Picture of Hochschild Mining logo

HOC Hochschild Mining News Story

0.000.00%
gb flag iconLast trade - 00:00
Basic MaterialsSpeculativeMid CapHigh Flyer

REG - Hochschild MiningPLC - Q2 2023 Production Report

For best results when printing this announcement, please click on link below:
http://newsfile.refinitiv.com/getnewsfile/v1/story?guid=urn:newsml:reuters.com:20230725:nRSY0254Ha&default-theme=true

RNS Number : 0254H  Hochschild Mining PLC  25 July 2023

 

 

 

 

 

_____________________________________________________________________________________

25 July 2023

 

Production Report for the 6 months ended 30 June 2023

 

Hochschild Mining PLC ("Hochschild" or "the Company") (LSE: HOC) (OTCQX:
HCHDF) is pleased to announce its production report for H1 2023.

 

Ignacio Bustamante, Chief Executive Officer said:

"After a stronger second quarter, we are looking forward to production
increasing throughout the remainder of 2023. With regards to Inmaculada's
Modified Environmental Impact Assessment, we are continuing to work with
SENACE on its final review, and therefore will update our production and cost
guidance for 2023 following completion of the process. Finally, we are pleased
that further promising progress has been made at our Mara Rosa development
project in Brazil and that we remain on track for first production early in
2024."

 

Operational highlights

§ Q2 2023 attributable production:(( 1 ))

o  43,622 ounces of gold

o  2.4 million ounces of silver

o  72,364 gold equivalent ounces

o  6.0 million silver equivalent ounces

§ H1 2023 attributable production

o  83,357 ounces of gold

o  4.4 million ounces of silver

o  136,878 gold equivalent ounces

o  11.4 million silver equivalent ounces

Project highlights

§ Mara Rosa project in Brazil advancing on schedule and on budget - total
project progress at 88% with first production on track for H1 2024

§ H2 2023 Brownfield programme expected to commence subject to receipt of
Inmaculada's MEIA

ESG highlights

§ Lost Time Injury Frequency Rate of 0.84 (FY 2022: 1.37)(( 2 ))

§ Accident Severity Index of 32 (FY 2022: 93)(( 3 ))

§ Water Consumption of 168lt/person/day (FY 2022: 171lt/person/day)

§ Domestic waste generation of 0.95 kg/person/day (FY 2022:
1.05kg/person/day)

§ ECO score of 5.89 out of 6 (FY 2022: 5.27)(( 4 ))

Financial position

§ Total cash of approximately $94 million as at 30 June 2023 ($103 million as
at 31 March 2023)

§ Net debt of approximately $227 million as at 30 June 2023 ($218 million as
at 31 March 2023)

§ Current Net Debt/LTM EBITDA of approximately 1.04x as at 30 June 2023

§ Additional gold hedges executed in Q2 in Brazil:

o  50,000oz of gold hedged for 2025 at $2,117 per ounce

o  50,000oz of gold hedged for 2026 at $2,167 per ounce

o  50,000oz of gold hedged for 2027 at $2,206 per ounce

________________________________________________________________________________________

 

A conference call will be held at 2.30pm (London time) on Tuesday 25 July 2023
for analysts and investors.

Dial in details as follows:

International Dial in: +44 330 551 0200

UK Toll-Free Number: 0808 109 0700

US/Canada Toll Free: 866-580-3963

Password: Hochschild - Q2 2023

Please dial into the call approximately ten minutes before the 2.30pm start
time.

A recording of the conference call will be available on demand on the
Company's website:

________________________________________________________________________________________

 

Overview

In Q2 2023, Hochschild delivered attributable production of 72,364 gold
equivalent ounces or 6.0 million silver equivalent ounces with Inmaculada
temporarily impacted by the ongoing delay in the decision on the MEIA
affecting mine development, as expected. However, this was partially offset by
increases versus the first quarter at San Jose and Pallancata. In the first
half of 2023 as a whole, Hochschild produced 136,878 gold equivalent ounces or
12.4 million silver equivalent ounces (on an attributable basis).

