the vein structures in
the Royropata system.

 

San Jose

At San Jose, 3,600m of potential drilling was carried out close to current
operations and 700m of drilling was also executed at the Ciclon project.
Selected results below:

 

 Vein       Results (potential/resource)
 Agostina   SJD-2468: 4.1m @ 7.5g/t Au & 84g/t Ag

            SJD-2469: 5.4m @ 3.3g/t Au & 29g/t Ag

            SJD-2471: 1.9m @ 1.6g/t Au & 68g/t Ag
 Ayelen SE  SJM-594: 1.5m @ 6.9g/t Au & 648g/t Ag
 Ciclon     DCE22-02: 2.9m @ 1.0g/t Au & 615g/t Ag

 

During Q3, 2,000m of potential drilling will be carried out on the Ayelen SE
vein to find new resources.

 

Financial position

Total cash was approximately $205 million as at 30 June 2022 resulting in a
net debt position of approximately $106 million.

_____________________________________________________________________________________

 

Enquiries:

 

Hochschild Mining PLC

Charles Gordon
 
                                  +44 (0)20
3709 3264

Head of Investor Relations

 

Hudson Sandler

Charlie Jack
                                  +44 (0)207 796 4133

Public Relations

________________________________________________________________________________________

 

About Hochschild Mining PLC

Hochschild Mining PLC is a leading precious metals company listed on the
London Stock Exchange (HOCM.L / HOC LN) and crosstrades on the OTCQX Best
Market in the U.S. (HCHDF), with a primary focus on the exploration, mining,
processing and sale of silver and gold. Hochschild has over fifty years'
experience in the mining of precious metal epithermal vein deposits and
currently operates three underground epithermal vein mines, two located in
southern Peru and one in southern Argentina. Hochschild also owns the Mara
Rosa Advanced Project in Brazil as well as numerous long-term projects
throughout the Americas
________________________________________________________________________________________

 

Forward looking statements

This announcement may contain forward looking statements. By their nature,
forward looking statements involve risks and uncertainties because they relate
to events and depend on circumstances that will or may occur in the future.
Actual results, performance or achievements of Hochschild Mining PLC may, for
various reasons, be materially different from any future results, performance
or achievements expressed or implied by such forward looking statements.

 

The forward looking statements reflect knowledge and information available at
the date of preparation of this announcement. Except as required by the
Listing Rules and applicable law, the Board of Hochschild Mining PLC does not
undertake any obligation to update or change any forward looking statements to
reflect events occurring after the date of this announcement. Nothing in this
announcement should be construed as a profit forecast.

 

Note

The information contained within this announcement is deemed by the Company to
constitute inside information as stipulated under the Market Abuse Regulation
(Regulation (EU) No.596/2014). Upon the publication of this announcement via a
Regulatory Information Service, this inside information is now considered to
be in the public domain.

 

LEI: 549300JK10TVQ3CCJQ89

- ends -

 1 All equivalent figures assume the average gold/silver ratio for 2021 of
72x.

 2 Calculated as total number of accidents per million labour hours

(( 3 ))Calculated as total number of days lost per million labour hours.

 4 The ECO Score is an internally designed Key Performance Indicator measuring
environmental performance in one number and encompassing numerous fronts
including management of waste water, outcome of regulatory inspections and
sound environmental practices relating to water consumption and the recycling
of materials.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  DRLKKLFFLDLLBBV

Recent news on Hochschild Mining

See all news