 

TOTAL GROUP PRODUCTION

                                Q2 2023  Q1 2023  Q2 2022  H1 2023  H1 2022
 Silver production (koz)        2,955    2,438    3,346    5,393    6,105
 Gold production (koz)          54.12    46.44    60.27    100.55   113.94
 Total silver equivalent (koz)  7,447    6,292    8,348    13,739   15,562
 Total gold equivalent (koz)    89.72    75.81    100.58   165.53   187.50
 Silver sold (koz)              3,011    2,414    3,445    5,425    6,045
 Gold sold (koz)                55.29    44.50    63.06    99.79    112.70

Total production includes 100% of all production, including production
attributable to Hochschild's joint venture partner at San Jose.

 

ATTRIBUTABLE GROUP PRODUCTION

                          Q2 2023  Q1 2023  Q2 2022  H1 2023  H1 2022
 Silver production (koz)  2,386    2,057    2,641    4,442    5,065
 Gold production (koz)    43.62    39.73    49.13    83.36    96.36
 Silver equivalent (koz)  6,006    5,355    6,719    11,361   13,063
 Gold equivalent (koz)    72.36    64.51    80.96    136.88   157.38

Attributable production includes 100% of all production from Inmaculada,
Pallancata and 51% from San Jose.

 

Production

Inmaculada

 Product                          Q2 2023               Q1 2023                   Q2 2022                   H1 2023  H1 2022
 Ore production (tonnes treated)  257,768               278,138                   327,837                   535,905  657,202
 Average grade silver (g/t)       181                   176                       137                       178      145
 Average grade gold (g/t)         3.92                  3.78                      3.47                      3.85     3.61
 Silver produced (koz)                    1,300         1,274                               1,322           2,573    2,815
 Gold produced (koz)                      30.64                   31.21                   34.86             61.85    72.67
 Silver equivalent (koz)          3,843                 3,864                     4,215                     7,707    8,846
 Gold equivalent (koz)            46.30                 46.56                     50.78                     92.86    106.58
 Silver sold (koz)                1,357                 1,204                     1,422                     2,561    2,805
 Gold sold (koz)                  32.10                 29.29                     37.56                     61.39    72.72

 

Inmaculada's second quarter production was 30,639 ounces of gold and 1.3
million ounces of silver which amounts to a gold equivalent output of 46,297
ounces. Tonnage was lower than the previous quarter, as expected, due to the
ongoing delays in the decision on the MEIA impacting mine development although
this was offset by higher grades. Overall, in the first half of 2023,
Inmaculada produced 92,856 gold equivalent ounces (H1 2022: 106,584 ounces).

 

Hochschild continues to work with SENACE, Peru's National Service of
Environmental Certification for Sustainable Investments, to complete the final
review of Inmaculada's Modified Environment Impact Assessment.

 

Pallancata

 Product                          Q2 2023                       Q1 2023                       Q2 2022                       H1 2023  H1 2022
 Ore production (tonnes treated)  123,782                       115,842                       134,276                       239,624  259,058
 Average grade silver (g/t)                    147                           126                           154              137      159
 Average grade gold (g/t)         0.60                          0.49                          0.69                          0.55     0.72
 Silver produced (koz)            493                           386                           586                           879      1,167
 Gold produced (koz)              2.06                          1.55                          2.69                          3.61     5.39
 Silver equivalent (koz)                      664                            514              809                           1,179    1,615
 Gold equivalent (koz)                      8.00                           6.20                        9.75                 14.20    19.46
 Silver sold (koz)                497                           427                           584                           923      1,161
 Gold sold (koz)                  2.06                          1.69                          2.66                          3.75     5.36

 

In the second quarter, Pallancata produced 0.5 million ounces of silver and
2,062 ounces of gold bringing the silver equivalent total to 0.7 million
ounces, an increase versus the first quarter. Overall, in H1 2023,
Pallancata's output was 1.2 million silver equivalent ounces (H1 2022: 1.6
million ounces). Reduced tonnage and grades versus H1 2022 are in line with
the current declining production profile.

 

San Jose (the Company has a 51% interest in San Jose)

 Product                          Q2 2023                 Q1 2023                   Q2 2022               H1 2023  H1 2022
 Ore production (tonnes treated)  143,563                 128,499                   131,467               272,063  205,359
 Average grade silver (g/t)       288                     215                       383                   254      365
 Average grade gold (g/t)         5.40                    3.88                      6.09                  4.68     6.19
 Silver produced (koz)            1,163                   778                       1,438                 1,941    2,123
 Gold produced (koz)              21.42                   13.68                     22.72                 35.09    35.88
 Silver equivalent (koz)                  2,940                     1,913                   3,324         4,854    5,101
 Gold equivalent (koz)                     35.42                  23.05                     40.05         58.48    61.46
 Silver sold (koz)                1,157                   784                       1,440                 1,941    2,080
 Gold sold (koz)                  21.14                   13.52                     22.83                 34.66    34.62

 

Q2 production at San Jose was 1.2 million ounces of silver and 21,416 ounces
of gold which is 2.9 million silver equivalent ounces with grades improving
from the first quarter when mine sequencing and annual holidays impacted
production. This brings the total for the first half of the year to 4.9
million silver equivalent ounces (H1 2022: 5.1 million ounces).

 

Average realisable prices and sales

Average realisable precious metal prices in Q2 2023 (which are reported before
the deduction of commercial discounts) were $1,958/ounce for gold and
$23.4/ounce for silver (Q2 2022: $1,843/ounce for gold and $22.0/ounce for
silver). For H1 2023, average realisable precious metal prices were
$1,957/ounce for gold and $23.3/ounce for silver (H1 2022: $1,875/ounce for
gold and $23.7/ounce for silver).

 

Advanced Project: Mara Rosa

The Mara Rosa project is progressing according to schedule and budget with
total project progress now standing at 88% and with the Company continuing to
expect first production in H1 2024.

 

Procurement

Currently purchase orders have been issued for 97% of the project equipment.
Deliveries are on schedule with key equipment received including the crusher,
belt conveyors, the secondary substation, electrocentres, filters, HDPE
piping, aluminium cables for the transmission lines, hydrocyclones, agitators,
wastewater treatment station, thickeners and the ball mills. In addition, the
drilling service contract was signed during the period and the contractor is
already mobilised.

 

Mine and Pre-Stripping:

The pre-stripping contractor has begun blasting work and 365kt of ore has
already moved according to schedule. The target is to guarantee a stockpile
for use during the plant ramp-up period. Construction of the waste dumps and
ore stockpiles are also underway.

 

Civil works

Civil works in the processing plant area have advanced in line with schedule
and are mostly complete which allowed electromechanical assembly to start on
time. Assembly work is advancing slightly ahead of schedule on the crushing,
screening and belt conveyor areas with commissioning on this circuit expected
towards the end of Q3. The grinding area is also advancing well (84%
completion), and mechanical completion is expected to finish in the quarter,
whilst the thickening and leaching areas are expected to have mechanical
completion in Q4.

 

Infrastructure assembly

The Electromechanical assembly contractor has been mobilised, and the work is
advancing in line with schedule at 42% progress. The power supply for the mine
is being provided by the building of a 67km, 138kv transmission line from the
Porangatu substation with work currently 97% advanced and expected to be
completed very shortly.

 

Earthworks

The water reservoir is fully operational and already at 95% of storage
capacity with water from the pit area whilst dry stacking construction started
during the quarter and is expected to finish in the fourth quarter.

 

Permitting

Preparations are underway for the operational license from local authorities
whilst the license for the crusher/screening circuit (dry circuit) has already
been submitted and it is expected to be received in the third quarter. The
remaining licenses for the processing plant (wet circuit) are expected to be
submitted in this quarter whilst the operational permit for the transmission
line was submitted last month and is expected in September.

 

Sustainability

Environmental controls to monitor construction work have been implemented to
ensure compliance with applicable permits. ESG programmes are advancing as
expected with almost 900 people having visited the "knowledge trail" as of
June 2023. On 5 June, the trail received the "Goiás Sustainability Award" in
the Innovation, Science and Education category.

 

During May, the project hosted over 70 stakeholders including local mayors,
politicians and community members, who inspected the site progress and gave
some very positive feedback. Also in May, the team helped to promote "Traffic
Week" involving 2,600 people from schools in Mara Rosa as well as on the main
street in Mara Rosa itself. Monthly newsletters covering project progress and
sustainability initiatives are continuing to be distributed to local
communities.

 

Health and Safety

Hochschild's health and safety corporate standards have been implemented at
the project, including the introduction of the Company's Seguscore safety
indicator. The project has recently surpassed three million injury-free
working hours and year-to-date Frequency and Severity Indexes are currently at
zero.

 

Brownfield exploration

Although the brownfield team is planning a busy half of drilling, the budget
for the exploration programme in Peru is subject to the Inmaculada MEIA
approval.

 

Financial position

Total cash was approximately $94 million as at 30 June 2023 resulting in a net
debt position of approximately $227 million.

 

During the quarter, the Company executed several precious metal hedges for
production from Brazil

o  50,000oz of gold hedged for 2025 at $2,117 per ounce

o  50,000oz of gold hedged for 2026 at $2,167 per ounce

o  50,000oz of gold hedged for 2027 at $2,206 per ounce

 

These were in addition to the previous announced hedges:

o  29,250 ounces of gold hedged for the remainder of 2023 at $2,047 per ounce
in Peru

o  27,600 ounces of gold hedged between March and December 2024 at $2,100 per
ounce in Brazil

 

_____________________________________________________________________________________

 

Enquiries:

 

Hochschild Mining PLC

Charles Gordon
                                 +44 (0)20 3709 3264

Head of Investor Relations

 

Hudson Sandler

Charlie Jack
                                    +44 (0)207 796 4133

Public Relations

________________________________________________________________________________________

 

About Hochschild Mining PLC

Hochschild Mining PLC is a leading precious metals company listed on the
London Stock Exchange (HOCM.L / HOC LN) and crosstrades on the OTCQX Best
Market in the U.S. (HCHDF), with a primary focus on the exploration, mining,
processing and sale of silver and gold. Hochschild has over fifty years'
experience in the mining of precious metal epithermal vein deposits and
currently operates three underground epithermal vein mines, two located in
southern Peru and one in southern Argentina. Hochschild also owns the Mara
Rosa Advanced Project in Brazil as well as numerous long-term projects
throughout the Americas
________________________________________________________________________________________

 

Forward looking statements

This announcement may contain forward looking statements. By their nature,
forward looking statements involve risks and uncertainties because they relate
to events and depend on circumstances that will or may occur in the future.
Actual results, performance or achievements of Hochschild Mining PLC may, for
various reasons, be materially different from any future results, performance
or achievements expressed or implied by such forward looking statements.

 

The forward looking statements reflect knowledge and information available at
the date of preparation of this announcement. Except as required by the
Listing Rules and applicable law, the Board of Hochschild Mining PLC does not
undertake any obligation to update or change any forward looking statements to
reflect events occurring after the date of this announcement. Nothing in this
announcement should be construed as a profit forecast.

 

Note

The information contained within this announcement is deemed by the Company to
constitute inside information as stipulated under the Market Abuse Regulation
(Regulation (EU) No.596/2014). Upon the publication of this announcement via a
Regulatory Information Service, this inside information is now considered to
be in the public domain.

 

LEI: 549300JK10TVQ3CCJQ89

- ends -

 1  (#_ftnref1) All equivalent figures assume the average gold/silver ratio
for 2022 of 83x.

 2  (#_ftnref2) Calculated as total number of accidents per million labour
hours

(( 3  (#_ftnref3) ))Calculated as total number of days lost per million labour
hours.

 4  (#_ftnref4) The ECO Score is an internally designed Key Performance
Indicator measuring environmental performance in one number and encompassing
numerous fronts including management of waste water, outcome of regulatory
inspections and sound environmental practices relating to water consumption
and the recycling of materials.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact
rns@lseg.com (mailto:rns@lseg.com)
 or visit
www.rns.com (http://www.rns.com/)
.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our
Privacy Policy (https://www.lseg.com/privacy-and-cookie-policy)
.   END  DRLKZLFLXDLBBBX

Recent news on Hochschild Mining

See all news